That the draft business rate baseline figure of £53.701m for 2018/19 be approved subject to any changes which may result from: • the provisional Local Government Finance Settlement 2018/19 • the issue of the Department for Communities & Local Government (DCLG) guidance on completion of the 2018/19 business baseline (NNDR1), due in January 2018; 2. That the Chief Finance Officer, in consultation with the Cabinet Member for Corporate and Resources, to be authorised to conclude and agree the final business rate baseline return (NNDR1) due on 31st January 2018, should the final information yet to be received from DCLG change the baseline figure for 2018/19; 3. That the precepts payment schedule detailed in paragraph 4.2 of the report be approved. Reason for decision: The Non-Domestic Rating (Rates Retention) Regulations 2013 (SI 2013/452) require billing authorities to notify the Secretary of State and their major precepting authority of their calculation of non-domestic rating income for the following financial year and the estimated surplus/deficit on the Collection Fund by 31st January each year. The figures are produced subject to the DCLG guidance being published and provided, following which the figure in the report may have to be revisited and therefore the delegation to the Chief Finance Officer, in consultation with the Cabinet Member for Corporate and Resources to conclude and agree the final business rate baseline return was sought. Eligible for call in – yes
Word for word from the decision Rochdale published for this meeting.Source: democracy.rochdale.gov.uk
1. For the setting of the business rates baseline for 2018/19 in accordance with the Local Government Finance Act 1988 and the Non-Domestic Rating Regulations 2013.
2. For the precept payment dates for 2018/19.
3. For the delegation of the calculation of the Business Rates base to Cabinet for future years.
Recommendation
2.1Cabinet is asked to approve:
1. That the draft business rate baseline figure of £53.701m for 2018/19 subject to any changes which may result from :
the provisional Local Government Finance Settlement 2018/19 the issue of the Department for Communities & Local Government (DCLG) guidance on completion of the 2018/19 business baseline (NNDR1), due in January 2018.
2. The approval of the Chief Finance Officer, in consultation with the Cabinet Member for Corporate and Resources, to be authorised to conclude and agree the final business rate baseline return (NNDR1) due on 31st January 2018, should the final information yet to be received from DCLG change the baseline figure for 2018/19.
3. That the precepts payment schedule detailed in paragraph 4.2 be approved. Reason for Recommendation
3.1The Non-Domestic Rating (Rates Retention) Regulations 2013 (SI 2013/452) require billing authorities to notify the Secretary of State and their major precepting authority of their calculation of non-domestic rating income for the following financial year and the estimated surplus/deficit on the Collection Fund by 31st January each year.
3.2The figures are produced subject to the DCLG guidance being published and provided, following which the figure in this report may have to be revisited.
Key Points for Consideration
4.1Setting the Business Rates Baseline
4.1.1 From 1st April 2013 the business rates retention scheme (BRRS) was introduced as part of the move to localise and stimulate business growth at a local level. Under the original BRRS the Authority pays 50% of its business rates income to Central Government, 1% to Greater Manchester Fire and Rescue Authority and retains the remaining 49%.
4.1.2 The Local Government Settlement 2017/18 included the introduction of the 100% retention of Business Rates for identified regional pilot authorities, including Greater Manchester. The Government has confirmed that the GM pilot scheme will continue in 2018/19. The pilot authorities will retain 100% of the business rates income in lieu of Revenue Support Grant and Public Health Grant. The precept arrangement under the pilot scheme is 99% to Rochdale BC and 1% to GMCA:GM Fire & Rescue Authority.
4.1.3 Central Government has assessed potential retained business rates income and provided a “top up” grant within the local government finance settlement to bridge the gap in funding as a result of the move to the BRRS.
4.1.4 The BRRS is accounted for within the Collection Fund. This account reflects the statutory requirements for the Council to maintain a separate Collection Fund, in relation to the operation of the BRRS and Council Tax. The Fund records all the transactions for billing, payments by council tax/business rates payers, reliefs granted, write offs and payments to the precepting authorities. At the end of each year the surplus/deficit on the Fund is charged to the precepting authorities on the basis of their level of precept on the Collection Fund.
4.1.5 In January of each year the Authority is required to set an estimated business rates income yield for the following year which is to be used to inform the precepting authorities of their precept on the Fund on the basis of:
Rochdale BC – General Fund 99% GM Fire and Rescue Authority 1%
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Finance Update 2026/27 Quarter 1That the 2026/27 forecast positions for Revenue, Capital, and the Collection Fund as at the end of June 2026, as deta...
Best Start Family Hubs ProgrammeThat the Best Start Family Hubs and Healthy Babies Programme grant funding be accepted and expenditure be approved in...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.