That (i) the update and implementation progress of red risk recommendations be noted; and (ii) the following information be sent to Members of the Committee: (a) a summary of details relating to agency workers and consultants employed by the Council; and (b) the Briefing Note presented to Members of the former Audit Committee on the new Audit Structure and the number of audit days.
Word for word from the decision Redbridge published for this meeting.Source: moderngov.redbridge.gov.uk
1.1This report sets out the Internal Audit and Counter Fraud update including the progress made by management in implementing red risk recommendations relating to audit reviews completed to the end of April 2017.
Recommendation
That the Governance & Assurance Committee:
2.1Note the update and implementation progress of red risk recommendations.
3.1Internal audit recommendations are categorised as red, amber or green risk depending upon the impact of the associated risk attached to the recommendation. Where a recommendation is considered to address a “major weakness with material loss, error, fraud, inability to comply with laws, regulations and internal policies or procedures, or significantly impede service delivery” it is considered to be red risk and categorised accordingly.
3.2As part of its remit to monitor remedial action being taking to rectify significant control weaknesses, the Governance & Assurance Committee receives at each meeting a report setting out progress being made by service areas to implement red risk recommendations and any audit reviews where a ‘nil’ assurance is given. This report details the progress that management have made up to the end of April 2017.
3.3Management are expected to implement all red risk recommendations within the agreed target dates. Internal Audit tracks management progress by way of a chase up or follow up to the audit client accordingly. School audit recommendations are followed up annually as part of the school audit programme, starting in the autumn of each year. Slippage in implementing agreed actions does occur and requires management to instigate revised targets and consider ways to mitigate the identified risks.
4. Escalation Process
4.1In respect of red risk recommendations, the escalation process is as follows:-
Individual recommendations are chased up with the service areas in advance of each Governance & Assurance Committee meeting and updates are provided for directorate management team meetings. Internal Audit now verifies and provides assurance that recommendations are implemented before removing them from the tracker, rather than relying on management assurance. The Council’s Management Team review the tracker each quarter, enabling directors to check progress and call for action with recommendations relating to their directorate.
5. Management’s progress in implementing Red Risk recommendations
5.1During the current financial year 6 new red risk recommendations have been made (arising from 2 reviews) and these have been added to Appendix 1. Appendix 2 shows those recommendations which have been implemented and removed from the tracker at Appendix 1.
5.2In summary, during the month of April 2017 the movement in red risk recommendations is as follows:
Number Red risks as at 31 March 2017 37 New red risks added in the financial year 6 Less: Red risks implemented during the (5) financial year Red risks as at 30 April 2017 38 5.3 At the end of April 2017, there are 34 red risk recommendations outstanding relating to 20 reviews. For each of these reviews, management have responded and returned a completed management action plan. The action plans, where appropriate, have indicated where red risk recommendations have been actioned/in progress or are not yet due to be implemented. Of these, 21 have now passed the implementation date given by management and these are shown as greyed out recommendations in Appendix A. Continuous dialogue with management is taking place as to the status of these recommendations.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Annual Internal Audit Report 2020/21That the Governance and Assurance Committee noted the Head of Audit and Investigations’: ( i ) 0verall opinion for 20...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.