Somers Orchard Project - Delivering Phase 1 (Block C)

Noted Executive 2 papers

AI summaryPortsmouth Cabinet notes plan to deliver Phase 1 of Somers Orchard: 175 council homes in Block C, on site expected summer 2027.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedReport for information, not subject to call-in
MoneyNot statedInformation-only report carries no finance comments
What happens nextTender for Block C design and build. Two-stage procurement under existing delegations
Who it affectsSomerstown residents and future tenants175 council homes at social rent on former tower block sites

What was decided

Cabinet noted the report, which is for information only and is not subject to call-in. Report P10

The council will directly deliver Phase 1, Block C, using the Housing Revenue Account, held and managed by Portsmouth Homes at social rent. Report 5.3, 12.6

Work will begin to discharge pre-commencement conditions for planning consent 23/01574/FUL, with on-site start expected in summer 2027. Report 4.4, 4.5

Why

Block C is now considered financially viable after value engineering, revised phasing, and a review of funding mechanisms, enabling the first phase of direct delivery. Report 3.5, 3.6, 9.1, 9.2

The project had been rendered unviable by market volatility, rising construction costs, higher interest rates and supply chain pressures, requiring a comprehensive review of delivery options. Report 3.4, 3.5

The scheme prioritises social and affordable housing in line with the council's corporate priorities and housing strategies. Report 3.3, 6.1

What happens next

Procurement will follow a two-stage route with a Guaranteed Maximum Price, via advertised tender or framework call-off, under existing delegations to the Director of Housing, Neighbourhood and Building Services and the Section 151 Officer. Report 9.7, 10.4, 10.5, 10.9, 10.10

The community panel will be re-engaged and meet monthly with the project team and design team, including a 'meet the contractor' event after appointment. Report 7.3, 7.5, 11.7

Further viability and delivery work on Blocks A, B and D will continue, with partner agencies such as MHCLG and Homes England, including possible sale or long leasehold disposal of remaining sites. Report 6.3, 6.4, 6.5, 6.6

Options considered

  • Chosen: Two-stage procurement with Guaranteed Maximum Price (advertised tender or framework call-off). Contractors' clear preference; supports cost control, buildability and early contractor involvement Report 10.4, 10.5
  • Rejected: Commence Build to Rent Unit (Block B) under consent 23/01575/FUL within this phase. Further work required to assess delivery routes and funding options Report 4.6
  • Rejected: Undertake associated highway and traffic management works (Melbourne Place, Wiltshire, Waltham Street, Meriden Road, Earlsdon Street, Sackville Street) in this phase. Not required for delivery of Block C Report 5.6, P44

Implications

  • Legal: Planning consents 23/01574/FUL and 23/01575/FUL were approved at committee in August 2024 and the legal agreements were finalised and sealed in December 2025; works must commence within three years of the 2 December 2025 permission dates. Report 4.1, 4.2, 4.3
  • Legal: Design and build works must follow public procurement regulations as they meet the relevant threshold; the council relies on section 9 of the Housing Act 1985 to provide housing on this land. Report 12.6, 12.7
  • Legal: A Right to Light assessment has been undertaken and further specialist advice will be procured for the tender stage; an existing licence for part of Wiltshire Street car-park will end before the estimated start on site. Report 12.3, 12.4
  • Financial: Financial viability depends on long-term PWLB borrowing rates and the availability of the HRA discount rate; viability will continue to be tested at each procurement stage. Report 9.5, 9.6
  • Risk: Market interest in preliminary engagement was limited, with three compliant expressions of interest and two completing the process, though those who engaged had relevant experience and capacity. Report 10.2, 10.6
  • Climate: Block C homes are designed to meet the best achievable energy performance certification within budgeted construction costs, with the design to be future-proofed against emerging regulations. Report 5.7
  • Equalities: 29 of the 175 homes will be fully accessible to M4(3) standards, and the scheme will deliver a publicly accessible changing places toilet and secure communal courtyard gardens. Report 5.3, 5.2, 5.5

Who and where

  • Future residents of the 175 council homes in Block C, including general needs and supported housing tenants of Portsmouth Homes Report 5.3
  • Residents of Somerstown and the wider Somers Orchard community, including the community panel and users of the community garden Report 3.3, 7.1, 8.3
  • Users of the Wiltshire Street car-park, which will be demolished to enable Phase 1 infrastructure Report 5.6
  • Portsmouth City Council as direct developer and landlord via the Housing Revenue Account Report 5.3, 12.6

Timeline

  • August 2024: Planning consents for Blocks A, C and D (23/01574/FUL) and Block B (23/01575/FUL) approved at committee, subject to conditions and legal agreements Report 4.1
  • January 2025: Preliminary Market Engagement exercise started Report 10.1
  • October 2025: Preliminary Market Engagement concluded Report 10.4
  • 2 December 2025: Decision notices for both planning applications issued and legal agreements sealed Report 4.2, 4.3
  • Spring 2026: Sunflower competition and small garden-based events planned at the community garden Report 8.5
  • Summer 2027: Expected commencement of physical works on site for consent 23/01574/FUL (Block C) Report 4.5

Plain English for the jargon

  • HRA: Housing Revenue Account, the ring-fenced account local authorities use for income and spending on council-owned housing
  • M4(3): Building regulation standard for dwellings accessible to wheelchair users
  • PWLB: Public Works Loan Board, a government body that lends money to local authorities
  • MHCLG: Ministry of Housing, Communities and Local Government
  • PME: Preliminary Market Engagement, early market sounding exercise before formal procurement
  • Large panel system tower blocks: High-rise residential buildings constructed using prefabricated concrete panel systems, some of which have failed fire safety standards
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

Noted the report which is for information and is not subject to call-in.
Word for word from the decision Portsmouth published for this meeting. Source: democracy.portsmouth.gov.uk

Follow this further

Built from Portsmouth's papers

What the report saysPro

Report to Cabinet

Background

3.1The Somers Orchard development sits on the sites of the former council owned tower blocks Horatia House and Leamington House, Somerstown.

3.2The development opportunity arose from the requirement to deconstruct two large panel system tower blocks due to the need to meet regulatory fire, building safety and compliance standards. This created the potential for a comprehensive regeneration of the site.

3.3A masterplan for the development was prepared following engagement with the local community, and the administration established clear expectations to deliver a scheme prioritising social and affordable housing, in alignment with the Council’s corporate priorities and housing strategies.

3.4The development, like many others locally and nationally, was adversely affected by national and international financial market volatility, rising construction costs, increased interest rates, inflationary pressures, and supply chain disruptions. These combined factors significantly impacted development appraisals, rendering the scheme financially unviable under the prevailing economic conditions.

3.5In response, the Council has undertaken a comprehensive review of delivery options, including revised phasing, value engineering, and alternative funding mechanisms, whilst maintaining a strong emphasis on securing some direct delivery to retain control and ensure alignment with the councils corporate strategy and priorities to deliver affordable homes to the city.

3.6This move towards financial viability for Block C unlocks the first phase of direct delivery for the Somers Orchard masterplan, providing essential council owned affordable housing.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Planning decision noticeAppendix 1 359 KB Download
PDF
Somers Orchard Project: Delivering Phase 1 (Block C)Report 1.1 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 10 attended
SP
Councillor Steve PittChair, present
DS
Councillor Darren SandersVice-Chair, present
DA
Councillor Dave AshmoreCabinet Member, present
CA
Councillor Chris AttwellCabinet Member, present
KB
Councillor Kimberly BarrettCabinet Member, present
PC
Councillor Peter CandlishCabinet Member, present
ND
Councillor Nicholas DorringtonCabinet Member, present
LH
Councillor Lee HuntCabinet Member, present
HM
Councillor Hugh MasonCabinet Member, present
MW
Councillor Matthew WinningtonCabinet Member, present

More from Portsmouth Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Housing & Social Care Scrutiny Panel review "Portsmouth Homes' compliance with the Transparency, Influence & Accountability Standard (Part of the Consumer Standards) - Response reportThanked the Housing and Social Care Scrutiny Panel for its work in undertaking the review and for the report; and 2. ... Noted Open
22 Sep 2026 Publicising Fly Tipping & Environmental Crime Cases PolicyApproved and adopted the Publicising Fly Tipping and Environmental Crime Cases Policy effective from 23 September 202... Approved Open
21 Jul 2026 Carbon Action PlansNoted the report which is for information and is not subject to call-in. Noted Open
21 Jul 2026 Education, Children & Young People Scrutiny Panel review "Increasing accessibility in Portsmouth's play parks" - Response reportThanked the panel for its work in undertaking the review. 2. Noted and considered the conclusions and recommendations... Noted Open
21 Jul 2026 Treasury Management Outturn Report 2025/2026Noted the actual prudential and treasury management indicators based on the unaudited accounts, as shown in Appendix ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies