Applications - 3/2021/0660 and 3/2021/0661 - HARP

Approved Planning 1 paper

Planning and Development approved this item on Thursday 16 March 2023. Below is the council's own wording, with the papers it was decided on.

Item797a

Resolved

RESOLVED THIS COMMITTEE: The Members were informed that if they are minded to approve the application, it will have to be referred to the Secretary of State. The Secretary of State will then determine whether he wants to call in the application for determination or whether this can be determined at the local level. If the Secretary of State determines that this application can be determined at the local level the application will be APPROVED following the satisfactory completion of a Legal Agreement, which will be within 6 months from the date of the Secretary of State confirming the application will not be called in (or delegated to the Director of Economic Development and Planning in conjunction with the Chairperson and Vice Chairperson of Planning and Development Committee should exceptional circumstances exist beyond the period of 6 months) and subject to the conditions within the Committee report including the conditions amended below and additional conditions below. RESOLVED THAT COMMITTEE: Approve the application 3/2021/0661 subject to the following conditions: 1. The development must be begun not later than the expiration of five years beginning with the date of this permission. Reason: Required to be imposed by Section 51 of the Planning and Compulsory Purchase Act 2004. 2. Prior to the commencement of the development a phasing plan shall be submitted to and approved in writing by the Local Planning Authority. The plan shall detail the proposed phasing of the development hereby approved, including the: · ‘Initial 9-month construction period’ ( the details shall include the dates for the initial 9-month construction period ) and · the ‘Main Project Stage’ (the details shall include the dates for the Main Project Stage). The development thereafter shall be undertaken in accordance with the approved phasing plan. For the purposes of this planning permission, all references to a Phases or Sub-Phase shall be to a Phase or Sub-Phase as shown on the approved plan. Reason: To ensure the proper development of the site in a co-ordinated manner. 3. Prior to the commencement of each phase of the development, pursuant to condition 2, a a. environmental management system (EMS) detailing the procedures to deliver and monitor compliance with all the environmental requirements of the contract and all relevant legislation, standards, regulations and consents; and b. site-specific Construction Environmental Management Plans (CEMPs) in full accordance with the submitted Construction Code of Practice (CCoP) see specific requirements below- condition 27. Shall be submitted to and approved in writing by the Local Planning Authority. Thereafter the development shall be undertaken in accordance with the approved EMS and CEMP REASON: In the interests of the proper managements of the development throughout the construction period. 4. Unless explicitly required by condition within this consent, the development hereby permitted shall be carried out in complete accordance with the proposals as detailed on drawings/ documents: MARL HILL SECTION (3/2021/0661) Document Title Document Reference Planning, Design & Access Statement (including Major Development Test, Drainage Statement, SUDS Proforma and Land Stability Statement) RVBC-MH-APP-003 Construction Traffic Management Plan (with ... view the full minutes text for item 797a
Word for word from the decision Ribble Valley published for this meeting. Source: democracy.ribblevalley.gov.uk

Follow this further

Built from Ribble Valley's papers

What the report saysPro

Report to Planning and Development

RECOMMENDATION FOR PLANNING AND DEVELOPMENT COMMITTEE DEFER AND DELEGATE FOR APPROVAL DATE: 9th March 2023 REF: 3/2021/0661 AND 3/2021/0660 CHECKED BY: APPLICATION REF: 3/2021/0661 AND 3/2021/0660

DEVELOPMENT DESCRIPTION: PROPOSED WORKS FOR AND USE OF REPLACEMENT SECTION OF AQUEDUCT, INCLUDING EARTHWORKS AND ANCILLARY INFRASTRUCTURE INCLUDING: NEW VALVE HOUSE BUILDINGS WITHIN FENCED COMPOUNDS WITH PERMANENT VEHICULAR ACCESS PROVISION. WITH THE INSTALLATION OF TUNNEL SHAFTS; OPEN CUT CONNECTION AREAS AT EITHER END OF THE REPLACEMENT SECTION WITHIN TEMPORARY CONSTRUCTION COMPOUNDS, TO INCLUDE SITE ACCESSES, STORAGE AREAS, PLANT AND MACHINERY, AND DRAINAGE INFRASTRUCTURE. IN ADDITION, A TEMPORARY HAUL ROUTE WITH BRIDGE OVER THE RIVER RIBBLE (AS ONE OF TWO OPTIONS FOR VEHICULAR ACCESS TO THE TEMPORARY CONSTRUCTION COMPOUND); A SERIES OF LOCAL HIGHWAY WORKS TOGETHER WITH A TEMPORARY SATELLITE PARK AND RIDE FACILITY AND A VEHICLE MARSHALLING AREA.

LOCATION

Marl Hill Section. (3/2021/0661) From land northwest of New Laithe Farm off the B6478 Slaidburn Road; and land north of Cross Lane, near Sandy Ford Brook, off the B6478 Slaidburn Road; with highway mitigation works at various locations from Pimlico Link Road, Clitheroe to Slaidburn Road, north of Waddington, via Chatburn Road, Ribble Lane and Grindleton Road; a haul route from land south of West Bradford Bridge to West Bradford Road, west of Healings Farm, West Bradford; a vehicle marshalling facility on land at the Ribblesdale Cement Works, West Bradford Road, Clitheroe and a park and ride facility at the existing Ribblesdale Cement Works car park west of West Bradford Road

Bowland Section. (3/2021/0660) From land near the convergence of the Hornby Road, the Roman Road and Shooters Clough to land west of Newton in Bowland; with highway works at various locations from Pimlico Link Road, Clitheroe to Hallgate Hill, Newton in Bowland via Chatburn Road, Ribble Lane, Grindleton Road and Slaidburn Road; a haul route from land south of West Bradford Bridge to West Bradford Road, west of Healings Farm, West Bradford; a vehicle marshalling facility on land at the Ribblesdale Cement Works, West Bradford Road, Clitheroe and a park and ride facility at the existing Ribblesdale Cement Works car park to the west of West Bradford Road CONSULTEE RESPONSES/ REPRESENTATIONS MADE:

LCC HIGHWAYS: Have been extensively involved in the development of these schemes. Their comments are detailed within the body of the report

LCC ARCHAEOLOGY The Historic Environment Team is of the opinion that the proposed mitigation as outlined in section 10.7.1 of the Environmental Statement, Vol.2 is an appropriate means of mitigating any adverse impact of the proposed development on any archaeological features, known or currently unknown, that might lie within those parts of the proposed development.

LEAD LOCAL FLOOD AUTHORITY: No objection subject to conditions

SENIOR LANDSCAPE ARCHITECT AT LANCASHIRE COUNTY COUNCIL has commented on the applications on behalf of Forest of Bowland AONB

LCC PUBLIC RIGHTS OF WAY: Have commented on the proposed developments.

CRAVEN DISTRICT COUNCIL No comments

ENVIRONMENT AGENCY No objections subject to conditions

RVBC ENVIRONMENTAL HEALTH The air quality assessment concludes [in part]: Appropriate good practice dust mitigation measures would prevent significant effects occurring at offsite locations. Such measures are considered to be normal good practice that would be adopted by the contractor meeting the requirements of the air quality mitigation measures within the CCoP. These would also be agreed with the local authority prior to construction works commencing.

The noise and vibration assessment concludes [in part]: the CCoP includes construction mitigation measures for the management of construction airborne noise and vibration.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Applications: 3/2021/0660 and 3/2021/0661: HARPReport 456 KB DownloadRead as text

At this meeting

Whole meeting
797aApplications - 3/2021/0660 and 3/2021/0661 - HARPThis decision

Who was there

10 of 24 attended
AB
Councillor Alison BrownChair, present
A(
Councillor Anthony (Tony) AustinCommittee Member, present
IB
Councillor Ian BrownCommittee Member, present
SB
Councillor Stella Brunskill JPCommittee Member, present
R(
Councillor Robert (Bob) BullerCommittee Member, present
JC
Councillor Judith ClarkVice-Chair, present
LE
Councillor Louise EdgeCommittee Member, present
KF
Councillor Kerry FletcherCommittee Member, apologies
MF
Councillor Mark FrenchCommittee Member, present
KH
Councillor Kevin Horkin MBECommittee Member, apologies
SO
Councillor Simon O'RourkeCommittee Member, apologies
J(
Councillor James (Jim) RogersonCommittee Member, present

All 24 on the meeting page

More from Ribble Valley Planning and Development

All decisions
MeetingDecisionOutcome
27 Aug 2026 3/2025/0801 - Land to east of Salesbury View WilpshireRESOLVED THAT COMMITTEE: REFUSE PLANNING PERMISSION for the following reasons: 1. The proposed development would be o... Refused Open
27 Aug 2026 3/2022/0317 - Land at Higher Standen Farm and Part Littlemoor Farm ClitheroeRESOLVED THAT COMMITTEE: GRANT planning permission subject to the following condition(s): 1. Unless explicitly requir... Approved Open
27 Aug 2026 3/2026/0442 - Castle Museum Clitheroe Castle Castlegate Clitheroe BB7 1AZRESOLVED THAT COMMITTEE: GRANT planning permission subject to the following condition(s): The development hereby perm... Approved Open
27 Aug 2026 3/2025/0997 - Land off Henthorn Road Clitheroe BB7 3BYRESOLVED THAT COMMITTEE: Application deferred to enable an alternative access directly off Henthorn Road to serve the... Deferred Open
27 Aug 2026 3/2026/0230 - Land to the south of Ribblesdale Primary School west and north of Higher Standen DriveRESOLVED THAT COMMITTEE: DEFER AND DELEGATE to the Director of Economic Development and Planning for approval subject... Deferred Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies