That the 2016/17 Capital Outturn position be noted; 2. That the budget changes identified in paragraphs 4.3 and 4.4. of the submitted report be noted; 3. That the re-phasing amounts identified in paragraph 4.5. of the submitted report be noted; 4. That the Housing Standards Fund Overspends identified in 4.6. of the submitted report be noted; 5. That the use of £1.000m of Capital Receipts, to forward fund the Junction 19 scheme, as detailed in 4.9.3. of the submitted report be approved. Reason for decision: Effective budget management is critical to ensuring that financial resources are spent in line with the budget and are targeted towards the Council’s priorities. Monitoring enables the early identification of variations against plan and supports effective decision making. Transport for Greater Manchester (TfGM) is expected to fund the feasibility stage for the Junction 19 scheme. This funding is released when the Outline Business Case is approved. Therefore Capital Receipts of £1.000m are to be earmarked to fund the scheme until the release of funding by TfGM is approved.
Word for word from the decision Rochdale published for this meeting.Source: democracy.rochdale.gov.uk
1.1To update Cabinet and the Corporate Overview and Scrutiny Committee on the Council’s 2016/17 Capital Outturn position and enable decision making and action where appropriate in respect of that position.
1.2Effective financial management is essential if the Council is to maintain spending within available resources. It is vital that services make adjustments in spending to ensure that they spend in line with the approved budget.
Recommendation
2.1Cabinet notes the 2016/17 Capital Outturn position.
2.2Cabinet Members note the budget changes identified in paragraphs 4.3 and 4.4.
2.3Cabinet Members are asked to note the re-phasing amounts identified in paragraph 4.5.
2.4Cabinet Members are asked to note the Overspends identified in 4.6.
2.5Cabinet Members are asked to approve the use of £1.000m of Capital Receipts to forward fund the Junction 19 scheme, as detailed in 4.9.3. Reason for Recommendation
3. Cabinet Members are to be kept updated on the latest Capital budgets position as effective budget management is critical to ensuring that financial resources are spent in line with the budget and are targeted towards the Council’s priorities. Monitoring enables the early identification of variations against plan and supports effective decision making.
Key Points for Consideration
Background
4.1The report highlights the final capital position of the Council for 2016/17, and also confirms the position regarding the 2017/18 and 2018/19 programmes as at the March 2017 year end. The 2017/18 Capital programme was presented to Budget Council on 1st March 2017.
4.2The Capital Budget for 2016/17 reported to March Cabinet was £32.110m.
4.3The 2016/17 Capital Budget as at the end of March 2017 is calculated at £32.715m which is £0.605m higher than the Capital budget agreed at March Cabinet. Table 1 below summarises the movements:
Table 1 – 2016/17 Capital Programme
2016/17 2017/18 2018/19
£m £m £m CAPITAL BUDGET APPROVED AT MARCH BUDGET COUNCIL - 46.519 43.258 CAPITAL BUDGET REPORTED AT MARCH CABINET 32.110 - - Rephasing approved to end of December - 17.095 - Budget Changes Increases to Grants/Contributions/Capital Receipt Allocations 5.275 1.000 Sub total 37.385 64.614 43.258 Rephasing identified at the end of March (4.695) 4.695 - Overspend 0.025 - - CAPITAL BUDGET FINAL OUTTURN MARCH 2017 32.715 69.309 43.258 Graph 1 shows the 2016/17 Capital Outturn position by Directorate
GRAPH 1 - Current Budget and Final 2016/17 Spend 16,000
14,000
12,000
10,000 £000
8,000
6,000
4,000
2,000
-
-2,000
Adult Care Children's Economy Neighbourhoods Public Health Total Directorate Directorate Directorate Directorate Directorate £000 £000 £000 £000 £000 £000
Final In Year Spend 1,677 12,364 5,023 13,338 313 32,715
Rephasing 451 1,311 1,718 1,215 - 4,695
(Overspend)/ Underspend - - - - 25 - (25)
2,128 13,675 6,741 14,528 313 37,385 Total Budget
4.3.2 Of the £4.695m budget to be re-phased into future years, £1.566m is funded by Prudential Borrowing.
4.4Changes to Grants/Contributions
4.4.1 The capital expenditure budgets have increased by £3.068m in Children’s Services. The increase in budget is funded by School Revenue contributions to capital (RCCO).
4.4.2 The capital expenditure budgets have increased by £0.272m in Economy Directorate. The increase in budget is funded by external contributions relating to Town Centre schemes.
4.4.3 The capital expenditure budgets have increased by £1.735m in Neighbourhoods Directorate. The increase in budget is funded by external contributions relating to Highways schemes.
4.5Re-phasing identified from 2016/17 to future years
As at the end of March 2017, £4.695m of new re-phasing from 2016/17 into future years has been identified. An overview is provided below, and further details can be found in Appendix 1: 4.5.1 Adult Care (£0.451m)
There is a total of £0.451m requested to be re-phased, as follows:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Finance Update 2026/27 Quarter 1That the 2026/27 forecast positions for Revenue, Capital, and the Collection Fund as at the end of June 2026, as deta...
Best Start Family Hubs ProgrammeThat the Best Start Family Hubs and Healthy Babies Programme grant funding be accepted and expenditure be approved in...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.