RESOLVED That the application be refused for the following reason: The proposed development would result in a significant encroachment of built form into undeveloped agricultural land to the south of the existing caravan park and would be an unacceptable intensification of the use which fails to acknowledge the historic rural character of the surrounding area due to its scale and siting. The economic benefits of the scheme are not considered to outweigh the harm. As such the proposal is considered to be contrary to policies DMG2 and DMB3 and EN2 of the Core strategy for the Ribble Valley. (Simon Pemberton spoke in favour of the above application. Stella Rosthorn spoke against the above application)
Word for word from the decision Ribble Valley published for this meeting.Source: democracy.ribblevalley.gov.uk
APPLICATION REF: 3/2021/0720 GRID REF: SD 382579 451917 DEVELOPMENT DESCRIPTION: CHANGE OF USE OF LAND TO FORM AN EXTENSION OF RIBBLE VALLEY COUNTRY AND LEISURE PARK TO FACILITATE AN ADDITIONAL 62 STATIC CARAVAN PITCHES (ALLOWING A TOTAL OF 387 PITCHES ACROSS THE PARK), ASSOCIATED HIGHWAY WORKS, SEWAGE TREATMENT PLANT AND PUMPING STATION, IMPROVEMENTS TO THE EXISTING OPEN SPACE AND THE CREATION OF ADDITIONAL OPEN SPACE, LANDSCAPING AND OTHER ASSOCIATED WORKS AT TWYN GHYLL CARAVAN SITE, SETTLE LANE, PAYTHORNE, BB7 4JD
CONSULTEE RESPONSES/ REPRESENTATIONS MADE:
PARISH COUNCIL:
Paythorne Parish Council wishes to object to the application a detailed letter has been submitted and the main areas of concerns raised are in relation to: • Highway safety, access, deliveries. • Impact on ecology no biodiversity net gain • Detrimental visual impact on the surrounding countryside and landscape.
The Parish Council do not consider that the revised scheme adequately addresses their concerns and that the development will still have an unacceptable impact.
ENVIRONMENT DIRECTORATE (COUNTY SURVEYOR):
The Highways Development Control Section has raised no objection to the proposal subject to the imposition of technical conditions which are discussed further in the report.
WOODLAND TRUST:
Object:
• Detrimental impact to ancient woodland – potential damage. • Damage to plantations on ancient woodland sites. • Non-suitable buffer zone. • Increasing amount of pollution including dust, light. • Disturbance to wildlife from traffic and visitors. • Changing landscape character of area. • Increasing damaging activities like fly-tipping and domestic pets.
The Woodland Trust has been consulted on the revised scheme but at the time of writing the report have not provided further comments.
CAMPAIGN TO PROTECT RURAL ENGLAND:
Object:
• Too much farmland is being lost for development. • Contrary to adopted local plan policy DMB3 (as undermines character and visual amenity of area). • Levels of traffic would be too high – noise and air pollution issues. • Impact on site ecology. • Not enough amenities in Paythorne.
UNITED UTILITIES:
• Concerns around water supply - Extending of water mains needed. • Sustainable draining of surface water. • No wastewater assets in the area.
ENVIRONMENTAL HEALTH:
• The proposed scheme must comply with RVBC’s standard licence conditions for ‘holiday’ caravan sites.
• More information is required regarding the proposed foul drainage arrangement ie details about the existing treatment works (location, type, capacity etc).
• Environmental Health need to ensure that there will be no noise nuisance to neighbouring noise sensitive properties which could arise from these works? LANCASHIRE FIRE AND RESCUE:
• Scheme fully meets all the requirements of Building Regulations Approved Document B, Part B5 ‘Access and Facilities for the Fire Service’
RVBC COUNTRYSIDE:
• All tree protections shall be carried out in strict accordance with the submitted Arboricultural Impact Assessment (July 2021). Shall remain in place throughout construction and shall be maintained during all site preparation/construction works.
• All recommendations mitigation and wildlife enhancement measures for ecology/biodiversity measures as detailed in the ecology report dated 21 July 2021.
• Concerns raised regarding impact on the ancient woodland from additional activity and request a larger buffer as per woodland trusts comments.
The countryside officer has been consulted on the revised scheme but at the time of writing the report have not provided further comments.
ADDITIONAL REPRESENTATIONS:
65 Objections have been received.
Issues of Concern:
Social/Community:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.