EMPLOYMENT AND SKILLS PLANS - ANNUAL PROGRESS REPORT
NotedPlanning1 paper
Strategic Environment, Planning and Transport Committee noted this item on Tuesday 9 July 2019. Below is the council's own wording, with the papers it was decided on.
Resolved – (1) That the ongoing delivery of employment and skills outcomes, as enabled by Section 106 Employment and Skills Plans, be noted and welcomed ; (2) That the benefits of the delivery of employment and skills outcomes to the local economy and in particular to local residents by assisting residents to find good quality, permanent employment within the Borough be noted and welcomed.
Word for word from the decision Reading published for this meeting.Source: democracy.reading.gov.uk
Report to Strategic Environment, Planning and Transport Committee
Executive summary
1.1This report updates the Committee on progress with the implementation of planning policies concerned with promoting Employment and Skills Plans.
1.2Through engagement and contributions from developers, and the end users of completed developments, appropriate skills development and employment opportunities have been undertaken to assist the local economy and local residents. The report sets out both the successes gained through the delivery of plans, working mainly with the construction industry, the various employment projects delivered using financial contributions and the schedule for Year 2 of the programme delivery.
2. Recommended Actions
2.1That the Committee note the report and welcome the ongoing delivery of employment and skills outcomes as enabled by Section 106 Employment and Skills Plans. 2.2 That the Committee note the benefits of this delivery to the local economy and in particular to local residents by assisting residents to find good quality, permanent employment within the Borough.
3. BACKGROUND - DELIVERY OF PLANS BY INVESTOR DEVELOPERS
3.1Reading Borough Council adopted the requirement for Employment and Skills Plans (ESP) under a 2013 Supplementary Planning Document that seeks to implement adopted (2008) Core Strategy Policies CS9: Infrastructure, Services, Resources and Amenities, and CS13: Impact of Employment Development. The drafting of the SPD relied on detailed discussion between Reading UK and the Borough Council Planning Service, with Reading UK being identified as the main agent for implementing the policy. The aims of the ESP requirement as part of a planning permission have been clearly defined in working with employers to improve the work and training opportunities of local people.
3.2An ESP requirement is attached to any new development or any regeneration or extension programme where more than 1,000 square metres of new non- residential floor space or 10 dwellings are being created, or costing more than £1million.
3.3In simple terms the developer can choose to either enter into a delivery plan, through Reading UK and working with local partners, or to pay a financial contribution towards the delivery of training and employment programmes. The financial contribution is based on a simple percentage of the anticipated construction costs, and will be confirmed by a S106 legal agreement which is entered into by the developer before planning permission is granted.
3.4To date (June 2019) 25 developers have chosen to pay financial contributions (ranging from £1,600 to £178,000) and a total of 45 plans (both construction and end use) have either been delivered, or are in the process of being delivered.
3.5Reading UK, through the Economic Development Manager and other partners, work closely with the developers to create an employment plan that is both deliverable with clear outcomes and shaped to the needs of the relevant sector.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategic Environment, Planning and Transport Committee at Reading and we tell you when its next papers are published, before the meeting rather than after it.
Strategic Transport Schemes UpdateResolved – (1) That the progress made towards the delivery of the current programme of strategic transport schemes, a...
Strategic Transport Schemes UpdateResolved - (1) That the progress made towards the delivery of the current programme of strategic transport schemes, a...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.