Resolved
The Sub-Committee approves the allocation of £68,574 of s.106 open space contributions from development at the former Innes School (£67,422) and 22 Rooley Moor Road (£1,152) to fund improvements at Ings Lane Play Area.
Rochdale North Township Delegated Sub-Committee approved this item on Thursday 5 July 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
The Sub-Committee approves the allocation of £68,574 of s.106 open space contributions from development at the former Innes School (£67,422) and 22 Rooley Moor Road (£1,152) to fund improvements at Ings Lane Play Area.
1.1This report seeks approval to allocate funds currently held from s.106 open space contributions in the Spotland and Falinge Ward to contribute to improvements to children’s play and recreation at Ings Lane Play Area.
2.1It is recommended that Committee Members approve the allocation of £68,574 of s.106 open space contributions from development at the former Innes School (£67,422) and 22 Rooley Moor Road (£1,152) to fund improvements at Ings Lane Play Area.
3.1Rochdale Township Members have previously requested that all s.106 open space funded schemes be approved by Members by way of a report to an appropriate committee. A similar process of reporting exists in all other Townships.
3.2A costed scheme has been prepared by the Council’s Environmental Management Service and is supported by the Ward Councillors.
3.3The scheme is within the parameters of the s.106 agreement and the Council’s ‘Provision of Recreational Open Space in New Housing’ Supplementary Planning Document.
Key Points for Consideration
4.1Rochdale Council’s Supplementary Planning Document ‘Provision of Recreational Open Space in New Housing’, states that contributions may be used towards the provision (including 20 years maintenance) and / or improvement of open space within 5 years of receipt. In the case of informal open space, provision should be within 20 minutes walking distance of the development generating the contribution.
4.2s.106 contributions have been received for £68,574 in relation to the development of the former Innes School, Ings Lane (£67,422) and 22 Rooley Moor Road (£1,152).
4.3A scheme prepared by the Council’s Environmental Management Service to improve the existing play area, including additional play equipment aimed at younger users, new safety surfacing throughout the play area, new fencing and access gates, a picnic table with wheelchair access and a roadway / cycle track aimed at younger users.
4.4Members are asked to approve the allocation of £68,574 of s.106 open space contributions to enable the implementation of this project.
Alternatives Considered
4.5The Council is required to spend s.106 contributions in accordance with legal agreements and local and national planning policy. Not bringing forward projects to spend s.106 contributions in accordance with these agreements and policies risks the loss of investment in local facilities, and the refunding of monies held from s.106 contributions where there is a time limited period for spend.
4.6Proposals put forward in this report have been the subject of consultation with Ward Members and reflect their priorities. The use of resources has been considered to maximise the funding available.
Costs and Budget Summary
5.1S.106 contributions are monitored and managed to ensure that they are received and spent in accordance with policy and financial regulations.
5.2The Council’s Environmental Management Service will manage the implementation of this project in accordance with established project management methodology and are able to meet the full cost of the project from the identified budget.
5.3The works will not incur additional revenue costs such as increased maintenance requirements.
5.4The identified funding of £68,574 is made up of s.106 open space contributions from development at the former Innes School, Ings Lane (£67,422) and 22 Rooley Moor Road (£1,152).
Risk and Policy Implications
6.1As identified within the report, contributions from s.106 agreements must be spent within the parameters of each of those legally binding documents. Where money is not spent within the appropriate parameters, then this risks legal challenge, which would present significant financial and reputational as well as legal risk to the Council.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Section 106: Ings Lane Play AreaReport | 101 KB | DownloadRead as text |
Follow Rochdale North Township Delegated Sub-Committee at Rochdale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Jun 2026 | MinutesThat the minutes of the Rochdale North Township Delegated Sub-Committee meeting held on 9 December 2025 be approved a... | Approved | Open |
| 30 Jun 2026 | Rochdale North Township Funds 2026/27That the expenditure, commitments and balances of the Rochdale North Township Revenue and Capital Funds, as detailed ... | Noted | Open |
| 9 Dec 2025 | MinutesThat the minutes of the Rochdale North Township Delegated Sub-Committee meeting held on 7 October 2025 be approved as... | Approved | Open |
| 9 Dec 2025 | Rochdale North Township Funds 2025/26That the expenditure, commitments and balances of the Rochdale North Township Revenue and Capital Funds, as detailed ... | Noted | Open |
| 9 Dec 2025 | Educational Sufficiency Strategy UpdateThat the update to the Education Sufficiency Strategy be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.