F urther to the Leader's decision on 22 November 2022, the Cabinet confirmed approval to dispose of the site known as 32, 34, 42, 56 and 58-60 Middle Street, Portsmouth to PVD1 Ltd, subject to the long leases currently in place in accordance with the schedule of interests attached in Appendix B.
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
1.1To seek the final approval of the Leader of the council as portfolio holder to dispose of the above properties shown on the plan at Appendix A, subject to the existing long leaseholds listed in Appendix B on the terms set out in the Heads of Terms in Appendix D (exempt).
Recommendations
2.1Further to the Leader's decision on 22 nd November 2022, the Cabinet is now asked to confirm approval to dispose of the site known as 32, 34, 42, 56 and 58- 60 Middle Street, Portsmouth to PVD1 Ltd, subject to the long leases currently in place in accordance with the schedule of interests attached in Appendix B.
Background
3.1Following a report to Cabinet on 22nd November 2022, officers have concluded negotiations and agreed terms as set out in the attached Heads of Terms document in Appendix D (exempt).
3.2On 22nd November 2022, the Leader and Members delegated authority to officers to enter into negotiations to agree terms to dispose of the properties described subject to final approval of terms. As such this report seeks to advise members of the terms agreed and to seek final approval to conclude the sale.
3.3The disposal will be subject to an Option Agreement exercisable on receipt of a successful planning consent by the purchaser.
1 www.portsmouth.gov.uk - Official -
3.4The developer owns the leasehold interest in four of the properties, having negotiated and acquired these from the previous leaseholders. The council has reviewed its own ability to acquire and deliver a housing scheme on this site and whilst policy compliant it is not considered viable and is not within the approved capital programme. The council would also need to negotiate the surrender of the current leasehold interests from the developer.
3.5The council's planning department did recommend council approve an application to redevelop the site to provide 163 residential units. Due to a legal technicality on ownership the developer was unable to satisfy the s.106 agreement, as such the developer withdrew the application (now showing status as dismissed).
Reasons for recommendations
4.1As mentioned in the 22nd November 2022 report the council will receive a capital sum as set out in the agreed Heads of Terms in Appendix D (exempt) subject to the developer securing a successful planning consent for the proposed scheme.
5. Integrated impact assessment
5.1See Appendix C.
Legal implications
6.1Under s.123 of the Local Government Act 1972 the council may dispose of any land in any manner it wishes provided it is for the best consideration that can reasonably be obtained. If the disposal is not for the best consideration then the consent of the Secretary of State will be required.
6.2However, Secretary of State consent to the disposal would be required where the Local Authority considered that the purpose for which the land is to be disposed is likely to contribute to the achievement of any one or more of the following objects in respect of the whole or any part of its area, or of all or any person resident or present in its area:
(i) the promotion or improvement of economic well being (ii) the promotion or improvement of social well being (iii) the promotion or improvement of environmental well being
6.3Property & Investment have confirmed that the council is obtaining the best consideration that can reasonably be obtained.
7. Director of Finance's comments
7.1The current income from the council's interest in this property is £264 per annum.
7.2The disposal will result in a capital receipt to the council exceeding the capital value of the existing interest.
2 www.portsmouth.gov.uk - Official -
……………………………………………… Signed by:
Appendices
Appendix A: Location Plan Appendix B: Schedule of interests Appendix C: Integrated Impact Assessment Appendix D: Heads of Terms (Exempt) Appendix E: Cabinet Report 22/11/2022
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.