AI summaryRibble Valley Personnel Committee approves temporary part-time Assistant Planning Officer for Haweswater Aqueduct project, a new EHO housing post, and notes a new temporary Lawyer post.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedNew planning, EHO and lawyer posts
MoneySalary scales £27,694 to £35,412Funded by Section 106 contributions, 5 years secured
What happens nextJob to be advertised and reviewedReview near end of 2-year temporary period
Who it affectsPlanning, environmental health and legal teamsSupports HARP and other council duties
What was decided
Approved a part-time Assistant Planning Officer post for an initial temporary 2-year period. Report 1.7, P40
Approved replacing the vacant part-time Environmental Health Officer (Housing) Scale PO1-4 with a new part-time Environmental Health Officer (Housing and Caravan Licensing) Scale SO2.
Noted a new temporary post of Lawyer (Regulatory and Governance) Scale PO5-8 until end July 2026.
Why
Section 106 funding has been secured for the planning post, with sufficient funds for 5 years; a 2-year initial period is proposed because of the potential for Local Government Reorganisation. Report 1.5, 3.4, P39
Two HARP planning applications were approved in January 2024 and a contractor has been appointed, with detailed design and condition discharge work now underway. Report 2.4, P23, 2.7
What happens next
The post is to be added temporarily to the Council's establishment and advertised. Report P40, 1.4, 3.4
The role is to be reviewed close to the end of the 2-year temporary period. Report 1.5
The money
£27,694 to £29,064 per annum Salary Scale 4 (scp 10-13) for the Assistant Planning Officer Report P44
£30,518 to £32,061 per annum Salary Scale 5 (scp 16-19) for the Assistant Planning Officer Report P44
£33,143 to £35,412 per annum Salary Scale 6 (scp 21-24) for the Assistant Planning Officer Report P44
Options considered
Rejected: Appoint the Assistant Planning Officer on a permanent basis. Proposed as temporary for 2 years due to potential Local Government Reorganisation, with a review at that point Report 3.4, 1.5
Implications
Financial: Section 106 funding is available to support the new planning role, with five payments secured covering about 5 years. Report 1.6, 3.4, P39
Staffing: A vacant part-time EHO (Housing) Scale PO1-4 is being replaced by a new part-time EHO (Housing and Caravan Licensing) Scale SO2, and a temporary Lawyer post is added.
Risk: Resources, technical, environmental, legal, political, reputation and equality and diversity implications have been considered in the risk assessment. Report P7, 1.6, P9, P10, P11, P12, P13, P39
Equalities: The establishment changes are intended to help the Council meet its duties across various sectors of the community. Report P10, P12, P13
Who and where
The Council's planning development management service and the HARP project Report 1.4, P46, P49
Cascade Infrastructure (Strabag, Equitix and GLIL Infrastructure), appointed as contractor for HARP Report 2.6
United Utilities, as procurer of HARP under the Direct Procurement for Customers model Report 2.6
The Council's environmental health and legal teams
Timeline
16 March 2023: Planning and Development Committee resolved to approve both HARP applications, subject to Secretary of State confirmation and a Legal Agreement Report 2.2
19 July 2023: Secretary of State decided not to call in the HARP applications Report 2.3
19 January 2024: Both HARP legal agreements completed and planning applications approved Report 2.4
October 2025: Further Ground Investigation works to start in Ribble Valley Report 2.7
23rd October 2025: Planning and Development Committee considered the HARP update and the new post Report P17, 1.3
2025-10-29: Personnel Committee considered Changes to the Establishment
late-2026 to mid-2028: Highways works expected, dependent on detailed design Report 2.7
end July 2026: End date for the temporary Lawyer (Regulatory and Governance) post
2028: Main construction expected to start on the Bowland Section Report 2.7
mid-2028: Main construction expected to start on Marl Hill Section Report 2.7
Plain English for the jargon
HARP: Haweswater Aqueduct Resilience Programme, a scheme to replace sections of the Haweswater Pipeline
S106: Section 106 planning obligations, used here to fund the new planning post
DPC: Direct Procurement for Customers, a water industry model introduced by Ofwat around 2019
CAP: Competitively Appointed Provider, the third party appointed under DPC
TBM: Tunnel Boring Machine, to be used on more than one section of the aqueduct
RTPI: Royal Town Planning Institute, professional membership relevant to salary scale
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item387
Resolved
RESOLVED THAT COMMITTEE: 1. Approved the inclusion of a part time Assistant Planning Officer within the establishment for a temporary two-year period initially. 2. Approved a new post of part time Environmental Health Officer (Housing & Caravan Licensing) Scale SO2 to replace the vacant post part time Environmental Health Officer (Housing) Scale PO1-4. 3. Noted the decision for a new Temporary post (until end July 2026) Lawyer (Regulatory and Governance) Scale PO5-8.
Word for word from the decision Ribble Valley published for this meeting.Source: democracy.ribblevalley.gov.uk
1.1The Council’s Establishment is a list of all the agreed posts across all Council Directorates. It is important to note that the list of posts approved is crucial for the efficient and effective running of our services and also for us to be aware of our required staffing budgets.
1.2As you would expect changes cannot simply be made to this list. Any proposed changes by Heads of Service must be submitted to CMT giving full and detailed reasons and also the financial implications of such changes and how these could be financed. The grades of all posts are assessed using the Council’s approved Job Evaluation scheme.
1.3Following agreement by CMT any proposed changes are then reported for approval to the relevant Committee and then Personal Committee. In this case this matter was considered by Planning and Development Committee on 23rd October. The decision of the Committee will be reported verbally.
3 CHANGES PROPOSED
1.4Committee approval is sought for the addition of a temporary part time Assistant Planning Officer within the establishment. The full details of the role including the job description, person specification and funding are detailed within the report which went to Planning and Development Committee and appended to this report.
1.5At this stage the role is only proposed for a 2-year period however there is sufficient funding for 5 years and as such the role will be reviewed close to the end of the two- year period.
4 RISK ASSESSMENT
1.6The approval of this report may have the following implications: • Resources – there is sufficient S106 funding available to support the role
• Technical, Environmental and Legal –.contained within the body of the report
• Political – the changes to the establishment will ensure that the Council meets its duties across various sectors of the community
• Reputation – To be a well-managed and efficient Council.
• Equality & Diversity – the changes to the establishment will ensure that the Council meets its duties across various sectors of the community
5 CONCLUSION
1.7Approve the inclusion of a part time Assistant Planning Officer within the establishment for a temporary two-year period initially.
NICOLA HOPKINS DIRECTOR OF ECONOMIC DEVELOPMENT AND PLANNING Appendix 1- Planning and Development Committee Report DECISION
RIBBLE VALLEY BOROUGH COUNCIL REPORT TO PLANNING AND DEVELOPMENT COMMITTEE meeting date: THURSDAY, 23rd OCTOBER 2025 title: HAWESWATER AQUEDUCT RESILIENCE PROGRAMME submitted by: DIRECTOR OF ECONOMIC DEVELOPMENT AND PLANNING principal author: NICOLA HOPKINS – DIRECTOR OF ECONOMIC DEVELOPMENT AND PLANNING
1 PURPOSE
1.1To update Committee on the Haweswater Aqueduct Resilience Programme (HARP) project and to seek approval to appoint a part time Assistant Planning Officer.
2 BACKGROUND 2.1 The Haweswater Aqueduct Resilience Programme (HARP) is a scheme to replace sections of the Haweswater Pipeline. The Aqueduct is a 110km pipeline which runs from the Lake District, through Lancashire and into Greater Manchester. Completed in the 1950’s, the pipeline needs essential maintenance to ensure it can continue to supply customers. The proposed plans include the replacement of six tunnel sections along the pipeline route and nine planning applications have been submitted across seven local planning authorities for approval to carry out the work.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.