Local Electric Vehicle Infrastructure (LEVI) Programme
ApprovedCommittee3 papers
AI summaryPortsmouth's Transport Cabinet Member has authorised procurement of a delivery partner for the LEVI electric vehicle chargepoint programme, backed by £3.682 million of government funding. The contract is expected to be awarded in September 2026, with 1,420 sockets to be installed over five years.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedAssistant Director of Transport authorised to proceed
Money£3.682 million LEVI fund awardPlus £187,780 annual capability grant
What happens nextContract award on 11 September 2026Subject to OZEV approval
Who it affectsResidents without off-street parkingEquitable access to EV charging
What was decided
The Cabinet Member for Transport granted delegated authority to the Assistant Director of Transport to seek formal approval from the Office for Zero Emission Vehicles and, subject to that approval, to run the procurement and appoint a delivery partner. Report 2.1
The Cabinet Member noted the delivery strategy, commercial model and procurement timeline set out in the report, which includes an open book concession contract of 15+1 years. Report 2.2, 4.8
A 'For Information' report will come back to the Cabinet Member once the procurement process has been completed. Report 2.3, 7.4
Why
The ZEV mandate requires 80% of new cars and 70% of new vans to be zero emission by 2030, and 100% by 2035, making public charging essential. Report 3.4, 6.1
Lessons from the earlier ORCS scheme showed lamp column chargers offer limited speed and scalability, and previous Traffic Regulation Orders met with resident resistance, prompting a shift to standalone, DNO connected chargers and a data-led TRO approach. Report 4.1, 6.1, P65
Preliminary Market Engagement with 10 suppliers confirmed strong appetite for a concession model that could leverage up to 80% private investment, reducing the council's financial exposure. Report 4.6, 6.1, P66
What happens next
The council will finalise the draft Invitation to Tender and submit it to OZEV for review, then publish the Tender Notice on the Find a Tender Service on 6 April 2026. Report 7.1, P70, 5.4, P63
Tenders are due back by 1 June 2026, with evaluation completed by 6 July 2026 and contract award on 11 September 2026, followed by mobilisation in Autumn 2026 and implementation starting in Early 2027. Report P63, 7.1
The council will bring a 'look back/forward direction of travel' report on EV infrastructure and, subject to outcomes, a refresh of the Electric Vehicle Infrastructure Strategy in 2027. Report 4.13
The money
£3.682 million LEVI fund award from the Department for Transport for EV chargepoints Report 3.5
£3,682,000 LEVI fund award, confirmed in Director of Finance comments Report 10.1
£3.52 million Earmarked for low power on-street charging infrastructure Report 3.5
£182k Reserved for potential trials of alternative EV charging solutions Report 3.5
£75,000 Annual fixed management fee paid by delivery partner, indexed by CPI Report 4.8, 10.5
5-15% Gross margin revenue share once revenue exceeds the fixed fee threshold Report 4.8, 10.5
£187,780 Annual LEVI capability grant funding internal council resource costs Report 10.6
Options considered
Chosen: Adopt an open book concession model with a delivery partner under the LEVI programme, prioritising standalone DNO connected 7-22kW chargers. Aligns with national and local EV strategies, leverages private investment, and addresses lessons from the earlier ORCS scheme Report 4.8, 6.1
Rejected: Continue reliance on lamp column chargers as used under ORCS. ORCS showed lamp column chargers have limited charging speeds, poor scalability and no enduring asset value for the council Report 6.1, P65
Implications
Financial: All servicing, repair and maintenance liability sits with the operator, limiting the council's exposure to future operating costs; the council instead receives a fixed fee plus a 5-15% gross margin revenue share. Report 10.4, 10.5
Legal: The procurement will be run as an Open Procedure under Section 20 of the Procurement Act 2023, with the contract treated as a Concession Contract under Section 8, giving greater flexibility in contract management. Report 5.1, 5.2, 5.3
Equalities: An Integrated Impact Assessment found overwhelmingly positive impacts for residents without off-street parking, with no significant negative effects on protected characteristic groups, and compliance with PAS 1899 accessibility standards. Report 8.1, 8.2, 8.3
Climate: The programme supports Portsmouth's Air Quality Local Plan and Climate Emergency Declaration by enabling the decarbonisation of transport and accelerating EV adoption. Report 3.4, P15, 8.4
Risk: Under the concession model, the operator takes demand risk, while the council holds a margin cap to protect affordability; final approval of all sites remains with the council. Report 4.8, P39
Other: The council will keep members informed through regular Cabinet Member briefings at key milestones and quarterly progress reports. Report 7.2
Who and where
Residents without off-street parking in Portsmouth, who are prioritised under the scheme Report 3.3, 4.11
Existing and future electric vehicle drivers in the city, as the public chargepoint network expands from 147 sockets in 2025 towards 734 by 2030 Report 4.5, P27, P31
Chargepoint operators and suppliers participating in the concession procurement, including the 10 suppliers involved in Preliminary Market Engagement Report 4.6, 5.6
Portsmouth City Council's Electric Vehicle Infrastructure team, funded through the management fee and capability grant Report 10.5, 10.6
Timeline
6th April 2026: Tender Notice published on Find a Tender Service and procurement documents made available on In-tend Report P63
1st June 2026: Tender return deadline Report P63
w/c 15th June 2026: Presentations and interviews with bidders Report P63
6th July 2026: Evaluation of tenders completed and recommendation submitted to OZEV for approval Report P63
31st August 2026: Assessment summaries issued and contract award notice published on Find a Tender Service Report P63
1st - 10th September 2026: Standstill period Report P63
11th September 2026: Contract award Report P63
Autumn 2026: Mobilisation and planning Report P63
Early 2027: Start of implementation, with at least 200 sockets to be delivered in Year 1 Report P63, 4.8
Over five year installation period: Minimum of 1,420 sockets to be delivered under the concession Report 4.8, P36
Plain English for the jargon
LEVI: Local Electric Vehicle Infrastructure, a national programme run by the Office for Zero Emission Vehicles (OZEV) to fund local EV charging, particularly for residents without off-street parking.
OZEV: Office for Zero Emission Vehicles, the government body that must approve the council's procurement documents and the use of the grant.
ITT: Invitation to Tender, the formal document issued to suppliers to bid for the concession contract.
TRO: Traffic Regulation Order, a legal order used to control traffic and parking; under the LEVI approach TROs will only be introduced where data evidences persistent bay blocking.
DNO: Distribution Network Operator, the company that manages the local electricity grid and provides new power connections for infrastructure.
PME: Preliminary Market Engagement, an open process used by the council to test supplier interest and refine the procurement before issuing the ITT.
CPO: Charge Point Operator, the private sector delivery partner to be appointed under the concession contract.
ZEV: Zero Emission Vehicle, the national mandate requires 80% of new cars and 70% of new vans sold to be zero emission by 2030 and 100% by 2035.
PAS 1899: British Standard for accessible electric vehicle charging, which the scheme will comply with.
NEVIS: National EV Insight and Support, the source of updated demand projections cited in the report.
ORCS: On-Street Residential Chargepoint Scheme, the earlier national programme under which Portsmouth installed over 300 lamp column chargers.
FTS: Find a Tender Service, the UK Government portal where public procurement notices are published.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10
Resolved
DECISION The Cabinet Member for Transport: 1. Granted delegated authority to the Assistant Director of Transport to proceed with seeking formal approval from OZEV to commence the LEVI procurement process and subject to OZEV approval, undertaking the procurement process, including issuing the ITT and appointing a delivery partner in accordance with the approach set out in the report. 2. Noted the delivery strategy, commercial model, and procurement timeline outlined in section 3-4 of the report. 3. Noted that a 'For Information' report would be brought back to the Cabinet Member once the procurement process had been completed.
Word for word from the decision Portsmouth published for this meeting.Source: democracy.portsmouth.gov.uk
1.1To seek delegated authority for Portsmouth City Council (PCC) to proceed with the procurement of a delivery partner for the Local Electric Vehicle Infrastructure (LEVI) programme. As required under LEVI fund conditions, approval to proceed to procurement must also be subsequently sought from the Office for Zero Emission Vehicles (OZEV). This report sets out:
• The scope and objectives of the LEVI project, including the minimum delivery targets, technology standards, Traffic Regulation Order (TRO) strategy, and commercial model. • The delivery approach, informed by updated projections, lessons learned from previous phases, and Preliminary Market Engagement (PME) with suppliers. • The procurement timeline and governance arrangements required to issue the Invitation to Tender (ITT) and appoint a concessionaire. • The rationale for this approach, ensuring alignment with LEVI fund objectives, Portsmouth’s adopted Electric Vehicle Infrastructure Strategy, and national policy commitments to accelerate electric vehicle (EV) adoption.
1.2Approval of this report will enable PCC to move forward ensuring timely delivery of high quality, future proof EV infrastructure for residents without off street parking.
Recommendations
It is recommended that the Cabinet Member for Transport: 1 www.portsmouth.gov.uk - Official -
2.1Grants delegated authority to the Assistant Director Transport to proceed with seeking formal approval from OZEV to commence the LEVI procurement process and subject to OZEV approval, undertaking the procurement process, including issuing the ITT and appointing a delivery partner in accordance with the approach set out in this report;
2.2Notes the delivery strategy, commercial model, and procurement timeline outline in section 3-4 of this report.
2.3Notes that a ‘For Information’ report will be brought back to the Cabinet Member once the procurement process has been completed.
Background
3.1The LEVI fund is a national programme administered by the Office for Zero Emission Vehicles (OZEV) to accelerate the rollout of local EV charging infrastructure, particularly for residents without off street parking. It builds on the earlier On Street Residential Chargepoint Scheme (ORCS) and aims to deliver a step change in deployment, moving from small scale pilots to commercially sustainable networks.
3.2LEVI funding supports local authorities to plan, procure, and deliver high quality, future proof infrastructure through partnerships with the private sector, leveraging significant private investment alongside public funding.
3.3LEVI expects local authorities to: • Develop a robust delivery strategy aligned with national policy and local transport plans. • Prioritise equitable access for residents without off street parking. • Ensure infrastructure is future proof, reliable, and scalable. • Adopt commercial models that attract private investment and minimise public cost. • Deliver against KPIs for availability, maintenance, and user experience.
3.4LEVI delivery supports:
• National Policy Framework: o Taking Charge: The Electric Vehicle Infrastructure Strategy (HM Government)1: sets out the vision for a comprehensive UK charging network.
1 Taking charge: the electric vehicle infrastructure strategy
2 www.portsmouth.gov.uk - Official -
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Residents Parking Zones Future ProgrammeDECISION The Cabinet Member for Transport: 1. Approved progressing the RPZs Future Programme for proposed new zones a...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.