Item4
Resolved
It was agreed that Planning would confirm that cycle parking requirements would continue to be developed in detail. JP informed members that the AAP was submitted to the Secretary of State in September 2010 who was undertaking an examination of the plan and the adoption of the plan was scheduled for Summer 2011. John Pearce informed members that he would speak to the appropriate person in order to investigate the possibility of turning a disused tunnel that runs parallel to the Liverpool Street rail line to a cycle route. [name removed] asked that a picture of the Seven Kings Water Cycle Route be provided. The Chairman informed all members o f the group to liaise with Rogan Keown on ways to go forward with regards to the Cycling Strategy document. CE requested that cycle parking on platforms be taken up with Network Rail in addition to the provision of stairway gutters to assist cyclists to gain access to the parking areas.
Word for word from the decision Redbridge published for this meeting.
Source: moderngov.redbridge.gov.uk