To receive and consider a report from officers entitled "Revenue and Capital Budget and Council Tax 2026/27 and MTFS 2026/27- 2030/31"
ApprovedCommittee6 papers
AI summaryRedbridge Council sets 2026/27 budget with 4.99% Band D council tax rise and approves £769.583m capital programme, awaiting £70m Exceptional Financial Support.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedRevenue, capital, treasury and Council Tax for 2026/27 set
Money£769.583m capital programmeWith General Fund revenue budget of £314.896m
What happens nextEFS capitalisation direction pendingSubject to external assurance review by Secretary of State
Who it affectsAll Redbridge Council Tax payersIncluding General Fund tenants and schools
What was decided
Approved £55.818m new capital spend and £149.384m new capital lease proposals for 2026/27 to 2030/31, and a revised capital programme of £769.583m. Report P7, P8
Approved General Fund net revenue budget of £314.896m for 2026/27, Schools budget of £453.664m, and a 4.8% rent rise on General Fund housing from 6 April 2026. Report P22, P27, P28
Approved a 2.99% general Council Tax rise and a 2.00% Adult Social Care Precept, setting Redbridge's Band D council tax at £1,784.07 (total with GLA £2,294.58). Report P45, P46, P56, P58, P64
Why
The Council must set its budget and Council Tax by 11 March of the preceding financial year to allow bills to be issued on time for 1 April. Report 3.1, 13.5
Cabinet considered the budget on 26 February 2026 and recommended approval, with updates since including late-notified highways grant schemes. Report 1.2, 5.2
The Executive Director of Resources advises the budget is robust, with £3.450m General Fund balance, £27.136m earmarked reserves and a £7.000m Risk and Contingency Provision. Report 4.3, 4.4, 4.5, 12.3
What happens next
Late-notified grant-funded highways schemes totalling £3.603m will be added to the capital programme once Council approval is confirmed. Report P9
Conditional capital schemes in Appendix D(ii) require further reports approved by the Deputy Leader and Cabinet Member for Finance in consultation with relevant leaders before funds are released. Report P10, 4.7
The Secretary of State will decide whether to grant a £70m Exceptional Financial Support capitalisation direction for 2026/27 after an external assurance review. Report 5.1, P85
The money
£769.583m Revised capital programme 2025/26 to 2030/31 Report P8
£55.818m Total new capital spend proposals 2026/27 to 2030/31 Report P7
£149.384m Total new capital lease proposals 2026/27 to 2030/31 Report P7
£314.896m General Fund net budget requirement 2026/27 Report P27
£453.664m Schools budget 2026/27 Report P28
£1,784.07 Redbridge Band D Council Tax 2026/27 Report P56, P83
£2,294.58 Total Band D Council Tax including GLA precept Report P58, P83
£510.51 GLA Band D precept 2026/27 Report P35, P61
£51.132m Proposed growth for 2026/27 Report P31
£10.478m Service inflation for 2026/27 Report P31
£0.122m Proposed savings for 2026/27 Report P31
£51.251m Total net savings proposals across MTFS Report P40
£132.811m Forecast savings and additional income needed 2026/27 to 2030/31 Report P41
£26.227m Council's share of business rates income 2026/27 Report P37
£1.632m Forecast collection fund surplus (Council share) Report P30
£3.450m Forecast General Fund balance at 31 March 2026 Report 4.3, P42
£27.136m Forecast earmarked reserves at 31 March 2026 Report 4.5, P42
£7.000m Risk and Contingency Provision for 2026/27 Report 4.4
£70m Exceptional Financial Support requested from Secretary of State Report 5.1, P85
£50m Unfunded Broadmead Bridge scheme in capital programme Report 4.8
£1.083m Safer Corridors & Neighbourhoods highways grant
£0.266m Cycleway Network Development highways grant
£0.033m Bus Priority highways grant
£0.350m Safer Streets highways grant
£0.060m Cycle Parking highways grant
£1.811m Highway Maintenance Funding grant
£167,968,406 Council tax requirement 2026/27 Report P50, P54
94,149 Council tax base 2026/27 (Band D equivalents) Report P36, P55
Options considered
Chosen: Apply 2.99% general Council Tax increase and 2.00% Adult Social Care Precept. Total 4.99% rise is below the 5% referendum trigger, so no referendum is required Report P45, P46, 4.11, P64
Chosen: Add late-notified grant-funded highways schemes to capital programme. Funded by recently announced grants; in addition to Cabinet recommendations Report P9
Chosen: Pursue £50m unfunded Broadmead Bridge scheme. Council submitting funding bid to Department for Transport's Structures Fund and lobbying government Report 4.8
Implications
Financial: General Fund balance of £3.450m and Business Risk Reserve are below target levels and will take several years to replenish under the proposed MTFS. Report 4.3, 12.3
Financial: The Council requested £70m Exceptional Financial Support, which if not granted could lead to a Section 114 Notice, the S151 Officer warns. Report 5.1, 12.4
Equalities: Cumulative equalities impact analysis identified low adverse risk for two proposals, one affecting disabled people and one across all protected characteristics. Report 7.10, 7.11
Staffing: No planned reductions in staffing from the savings identified since February 2024; redundancies would be minimised by prioritising vacant posts and reducing agency staff. Report 8.1, 8.2
Risk: Key risks include funding volatility beyond 2026/27, savings delivery, adult social care and homelessness pressures, and ageing infrastructure liabilities. Report 4.2, P73
Legal: Budget must be set by 11 March or council tax bills cannot be issued on time, exposing the Council to legal challenge and loss of income. Report 3.1, 13.5
Who and where
Redbridge Council Tax payers in all property bands A to H Report P58, P64
General Fund housing tenants (4.8% rent rise from 6 April 2026) Report P22, P24
Council employees in Council accommodation (4.8% rent rise) Report P23
Redbridge schools (Schools budget of £453.664m) Report P28, P29
Adult Social Care service users (funded by 2.00% precept) Report P45
Residents near late-notified highways schemes (Safer Streets, Cycleways, Bus Priority)
Timeline
1 April 2026: Licence land charges by Housing Service increase by 4.8% Report P25
2026/27 financial year: New revenue budget, capital programme, fees and charges take effect Report P20, P27, P28
2026/27 to 2030/31: Medium Term Financial Strategy period, with £132.811m savings required Report P41
6 April 2026: General Fund and employee housing rents increase by 4.8%; tenant service charges align with HRA Report P22, P23, P24
Plain English for the jargon
MTFS: Medium Term Financial Strategy, covering several years of financial planning
MRP: Minimum Revenue Provision, the minimum amount the Council must set aside to repay debt
DSG: Dedicated Schools Grant, central government funding for schools
HRA: Housing Revenue Account, the ring-fenced account for council housing
EFS: Exceptional Financial Support, additional government funding for councils in financial difficulty
GLA precept: Council Tax charge set by the Greater London Authority
ASC precept: Adult Social Care precept, a specific Council Tax increase to fund adult social care services
Section 114 Notice: Formal declaration by a council's Chief Finance Officer that the authority cannot balance its budget
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8
Resolved
That with regard to the proposed Capital Budget, Council: In respect of the Capital Investment Programme 2025/26 to 2030/31 (i) Considered and approves the Capital Investment Strategy for 2026/27 to 2030/31 set out in Appendix B; (ii) Approves the £55.818m total new capital spend proposals and £149.384m total new capital lease proposals for 2026/27 to 2030/31 (paragraph 9.5 of Appendix AA and Appendix C ); (iii) Approves the revised capital programme for 2025/26 to 2030/31 of £769.583m, as set out in Appendix AA paragraph 9.9 and Appendices D( i ) and D(ii ); (iv) In addition to the recommendations of Cabinet, approves the addition of late notified grant funded highways related schemes detailed in paragraph 5.2.2 to the capital programme; (v) Notes that where capital schemes have been flagged as Conditional in Appendix D(ii), a report is required to be produced detailing the specific use of the budget, and where appropriate a full business case, to be approved by the Deputy Leader and Cabinet Member for Finance in consultation with the Leader, ... view the full minutes text for item 8.
Word for word from the decision Redbridge published for this meeting.Source: moderngov.redbridge.gov.uk
1.1This report seeks Council approval of the Revenue and Capital Budget and Council Tax for 2026/27. It also seeks approval of a capital programme for 2025/26 to 2030/31. It presents the refreshed Medium Term Financial Strategy 2026/27 – 2030/31 for approval and provides an update on the economic climate and funding position.
1.2Cabinet considered the Budget report on 26 February 2026 and set out budget proposals and recommendations for Council to consider at this budget setting meeting. The Cabinet report is attached at Appendix AA . The report includes several appendices as summarised in Section 4 below. These provide detailed information that should be used to support Members in their decision making. Where updated information has been received since the Cabinet report was publish ed, this report highlights where changes have bee n made.
Recommendations
It is recommended that:
2.1With regards to the proposed Capital Budget, that Council: -
In respect of the Capital Investment Programme 2025/26 to 2030/31
2.1.1 Considers and approves the Capital Investment Strategy for 2026/27 to 2030/31 set out in Appendix B;
2.1.2 Approves the £55.818m total new capital spend proposals and £149.384m total new capital lease proposals for 2026/27 to 2030/31 (paragraph 9.5 of Appendix AA and Appendix C);
2.1.3 Approves the revised capital programme for 2025/26 to 2030/31 of £769.583m, as set out in Appendix AA paragraph 9.9 and Appendices D(i) and D(ii);
2.1.4 In additi on to the recommendation s of Cabinet, a pproves the addition of the late notified grant funded highways related schemes detailed in paragraph 5.2.2 to the capital programme;
2.1.5 Notes that where capital schemes have been flagged as Conditional in Appendix D(ii), a report is required to be produced detailing the specific use of the budget, and where appropriate a full business case, to be approved by the Deputy Leader and Cabinet Member for Finance in consultation with the Leader, Cabinet Member responsible for the Portfolio the scheme is within, Executive Director of Resources and the Executive Director responsible for the scheme . In respect of the Treasury Management Strategy and Prudential Indicators 2026/27
2.1.6 Approves the Treasury Management Strategy 2026/27 as set out at Appendix F;
2.1.7 Approves the Treasury Management Policy Statement 2026/27 attached to Appendix F as Annex A;
2.1.8 Approves the Minimum Revenue Provision (MRP) policy 2026/27 attached to Appendix F as Annex B;
2.1.9 Approves the Prudential Indicators attached to Appendix F as Annex C;
2.1.10 Approves the Annual Investment Strategy 2026/27 attached to Appendix F as Annex D;
2.2With regards to the proposed Revenue Budget, that Council: -
In respect of the Robustness of the Budget
2.2.1 Considers and acknowledges the advice of the Executive Director of Resources on the robustness of the proposed Budget and Medium Term Financial Strategy, the adequacy of the Council’s Reserves and the Reserves Strategy, as required by Section 25 of the Loc al Government Act 2003;
In respect of Fees, Charges and Rents for 2026/27
2.2.2 Approve the changes to Fees and Charges which require Cabinet approval as set out in Appendix G;
2.2.3 Note the Parking Account set out in Appendix H;
2.2.4 Approves that rents for housing properties held within the General Fund and let on secure tenancies are increased by 4.8%, from 6 April 2026, as set out in Section 11 of Appendix AA;
2.2.5 Approves that rents for housing properties used by the Council for employee accommodation are increased by 4.8%, from 6 April 2026, as set out in Section 11 of Appendix AA;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.