CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Redbridge
Overview and Scrutiny Committee, Monday 13 July 2026

Medium Term Financial Strategy

Noted Scrutiny 2 papers

AI summaryRedbridge Overview and Scrutiny Committee noted the Medium Term Financial Strategy, which shows a balanced three-year settlement but a £51.324m gap opening in 2029/30.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNo decision taken, report received for information
MoneyBudget gap rises to £51.324m by 2029/30After applying Exceptional Financial Support through 2028/29
What happens nextFurther EFS bids expected for 2027/28 and 2028/29New corporate plan due later in 2026
Who it affectsCouncil services and residentsAdult social care, children's services, homelessness budgets

What was decided

The Overview and Scrutiny Committee noted the Medium Term Financial Strategy report covering the five-year period 1 April 2026 to 31 March 2031. Report 1.3

The committee received an update on current assumptions within the MTFS, including inflation, interest rates, demand pressures and future local government funding. Report 2.1, 4.2

Why

Officers identified a significant funding gap in future years of the MTFS, particularly from 2029/30, following agreement of the 2026/27 budget in March 2026. Report 3.1, 8.1

Demand-led pressures in adult social care, children's services and temporary accommodation, alongside higher inflation and interest rates, continue to challenge the budget. Report 4.4, 4.5, 4.11

What happens next

The Council anticipates submitting further EFS bids to MHCLG for 2027/28 and 2028/29, with the ambition of returning to financial stability without EFS by 2029/30. Report 5.6, P23

A new corporate plan is to be launched later in 2026, which will need to be aligned with the MTFS and the funding constraints identified. Report 11.1

The build of the 2027/28 budget will follow the timeline set out in the report, with monitoring through the Budgetary Control Report. Report 12.1, 13.3

The money

  • £61.5 million Additional government funding support secured after lobbying for fairer funding Report 4.3
  • approx. £20m Expected from EFS ask for 2026/27 to fund the transformation programme Report 5.5
  • £20m Of EFS used to rebuild the General Fund Balance Report 5.3
  • £0.500m Assumed annual increase in Council Tax receipts from housing growth Report 4.8
  • 2.99% plus an Adult Social Care precept increase of 2% Maximum Council Tax rise without referendum assumed in MTFS scenarios Report 4.7
  • £3.999m Budget gap for 2028/29 after assuming full Council Tax increases Report P36
  • £51.324m Budget gap for 2029/30 after assuming full Council Tax increases Report P36
  • £60.642m Budget gap for 2029/30 before assumed future Council Tax rate increases Report P36

Options considered

  • Rejected: Increase Council Tax at the maximum level without a referendum (2.99% plus 2% Adult Social Care precept). No decision has been taken on future Council Tax increases Report 4.7

Implications

  • Financial: Exceptional Financial Support is permission to capitalise revenue costs, not a cash grant, and is assumed to be financed by external borrowing. Report 5.2
  • Financial: Continued reliance on EFS is anticipated for another two years beyond 2026/27, with a 'cliff-edge' in funding after the current multi-year settlement ends. Report 4.1, 8.2
  • Legal: Full Council must approve the budget and Council Tax demand under the Local Government Act 2000, with EFS approval requiring the Council to evidence its recovery plan. Report 20.2
  • Staffing: Compulsory redundancies will be minimised by prioritising vacant post deletions and reducing agency staff, with voluntary redundancies also considered. Report 15.2
  • Equalities: The Council must have due regard to the Public Sector Equality Duty under section 149 of the Equality Act 2010 when exercising its functions. Report 14.1, P48
  • Risk: Inflation and interest rates are expected to remain higher for longer, with delivery and timing risks attached to the Modernisation programme. Report 7.2

Who and where

  • Residents using adult social care and children's services, where demand is rising Report 4.5
  • Households in temporary accommodation or at risk of homelessness
  • Council staff, given potential service modernisation and post reductions Report 15.2, 15.3
  • Council Tax payers in the London Borough of Redbridge Report 4.7

Timeline

  • March 2026: Council agreed the budget for 2026/27 and MTFS proposals for future years Report 3.1, 4.1
  • 17/06/26: Budgetary Control Outturn Report 2025/26 considered by Cabinet Report P73
  • 2026-07-13: Overview and Scrutiny Committee noted this MTFS report
  • 2026/27 to 2028/29: Period covered by the Government's multi-year financial settlement for Redbridge Report 4.1, 8.1
  • 2027/28 and 2028/29: Further EFS bids anticipated to be submitted to MHCLG Report P23
  • 2029/30: Stated ambition to return to financial stability without EFS Report 5.6

Plain English for the jargon

  • MTFS: Medium Term Financial Strategy, covering the five-year financial planning period
  • EFS: Exceptional Financial Support, permission from MHCLG to capitalise revenue costs
  • MHCLG: Ministry of Housing, Communities and Local Government
  • RRB: Redbridge Recovery Board, overseeing the Redbridge Recovery Plan
  • CIPFA: Chartered Institute of Public Finance and Accountancy
  • LGA: Local Government Association
  • PSED: Public Sector Equality Duty under section 149 of the Equality Act 2010
  • ASC: Adult Social Care
  • TA: Temporary Accommodation
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item22

Resolved

That Overview and Scrutiny Committee noted the report.
Word for word from the decision Redbridge published for this meeting. Source: moderngov.redbridge.gov.uk

Follow this further

Built from Redbridge's papers

What the report saysPro

Report to Overview and Scrutiny Committee

Executive summary

1.1The Council’s strategic aims and priorities drive the medium term financial planning process, with changes in resource allocation determined in accordance with policies and priorities. The Medium Term Financial Strategy provides the framework for the development of annual budgets in line with the aims of the Council’s strategy and priorities.

1.2The background to the current Medium Term Financial Strategy continues to be one of increased uncertainty, with inflationary and interest pressures, the national and global economy, and lack of progress on social care reform.

1.3The Medium Term Financial Strategy includes financial projections for the five- year financial planning period 1 April 2026 to 31 March 2031 in respect of the projected revenue resources available to the Authority.

Recommendations

The Cabinet is recommended to:-

2.1Note the content of this report.

Reasons for recommendations

3.1In March 2026, Council agreed the budget for 2026/27 including the budget proposals for future years, at which time it was recognised that there was a significant funding gap in future years of the MTFS, particularly from 2029/30.

3.2This report provides the Cabinet with an update on the assumptions currently contained within the MTFS and provides some insight into several factors that will play a significant role in the Council’s financial planning. THE DECISIONS PROPOSED IN THE RECOMMENDATIONS TO THIS REPORT MAY BE CALLED IN

Cabinet Member Contact Point Name: Cllr Vanisha Solanki Position: Deputy Leader/Cabinet Member for Finance and Share Prosperity Email: [email protected]

Contact Point Report Author: Ian Ambrose Position: Director of Finance (Deputy s151 Officer) Email: [email protected] 4. Background

4.1In March 2026, Council agreed the budget for 2026/27 including the budget proposals for future years. For the first time in several years, the Government issued a multi-year financial settlement for Local Government which gives a level of assurance over Redbridge’s expected funding from core grants for the period 2026/27-2028/29, and this settlement includes a substantial increase in funding for Redbridge over this period. Despite the increase it is not enough to undo several years of systemic underfunding alongside growing demand and cost for key services and as such the 2026/27 budget for Redbridge was set with the use of Exceptional Financial Support and it is anticipated this will need to continue for another two years.

4.2Within the MTFS, there are several key assumptions such as inflation, Cost of Living, service demographics, demand pressures and future local government funding which all need to be kept under review as new information becomes available. For example, there has been some slippage in the capital programme at the end of 2025/26 which should result in a reduction in the revenue cost of funding capital borrowing, however this is offset against interest rates remaining higher longer than expected.

Key Assumptions in producing the 2026/27 Budget and MTFS

4.3Improved Government Funding. Redbridge secured an additional £61.5 million in government funding support after lobbying for fairer funding. This is significant because historically Redbridge had been one of the lowest-funded London boroughs per capita.

4.4Continued Inflationary Cost Pressures. The budget assumed continued elevated inflation impacting operating costs.  Main pressures identified:  Contract inflation on outsourced services  Utility and energy price increases  Higher procurement costs  General service delivery cost escalation  The Council explicitly stated inflation remained one of the largest budget risks.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
MTFS Five Year Projection Council March 26 (1)Appendix A 195 KB Download
PDF
Medium Term Financial StrategyReport 346 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 9 attended
AC
Councillor Alex Charlton-HolmesChair, in attendance
SA
Councillor Stephen AdamsMember, in attendance
SL
Councillor Syeda Lovely ChoudhuryMember, in attendance
ME
Councillor Marwan ElfallahMember, in attendance
MG
Councillor Matthew GoddinMember, in attendance
JR
Councillor Jyotsna Rahman IslamMember, in attendance
MR
Councillor Milli Richards ClackMember, in attendance
MS
Councillor Martin SachsMember, in attendance
VT
Vibhu TanejaMember, in attendance

On this subject at Redbridge

Search all
  1. Medium Term Financial StrategyThis decision
  2. Medium Term Financial Strategy - UpdateAgreed
  3. Medium Term Financial StrategyNoted
  4. Medium Term Financial Strategy UpdateNoted
  5. Medium Term Financial Strategy UpdateNoted
  6. Revenue and Capital Budget and Council Tax 2021/22 and Medium Term Financial StrategyNoted

More from Redbridge Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
13 Jul 2026 Leisure and Culture - Future Service Delivery OptionsThat Overview and Scrutiny Committee noted the report. Noted Open
13 Jul 2026 Quarterly Corporate Performance ReportThat Overview and Scrutiny Committee noted the report. Noted Open
13 Jul 2026 Treasury Management ReportThat Overview and Scrutiny Committee noted the report. Noted Open
13 Jul 2026 Budgetary Control ReportThat Overview and Scrutiny Committee noted the report. Noted Open