Transport Consultancy Services - Procurement of New Contract
NotedPlanning1 paper
Strategic Environment, Planning and Transport Committee noted this item on Wednesday 21 November 2018. Below is the council's own wording, with the papers it was decided on.
Resolved – (1) That the existing Transport Consultancy Services Term Contract would expire on 31 August 2019, be noted; (2) That the procurement approach and anticipated timeframe for securing a new Transport Consultancy Services Term Contract be noted; (3) That the Director of Environment and Neighbourhood Services, in consultation with the Lead Councillor for Strategic Environment, Planning and Transport, the Head of Legal and Democratic Services and the Head of Finance, be delegated authority to award the new Transport Consultancy Services Term Contract upon completion of the procurement process. (The meeting started at 6.30pm and closed at 8.28pm)
Word for word from the decision Reading published for this meeting.Source: democracy.reading.gov.uk
JOB TITLE: ACTING TRANSPORT E-MAIL: [email removed].u PLANNING MANAGER k
1. PURPOSE OF REPORT AND EXECUTIVE SUMMARY
1.1This report highlights the end of the existing Transport Consultancy Services Term Contract with Peter Brett Associates, on 31st August 2019, and sets out the recommended procurement approach for a new Transport Consultancy Services Term Contract.
2. RECOMMENDED ACTION
2.1To note the existing Transport Consultancy Services Term Contract will expire on 31st August 2019.
2.2To note the procurement approach and anticipated timeframe for securing a new Transport Consultancy Services Term Contract.
2.3That delegated authority is given to the Director of Environment and Neighbourhood Services in consultation with the Lead Councillor for Strategic Environment, Planning and Transport, the Head of Legal & Democratic Services and the Head of Finance to award the new Transport Consultancy Services Term Contract upon completion of the procurement process.
3. POLICY CONTEXT
3.1To secure the most effective use of resources in the delivery of high quality, best value public service.
4. THE PROPOSAL
4.1The Transport Consultancy Services Contract with Peter Brett Associates, which is due to expire on 31st August 2019, provides valuable support and expertise in developing and delivering our Local Transport Plan. The existing consultancy contract allows us to call on expertise not available from within the Council and to respond to peaks in workload and funding availability. 4.2 There continues to be a demand for specialist support and advice on a range of transport matters to enable the Council to fulfil its role and responsibilities as Local Highway Authority, as detailed in national legislation.
4.3As with the existing Term Contract, the Contractor will be expected to assist in all aspects of transport planning and other supporting functions including offering advice on wider highway and network management functions, such as, but not limited to, flooding and drainage, bridges and structures and traffic signal design.
4.4It is now proposed that a new Transport Consultancy Services Term Contract is procured to ensure service continuity and a smooth transition between Contracts. It is recommended that the new contract is procured via a two-stage tendering process to ensure the Council is able to continue demonstrating best value for money and allow the Council and Contractor sufficient time to develop a successful partnership approach in the delivery of our transport strategy.
4.5However, it should be noted that procurement frameworks could continue to be considered for individual projects as required, as is currently the case with the Green Park Station scheme and the production of Concessionary Bus Passes.
4.6The anticipated timeframe for procuring a new Transport Consultancy Services Contract is:
Issue Pre-Qualification Questionnaire (PQQ) – January 2019 Shortlisting – February 2019 Issue Invitation to Tender (ITT) – March 2019 Tender evaluation – April 2019 Recommendation to appoint – May 2019 Mobilisation period commences – June 2019 New Contract commences – Sept 2019
4.7Whilst ‘do nothing’ is a potential option, the Council relies on the additional resource available through the Term Contract and wider expertise to support the development and delivery of transport schemes. Without this additional support the Council would be unable to develop and deliver major transport schemes, respond to external funding opportunities or overcome issues requiring specific technical expertise.
5. CONTRIBUTION TO STRATEGIC AIMS
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategic Environment, Planning and Transport Committee at Reading and we tell you when its next papers are published, before the meeting rather than after it.
Strategic Transport Schemes UpdateResolved – (1) That the progress made towards the delivery of the current programme of strategic transport schemes, a...
Strategic Transport Schemes UpdateResolved - (1) That the progress made towards the delivery of the current programme of strategic transport schemes, a...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.