Portsmouth City Council
Planning Committee, Wednesday 19 August 2026 at 10.30am

26/00579/LBC - Long Curtain Moat to Eastney Marine Barracks

Decided Planning 1 paper

AI summaryPortsmouth Planning Committee grants conditional listed building consent to remove and reposition 16 Grade II listed lamp columns along the seafront from Long Curtain Moat to Eastney Marine Barracks.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedFor 16 Grade II listed seafront lamp columns
MoneyNot stated
What happens nextMethod Statement required before works beginWorks must start within 3 years of consent
Who it affects16 Grade II listed seafront lamp columnsStretching from Long Curtain Moat to Eastney Marine Barracks

What was decided

Conditional listed building consent was granted for the removal and repositioning of 16 Grade II listed lamp columns along the seafront. Report P1

Three conditions were imposed, covering a three year time limit for starting works, adherence to the approved drawings, and submission of a Method Statement for the dismantling, repair, storage and re-instatement of the columns. Report P2, P3, P5, P9, P10

Why

The conditions are needed to preserve the special architectural and historic interest of the Grade II listed lamp columns. Report P11

The decision reflects policy PCS23 of the Portsmouth Plan (2012) and the aims of the revised National Planning Policy Framework (2024). Report P11

A three year time limit is required to comply with Section 18 of the Planning (Listed Buildings and Conservation Areas) Act 1990. Report P4

What happens next

A Method Statement based on the Heritage Impact Assessment dated 5/7/19, Issue 6, must be submitted to and approved in writing by the Local Planning Authority before any works take place. Report P9

Works must be carried out in full accordance with the approved Method Statement and the listed drawings. Report P5, P6, P7, P10

The development must begin before the expiration of three years from the date of this consent. Report P3

Options considered

  • Chosen: Grant conditional listed building consent. Recommended by officers subject to conditions to protect the historic interest of the Grade II listed lamp columns. Report P1, P2, P11

Implications

  • Legal: Consent must be begun within three years to comply with Section 18 of the Planning (Listed Buildings and Conservation Areas) Act 1990. Report P3, P4
  • Other: The Method Statement must cover recording, labelling, dismantling, repair or refurbishment, storage and re-instatement, in order to preserve the special interest of the listed structures. Report P9, P10, P11

Who and where

  • 16 Grade II listed lamp columns along the Portsmouth seafront between Long Curtain Moat and Eastney Marine Barracks Report P9, P11
  • Users and visitors to the seafront area covered by the application Report P7

Timeline

  • Within 3 years of the date of consent: Development to which the consent relates must be begun. Report P3
  • Before any removal or re-positioning works take place: A Method Statement must be submitted to and approved in writing by the Local Planning Authority. Report P9

Plain English for the jargon

  • Listed Building Consent: Permission required from the local planning authority to alter, extend or demolish a listed building.
  • Grade II Listed: A category of listed building in England judged to be of special interest, warranting preservation.
  • NPPF: The National Planning Policy Framework, the government's planning policy guidance for England.
  • Heritage Impact Assessment: A document assessing the effect of proposed works on the historic interest of a heritage asset.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item93

Resolved

RESOLVED that conditional Listed Building Consent be granted.
Word for word from the decision Portsmouth published for this meeting. Source: democracy.portsmouth.gov.uk

Follow this further

Built from Portsmouth's papers

What the report saysPro

Report to Planning Committee

26/00579/LBC WARD: EASTNEY & CRANESWATER

SOUTHSEA SEAFRONT FROM LONG CURTAIN MOAT IN THE WEST TO EASTNEY MARINE BARRACKS IN THE EAST.

REMOVAL AND RE POSITIONING OF 16 NO. GRADE II LISTED LAMP COLUMNS ALONG THE SEAFRONT

Application Submitted By: Portsmouth City Council

On behalf of: Portsmouth City Council Coastal Partners, on behalf of Portsmouth City Council

RDD: 8th May 2026 LDD: 6th July 2026

1.0SUMMARY OF MAIN ISSUES

1.1This application is brought to the Planning Committee as it is a Listed Building Consent application accompanying the application to vary Condition 1 of Planning Permission 25/00910/VOC (App. Ref. 26/00578/VOC, also on this agenda).

1.2The determining issue is whether the proposed works to remove and relocate the listed lamp columns would preserve their special architectural or historic interest.

2.0SITE AND SURROUNDINGS

2.1The Southsea Coastal Scheme is a Flood and Coastal Erosion Management Scheme that stretches 4.5km along the southern edge of Portsea Island. The scheme extends from Royal Garrison Church in the west (NGR SZ 63126 99156) to Eastney Barracks in the east (NGR SZ 67077 98784) and is split into seven sub-frontages.

2.2Sub Frontage 6 comprises a 1065 metre section from just east of South Parade Pier to the Coffee Cup, Eastney as shown on the location plan extracts below:

Figure 1- Application site in the context of the wider scheme Figure 2 - Application site location

2.3Planning consent was originally granted for the full scheme in December 2019 (19/01097/FUL) along with a Marine Licence (L/2020/00121/2) and Environmental Impact Assessment consent. A new planning decision was then issued in August 2021 (21/00820/VOC) under Section 73 of the Town and Country Planning Act 1990, granting minor amendments to sub-frontage 4; in April 2023 (22/01720/VOC) for minor amendments to sub-frontage 5 west (The Pyramids Centre to Speakers Corner); in October 2023 (23/00896/VOC) for minor amendments to sub-frontage 3; and in December 2024 for minor amendments to sub-frontage 2 (24/00987/VOC). A new separate application was also approved in December 2024 for Sub-frontage 2 where the proposal extends outside of the original red line planning boundary (24/00989/FUL). An updated Marine Licence was issued by the Marine Management Organisation (MMO) in April 2024 for minor amendments to sub-frontage 3 (Ref: L/2020/00121/4). A variation to the marine licence was submitted in April 2025 to account for an extension to an existing inlet/outlet pipe at Canoe Lake. A full planning history for the scheme can be found in Appendix B of the submitted Planning, Design and Access Statement.

2.4The Southsea Coastal Scheme is currently under construction and is being delivered in phases. Construction is complete at Sub-frontage 1 (Long Curtain Moat), Sub-frontage 4 (Southsea Castle) and Sub-frontage 5 west (Pyramids to Speakers Corner). Sub- frontage 3 (Southsea Common) is currently under construction and is due for completion in summer 2026.

3.0PROPOSAL

3.1Listed Building Consent is sought for the removal and re-positioning of 16 Grade II listed lamp columns along the seafront. These will be relocated as close to their existing position as possible. Modern lighting columns will placed at regular intervals between the historic columns in order to provide the appropriate lighting levels.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
26/00579/LBC: Long Curtain Moat to Eastney Marine BarracksReport 498 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 16 attended
SH
Councillor Suzy HortonChair, present
MV
Councillor Mary VallelyVice-Chair, present
MC
Councillor Matthew CordyCommittee Member, present
LH
Councillor Lee HuntCommittee Member, present
CI
Councillor Carl InmanCommittee Member, present
HM
Councillor Hugh MasonCommittee Member, apologies, sent representative
DP
Councillor Denise PerryCommittee Member, present
JS
Councillor Joe StandenCommittee Member, present
GV
Councillor Gerald Vernon-Jackson CBECommittee Member, present
CA
Councillor Chris AttwellStanding Deputy, present as substitute
LW
Lisa WebberCouncil Staff, expected
JG
Juliet GillOfficer, expected

All 16 on the meeting page

More from Portsmouth Planning Committee

All decisions
MeetingDecisionOutcome
19 Aug 2026 Minutes of the previous meetingRESOLVED that the minutes of the meeting held on 29 July 2026 be agreed as a correct record. The Supplementary Matter... Agreed Open
19 Aug 2026 26/00439/FUL - 92 Gladys Avenue, Portsmouth, PO2 9BHRESOLVED that the application be refused for the following reasons - the proposal would breach policy PCS20 in that t... Refused Open
19 Aug 2026 26/00648/FUL - 72 Ophir Road, Portsmouth, PO2 9ENRESOLVED that 1. Delegated authority be granted to the Assistant Director of Planning & Economic Growth to Grant Cond... Agreed Open
19 Aug 2026 25/01506/FUL - 68 Montgomerie Road, Southsea, PO5 1EDRESOLVED that the application be refused for the following reasons - the proposal would constitute over-intensificati... Refused Open
27 Apr 2021 Minutes from the previous meeting - 30 March 2021RESOLVED that the minutes of the Planning Committee held on 30 March 2021 be approved as a correct record . Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies