RESOLVED – That (1) the business rates baseline for 2017/18 be approved as detailed within the submitted report; (2) the Director of Resources, in consultation with the Cabinet Member for Finance, be authorised to conclude and agree the final business baseline return (NNDR1) due on the 31st January 2017, should the final information yet to be received from DCLG change the baseline for 2017/18; (3) the precepts payment schedule as detailed in paragraph 3.15 of the submitted report, be approved.
Word for word from the decision Rochdale published for this meeting.Source: democracy.rochdale.gov.uk
Title: Setting of the Business Rates Base Public/Private: For Publication 2017/18 Report to: Planning and Licensing Committee Date: Tuesday, 17 January 2017
Cabinet Member: Cabinet Member for Finance Director: Director of Resources
Report Author: Keith Mackenzie Tel: Tel: 01706 926003
1. Purpose of Report 1.1 To seek approval for the setting of the business rates baseline for 2017/18 in accordance with the Local Government Finance Act 1988 and the Non- Domestic Rating Regulations 2013.
1.2To approve the precept payment dates for 2017/18.
2 Recommendations 2.1 Members of Planning and Licensing are requested to approve the draft business rate baseline figure of £56.476m for 2017/18 subject to any changes which may result from the issue of the Department for Communities & Local Government (DCLG) guidance on completion of the 2017/18 business baseline (NNDR1), due in January 2017.
2.2Members of Planning and Licensing are requested to approve that the Director of Resources, in consultation with the Cabinet Member for Finance, be authorised to conclude and agree the final business rate baseline return (NNDR1) due on 31st January 2017 should the final information yet to be received from DCLG change the baseline figure for 2017/18.
2.3That the precepts payment schedule detailed in paragraph 3.15 be approved.
3 Background 3.1 From 1st April 2013 the business rates retention scheme (BRRS) was introduced as part of the move to localise and stimulate business growth at a local level. Under the BRRS the Authority pays 50% of its business rates income to Central Government, 1% to GM Fire and Rescue Authority and retains the remaining 49%.
3.2Central Government has assessed potential retained business rates income and provided a “top up” grant within the Revenue Support settlement to bridge the gap in funding as a result of the move to the BRRS. 3.3 The BRRS is accounted for within the Collection Fund. This account reflects the statutory requirements for the Council to maintain a separate Collection Fund, in relation to the operation of the BRRS and Council Tax. The Fund records all the transactions for billing, payments by council tax/business rates payers, reliefs granted, write offs and payments to the precept authorities, Rochdale Borough Council and Central Government. At the end of each year the surplus/deficit on the Fund is charged to the Council, Central Government and GM Fire and Rescue Authority on the basis of their level of precept on the Collection Fund.
3.4In January of each year the Authority is required to set an estimated business rates income yield for the following year which is to be used to inform Central Government and GM Fire and Rescue Authority of their precept on the Fund on the basis of: Central Government 50% Rochdale BC – General Fund 49% GM Fire and Rescue Authority 1%
3.5The Local Government Settlement 2017/18 included the introduction of the 100% retention of Business Rates for identified regional pilot authorities, including Greater Manchester. The pilots will retain 100% of the business rates income from 2017/18 in lieu of certain grants such as Public Health and Revenue Support grants. The legal framework is due to be published in February 2017 which would change the precept arrangement to 99% Rochdale BC – General Fund and 1% to GM Fire & Rescue Authority.
3.6A Central Government standard form is used (known as the NNDR1) to ensure a common approach for the collection of the business rates income forecast. The final return used in the completion of the 2017/18 estimate has not yet been made available by DCLG. The setting of the baseline for 2017/18 has been prepared on a draft basis until further clarification is received from DCLG.
3.7Setting of the Business Rate Baseline
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.