AI summaryRedbridge Cabinet approved starting a new Local Plan review and the indicative timetable, delegating authority to officers. The plan must be produced within 30 months under new legislation, costing an estimated £4.651m over four years.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedLocal Plan review to start
Money£4.651mestimated total over four years
What happens nextCommence by 30 April 2027publish Gateway 1 by then
Who it affectsRedbridge residents and developersall new development in the borough
What was decided
Cabinet approved the commencement of the Local Plan review, eight years after the current plan was adopted in 2018. Report 2.1, 3.3
Cabinet approved the indicative timetable and delegated authority to the Executive Director of Place, Communities and Enterprise, in consultation with the Cabinet Member for Housing and Planning, to amend the timetable and publish it. Report 2.2
Cabinet delegated authority to approve the draft Local Plan process, including publication of the Notice of Commencement and start of consultation, and to the Director of Planning and Head of Spatial Planning to take all necessary steps before adoption. Report 2.3, 2.4
Why
Without an up-to-date plan, control of development passes to speculative builders, and a statutory duty exists to have a current Local Plan. Report 1.2, 3.3, 4.3
New secondary legislation in force from 25 March 2026 cuts the plan-making period to 30 months and requires notice of intention by 31 December 2026 and commencement by 30 April 2027. Report 1.7, 3.1, 5.1
A new plan will shape development, deliver affordable housing, jobs and infrastructure, and protect green spaces and heritage, with genuine engagement of residents, including young people. Report 1.1, 1.5, 3.2, 4.5
What happens next
A pre-formal 'getting ready' stage runs from June 2026 to November 2026, covering scoping, spatial strategy options and Strategic Environmental Assessment scoping. Report P30
Stage 1 runs December 2026 to March 2027, with the Local Plan Commencement Notice and timetable published in December 2026 and a minimum 21-day scoping consultation. Report P31, P32
Stage 2 runs April 2027 to February 2029, with public consultations in autumn 2027 and 2028, followed by Stage 3 from March 2029 to September 2029 for examination and adoption. Report P33, P34, P35
The money
£4.651m estimated total cost of Local Plan review over 4 years, including programme officer, consultancy, legal and external advisor costs Report 12.1, 12.2
1.034 2026/27 budget allocation in £m Report 12.2, P64
1.495 2027/28 budget allocation in £m Report 12.2, P64
1.568 2028/29 budget allocation in £m Report 12.2, P64
0.554 2029/30 budget allocation in £m Report 12.2, P64
Implications
Financial: Estimated cost of approximately £4.651m over four years; growth has been set aside to fund this work as part of the 2026/27 budget setting process. Report 12.1, 12.3
Legal: Governed by the Planning and Compulsory Purchase Act 2004 and The Town and Country Planning (Local Planning) (England) Regulations 2026; adoption requires Full Council, with the Strategic Planning Corporate Panel reviewing at key stages. Report 13.2, 13.3
Risk: Risk of a plan not fit for purpose if under-resourced, with possible increased costs and government sanctions; the Government has stated it could take over production if not progressed. Report 7.1, 7.2
Staffing: Additional staff and technical consultants will be required, particularly to prepare the evidence base, with costs factored into the budget. Report 9.1, 9.2
Equalities: No spatial strategy or policy options exist yet, so equalities impacts cannot be determined; a full equalities impact assessment will be carried out as part of the plan and any Integrated Impact Assessment.
Climate: The Local Plan is intended to support tackling climate change alongside delivering new homes, jobs and infrastructure. Report 1.1, 4.1
Other: Young people will be engaged in consultation, building on Redbridge's status as a UNICEF Child-Friendly Borough; the Community Safety Team and Metropolitan Police Designing Out Crime Officer will also be involved. Report 10.1, 1.3, 11.1
Who and where
Redbridge residents, who will be invited to influence the plan's vision, strategy and site choices Report 1.4, 3.2
Developers and landowners, who will be subject to new plan policies and allocations Report 4.3, 4.4
Planning and wider council staff, with additional resources to be recruited throughout the process Report 9.1, 9.2
Children and young people in the borough, to be specifically engaged as part of the Child-Friendly Borough status Report 1.3, 10.1
People sharing protected characteristics, to be considered through a future equalities impact assessment Report 8.2
Timeline
June 2026 to November 2026: Pre-formal 'getting ready' stage: scoping, preparation, agreeing spatial strategy options and Strategic Environmental Assessment scoping Report P30
December 2026: Local Plan Commencement Notice published and timetable published Report P32
December 2026 to March 2027: Stage 1: scoping consultation (minimum 21 days) and additional initial informal consultation; PID, plan timetable and monitoring requirements identified Report P31, P32
31 December 2026: MHCLG deadline for giving notice of intention to commence a review Report 3.1, 5.1
April 2027 to July 2027: Visioning and strategy development Report P33
30 April 2027: MHCLG deadline for commencing a review, marked by publication of the Gateway 1 self-assessment and start of the 30-month timetable Report 3.1, 5.1, P33
September to October 2027: First public consultation on the Local Plan (6 weeks) Report P33
October 2027 to August 2028: Evidence gathering and drafting of the plan Report P34
September to October 2028: Public consultation on proposed Local Plan (8 weeks) Report P34
November 2028 to March 2029: Engagement, changes and submission Report P34
March 2029 to September 2029: Stage 3: Gateway 3 stop/go check, examination, finalisation and adoption of digital plan Report P35
Plain English for the jargon
Local Plan: The council's statutory planning document setting out policies and site allocations for development in the borough
Gateway 1, 2 and 3: Formal checkpoints in the new plan-making system, marking the start of the 30-month timetable, evidence review and pre-adoption checks
MHCLG: Ministry of Housing, Communities and Local Government
PSED: Public Sector Equality Duty under section 149 of the Equality Act 2010
UNICEF Child-Friendly Borough: Redbridge's designation under UNICEF's programme to put children's rights at the heart of local decisions
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9
Resolved
That ( i ) the commencement of the Local Plan review, be approved. (ii) the indicative timetable for the Local Plan, as outlined in 4.1 1 of this report, and d elegate authority to the Executive Director of Place, Communities and Enterprise, in consultation with the Cabinet Member for Housing and Planning, to agree amendments to the new Local Plan timetable and then publish it, be approved. ? (iii)Delegate authority to the Executive Director of Place, Communities and Enterprise, in consultation with the Cabinet Member for Housing and Planning to approve the draft Local Plan process which includes publication of the Notice of Commencement and the commencement of the consultation, be agreed. (iv)Delegate authority to the Director of ... view the full minutes text for item 9.
Word for word from the decision Redbridge published for this meeting.Source: moderngov.redbridge.gov.uk
1.1The Council, through an up-to-date Local Plan, will positively shape the Borough's environment. It will influence the location and form of new development so that high quality homes, neighbourhoods and facilities are provided for the Borough’s residents and businesses. The Local Plan will attract investment to deliver the local priorities such as tackling climate change, inequality, delivering new affordable homes, additional local jobs and infrastructure whilst protecting green spaces and heritage assets.
1.2It is a statutory duty to have an up-to-date Local Plan, and it is also the best opportunity to shape the future of Redbridge over the next 15 years to create a borough that our residents can be proud of to call home.
1.3This new Local Plan will be developed with our residents, including children and young people, to create the places, homes and jobs that are needed. The Local Plan will build on Redbridge’s unique status as a UNICEF Child-Friendly Borough to ensure Redbridge is the best Borough in London to raise a family.
1.4The Local Plan will be informed by a genuine listening exercise, where the views and priorities of residents will be at the centre of the process.
1.5The new Local Plan also presents an exciting and significant opportunity to safeguard the borough’s valued assets. It will enable key placemaking initiatives that support future generations to live healthy and happy lives. This will be achieved through the delivery of affordable housing, quality employment opportunities and infrastructure that underpin thriving, active and pleasant neighbourhoods for communities.
1.6The budgeted costs are prudently aligned to deliver a cost-effective, yet ambitious, Local Plan. Without an appropriate Plan in place, control is lost to speculative development but, with a Plan in place, residents can sit at the heart of the strategic plan -making process.
1.7New secondary legislation came into force on 25 March 2026 regarding the production of local plans which must now be completed within 30 months which is down from the previous average of around seven years for local plan production. (Planning Advisory Service Plan Making Reforms: Consultation on Implementation September Event Series). 1.8 This report provides information on an indicative timeframe and budget for the Local Plan review and seeks approval to begin the Local Plan review process.
Recommendations
Cabinet is recommended to:
2.1Approve the commencement of the Local Plan review.
2.2Approve the indicative timetable for the Local Plan, as outlined in 4.11 of this report, and delegate authority to the Executive Director of Place, Communities and Enterprise, in consultation with the Cabinet Member for Housing and Planning, to agree amendments to the new Local Plan timetable and then publish it.
2.3Delegate authority to the Executive Director of Place, Communities and Enterprise, in consultation with the Cabinet Member for Housing and Planning to approve the draft Local Plan process which includes publication of the Notice of Commencement and the commencement of the consultation.
2.4Delegate authority to the Director of Planning and Building Control and the Head of Spatial Planning, in consultation with the Cabinet Member for Housing and Planning to undertake all actions necessary to meet the approved Local Plan timetable prior to final adoption of the Local Plan.
Reasons for recommendations
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.