That the Assistant Director for Planning and Economy and the Head of Planning Services be authorised to: · Formally enter into ‘Planning Performance Agreements’; · To agree any subsequent variations or amendments to an approved Planning Performance Agreement; · Secure bespoke fees associated with any Planning Performance Agreements. Reason for resolution: To expedite the use of PPA’s with developers, and to assist with supporting planned growth and investment.
Word for word from the decision Rochdale published for this meeting.Source: democracy.rochdale.gov.uk
1. To delegate power from Cabinet to the Assistant Executive Director for Economy and Planning and Head of Planning Services to allow the Local Planning Authority (LPA) to enter into Planning Performance Agreements (PPA’s).
PPA’s are an important tool for the LPA and provide a framework by which the LPA and developers can consider and assess major development proposals outside of standard timescales for decision making. Crucially, they help to support the delivery of a high quality planning service to developers and investors whilst allowing the LPA to secure additional fee income through discretionary charges to assist with cost recovery.
Recommendation
2. That the Assistant Director for Planning and Economy and the Head of Planning Services be authorised to: Formally enter into ‘Planning Performance Agreements’; To agree any subsequent variations or amendments to an approved Planning Performance Agreement; Secure bespoke fees associated with any PPA;
Reason for recommendation
3. At the present moment in time, authority to enter into a PPA rests with Cabinet. In order to expedite the use of PPA’s with developers, and to assist with supporting planned growth and investment, it is necessary for these powers to be delegated to the Assistant Director for Planning and Economy and the Head of Planning Services rather than requiring a cabinet report each and every time a PPA is required. Key Points for Consideration
4. PPA’s are an important tool for the LPA and provide a framework by which the LPA and developers can consider and assess major development proposals outside of standard timescales for decision making.
Crucially, this approach can help to support the delivery of a high quality planning service to developers and investors whilst also allowing the LPA to secure additional fee income under S93 of the Local Authorities Act 2003 through discretionary charges to support cost recovery.
The nature of PPA’s can vary from a simple agreement to cover an agreed set of milestones for the determination of a planning application through to more complex agreements for the largest and most complex development proposal where, for example, it would extend to cover the life of the project from pre- application stage through to the point at which conditions are discharged.
Crucially, the use of a PPA can assist in providing greater certainty for a developer in respect of the decision timescales for their application and the processes which support that.
For that reason, the use of PPA’s are generally reserved for major development projects and sit as an additional discrete service over and above the existing chargeable ‘Pre-Application Advice Service’. The fees associated with a bespoke PPA are therefore in addition to the pre-application advice charges and are negotiated on a case by case basis. The fees associated with a PPA vary on a case by case basis but as a guide would normally be calculated on the basis of approximately 25% to 40% of the statutory planning fee. In some instances, and on larger schemes, they might also extend to cover costs of staff time over the life of the project and costs associated with commissioning external consultancy advice.
4.1Finally, it is important to clarify the use of a PPA does not imply an obligation on the part of the council to approve the planning application for the proposal.
Alternatives Considered
There are two potential alternatives that have been considered.
The first would be to keep the delegations with Cabinet. However this option is considered to hinder the ability for the LPA to easily enter into PPAs with developers and would not support the delivery of an effective and efficient planning service.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Finance Update 2026/27 Quarter 1That the 2026/27 forecast positions for Revenue, Capital, and the Collection Fund as at the end of June 2026, as deta...
Best Start Family Hubs ProgrammeThat the Best Start Family Hubs and Healthy Babies Programme grant funding be accepted and expenditure be approved in...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.