Resolved
RESOLVED THAT COMMITTEE: APPROVE planning permission with the following conditions:- 1. The development hereby approved must be begun not later than the expiration of three years beginning with the date of this permission. REASON: Required to be imposed by Section 51 of the Planning and Compulsory Purchase Act 2004. 2. Unless explicitly required by condition within this consent, the development hereby permitted shall be carried out in complete accordance with the proposals as detailed on drawings: Location Plan 1:2500 Site Plan 1:200 Pump Track Plan 1:250 Drainage Plan 1:250 Pump Track Formation Details 1:25 Site Sections 1:500 / 1:250 REASON: For the avoidance of doubt and to clarify which plans are relevant to the consent hereby approved. 3. No development shall take place until a construction method statement has been submitted to and approved in writing by the Local Planning Authority. The approved statement shall be adhered to throughout the construction period. It shall provide for: i ) The parking of vehicles of site operatives and visitors ii) The loading and unloading of plant and materials iii) The storage of plant and materials used in constructing the development iv) The erection and maintenance of security hoarding v) Wheel washing facilities vi) Measures to control the emission of dust and dirt during construction vii) A scheme for recycling/disposing of waste resulting from demolition and construction works viii) Details of working hours ix) Routing of delivery vehicles to/from site x) Measures to protect users of the public footpath REASON: To mitigate the impact of the construction traffic on the highway network 4. No development shall commence until full details of: (a) the works/contractors’ compound (including any buildings, moveable structures, works, plant, machinery, access and provision for the storage of vehicles, equipment and/or materials); and (b) a scheme for the removal of the works/contractors' compound and the restoration of the land on which it is situated are submitted to and approved in writing by the Local Planning Authority after consultation with Sport England. The works/contractors’ compound shall not be provided and used on the site other than in accordance with the approved details and shall be removed and the land on which it is situated restored in accordance with the approved details before occupation of the development hereby approved. REASON: To protect the playing fields from damage, loss or availability of use. 5. The development hereby approved shall not be first used until full details of a ball stop mitigation fence (or other means of enclosure as deemed appropriate), together with a maintenance and management schedule, informed by a ball strike assessment, have been submitted to and approved in writing by the Local Planning Authority. The approved fence / enclosure shall be installed in full before the development is first used. The fence / enclosure shall be managed and maintained thereafter in perpetuity in accordance with the approved details. REASON: To provide protection for the occupants of adjacent uses and their property from potential ball strike from ... view the full minutes text for item 346b