1.1The Ilford Western Gateway (IWG) is Redbridge Council’s largest and most ambitious regeneration initiative. The project will be a highly visible exemplar for inclusive, sustainable neighbourhood led growth, delivering genuine local economic and social benefit as enshrined in ‘Growing Redbridge Together’.
1.2Successfully delivered, the project will transform Ilford and realise benefits greater than those envisaged in the Cabinet approved Ilford Delivery Prospectus and Ilford Manifesto. Good progress is being made in implementing the resolutions made by Cabinet in February 2021, including procuring a development partner to form a 50:50 Joint Venture (JV) with the Council, to deliver the ambitious placemaking outcomes.
1.3The IWG will deliver a long-term legacy in terms of social, economic and environmental benefits. The social value and sustainability approaches alongside the masterplan, will act as a catalyst for investment in the local and wider area and will create a unique place for people to live, work and socialise. The Economic Impacts of the proposals from the potential preferred bidder are substantial providing 860 additional homes accommodating 2,300 new residents and generating £20million annual expenditure. Community and commercial space amounting to 4600 sq.m. will create around 300 jobs and add £15.6 million per annum (GVA) to the economy. These are in addition to huge benefits in health outcomes and safety through reduction in pollution and improvements to leisure and the environment through sustainable design.
1.4Cabinet approved the Ilford Western Gateway Delivery Strategy and the recommendations to deliver the strategy on 11 February 2021.
1.5The purpose of the report is to inform Cabinet of the outcome of the procurement so far undertaken by the Council to find a Private Sector Partner (PSP) for the comprehensive regeneration of the Ilford Western Gateway (IWG).
1.6This report will seek Cabinet approval to select a ‘Preferred Bidder’ to become the PSP for a Joint Venture partnership with the Council subject to finalising contracts. The report also seeks appropriate delegations to formalise the structure of the JV, finalise proposed contracts to form a Joint Venture Limited Liability Company with the Preferred Bidder, conclude the JV Business Plan for the delivery of the entire IWG programme.
The Cabinet Member/Cabinet is recommended to:-
2.1Note the outcome of the Competitive Dialogue stage of the procurement process under the Public Contracts Regulations 2015, as outlined in the report.
2.2Approve to continue the procurement process which has identified the company [see a) in annexe 3] as the Councils Preferred Bidder (PB) and potential Private Sector Partner with whom the Council will seek to establish a Joint Venture Partnership for the comprehensive regeneration of the Ilford Western Gateway
2.3Delegate to the Corporate Director Regeneration and Culture in consultation with the Cabinet Member for Growth & Operations and the Operational Director of Assurance, to clarify, specify and optimise the Preferred Bidder’s proposal in accordance with the procurement regulations, formalise the proposed structure of the JV, finalise proposed contracts to form a Joint Venture Limited Liability Company with the Preferred Bidder and conclude the JV Business Plan in line with the objectives as set out in the suite of legal agreements as detailed in annexe 2 of this report.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
5b public_Ilford Western Gateway_Annexe 1 Sept 22 CabinetAppendix | 506 KB | Download |
PDF |
Progress on Procurement of a Joint Venture partner for Regeneration of the Ilford Western Gateway (part Exempt)Report | 858 KB | DownloadRead as text |
Follow Overview Committee at Redbridge and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Apr 2023 | Pre-Decision ScrutinyThe Committee noted the usual process of delegating authority to the Operational Director of Assurance, in liaison wi... | Noted | Open |
| 27 Mar 2023 | Building Maintenance Capital Programme 2023-24The Overview Committee noted the report and the discussion. (Councillor M. Sachs declared a personal interest under t... | Noted | Open |
| 27 Mar 2023 | Children and Families Policy - Looked After Children Accommodated Under Section 20 of the Children's Act 1989.The Overview Committee i) Noted the report and the discussion ; and ii) Requested an implementation update in 18 mont... | Noted | Open |
| 27 Mar 2023 | Pre-Decision ScrutinyThe Committee noted the usual process of delegating authority to the Operational Director of Assurance, in liaison wi... | Noted | Open |
| 8 Feb 2023 | Review of Housing Revenue Account Financed and HRA Budget 2023/24The Committee noted the report and the discussion. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.