That Council adopts the proposed new Contract Standing Orders as set out within Appendix 1, notes the key changes to the Contract Standing Orders as defined within Section 4 of the report, and approves the consequential amendments required to other parts of the Constitution. The new Contract Standing Orders will come into effect from 1 November 2020.
Word for word from the decision Redbridge published for this meeting.Source: moderngov.redbridge.gov.uk
1.1The Council’s Contract Standing Orders (CSO), provide the governance structure for the procurement of all goods, works and services. They were last reviewed by the Council in 2017.
1.2These rules are intended to ensure:
Certainty in contract terms Consistency in the application of the law and Council policy Probity; Best Value
1.3It is considered that the current CSO can be simplified, improved and modernised as outlined below.
1.4The proposed changes to the current CSO were considered by the Constitution Review Corporate Panel at its meeting on the 21st July 2020. The Panel supported the proposals and in addition recommended that:
(i) Each Scrutiny Committee takes on a more active role in scrutinising the APP. Once the APP has been approved by Cabinet, each Scrutiny Committee will be asked to consider each item listed within the APP relevant to their remit. By Increasing the level of Scrutiny Committee involvement during the APP process, this will provide increased opportunities for each Committee to help shape future procurement outcomes.
(ii) Procurement produce a quarterly report for Cabinet which will provide details of all Contracts that have been awarded by the Council during the preceding quarter, including the total value of each contract and the name of the Decision Maker who was responsible for approving the Award.
1.5The proposed changes to the current CSO were also considered by the General Purposes Committee at its meeting on the 30 July 2020. The Committee also supported the proposals.
Recommendations
2.1Council is asked to adopt the proposed new Contract Standing Orders as set out within Appendix 1, note the key changes to the Contract Standing Orders as defined within Section 4 of the report, and approve the consequential amendments required to other parts of the Constitution. The new Contract Standing Orders will come into effect from the 1 November 2020.
Contact Point Report Author: Ian Ambrose Position: Operational Director of Finance (Deputy s151 Officer) Service: Finance Department Telephone: 0208 708 6410 Email: [email protected] 3. Background
3.1It is considered that the Council’s current CSO can be simplified, modernised and improved. This will help the Council to:
Achieve better quality and value for money – through stimulating and maximising market competition. Provide local suppliers with increased access to opportunities with the Council. This will be achieved through introducing the mandatory “open” advertising of all Works Contracts with a total contract value equal to or exceeding £500,000. Better manage, monitor and control its exposure to risk. Make it easier for Directorates to procure, Goods, Works and Services under the OJEU threshold.
4. Proposal
Approval to Procure
4.1It is considered that the Approval to Procure stage is the most important and critical stage of the procurement process. At this stage, each procurement is reviewed and scrutinised, before a decision is made as to whether to continue with the procurement or not.
4.2The Approval to Procure stage also represents the earliest opportunity for Cabinet Members and/or Cabinet to be consulted on each procurement. All feedback received at this stage is considered extremely valuable in helping shape and refine each future procurement.
4.3Currently Officers must obtain Cabinet approval prior to commencing any procurement process where the total contract value is likely to be equal to or greater than £0.500m. This requirement only applies to procurements over £0.500m which have not previously been reported to Cabinet as part of the Annual Procurement Plan (APP) approval process (see para 4.5 to 4.7 below).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.