That the recommendations of the Highways Scrutiny Study Group as detailed below, be approved:- a) That the Highways Scrutiny Study Group is satisfied and assured on the spending plans for the additional Highways investment funding allocations. b) That the Study Group is further assured on the governance arrangements in place around the monitoring of the Highways contract. c) That the Study Group is generally happy with the performance of the Highways Contract, but have some concerns with the performance indicators not being achieved in relation to pot holes filled within the required time. d) That the Study Group understands that Cabinet is looking at the overall Highways Contract, and request that Scrutiny be able to consider any proposals that Cabinet are considering, in relation to the Highways Contract before a final decision is taken.
Word for word from the decision Rochdale published for this meeting.Source: democracy.rochdale.gov.uk
Report to Communities, Regeneration and Environment Overview and Scrutiny Committee
Purpose of report
To advise on the work of the Highways Scrutiny Study Group and to recommend that its findings, below, be implemented.
2. Study Group Objectives
The Study Group held four meetings; calling on officers of the Council and other agencies; to monitor the additional highways investment and to make recommendations that would hopefully address any issues identified to Cabinet.
3. Key Lines of Enquiry
Monitor the additional Highways investment allocated by Cabinet for 2018/2019 and 2019/2020. Investigate how the performance of the Highways contract. Look at how the Contract is managed. To ensure the Council achieves value for money. Report finding/outcomes to Cabinet via either of the involved Scrutiny Committee’s.
Recommendations
1) That the Highways Scrutiny Study Group is satisfied and assured on the spending plans for the additional Highways investment funding allocations.
2) That the Study Group is further assured on the governance arrangements in place around the monitoring of the Highways contract.
3) That the Study Group is generally happy with the performance of the Highways Contract, but have some concerns with the performance indicators not being achieved in relation to pot holes filled within the required time.
4) That the Study Group understands that Cabinet is looking at the overall Highways Contract, and request that Scrutiny be able to consider any proposals that Cabinet are considering, in relation to the Highways Contract before a final decision is taken.
5. Background information
The Highways Study Group held a series of meetings the first of which considered its aims and objectives, agreeing that the Study should be task specific and focus Key Lines of Enquiry outlined above.
At two subsequent meetings the Study Group received presentations from the Council’s Highways team the additional Highways Funding and the KPI’s surrounding the Highways Contract.
The presentations received focussed on the following:
A break down on the Highways Additional Spend Proposed Carriageway and Footway Programme. Scheme selection principles Benefits of the schemes put forward Deliverability of schemes considered. Break down of the Highways contract, focusing on contractual tasks, such as Reactive Maintenance, Capital Work and Winter Maintenance. KPI’S for Reactive Maintenance, Capital Work and Winter Maintenance.
The Study group had some concerns around the performance of pot holes being filled and although this was accepted as just one element of the whole Highways contract, when Members considered the KPI’s they felt the backlog of unfilled pot holes was high. Members also expressed concern around some parts of the KPI’s that focused on gully cleaning performance.
The Study Group having received these presentations chose to suggest a number of recommendations as outlined above.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Councillor Peter WilliamsCommittee Member, present
PW
Councillor Peter WinklerCommittee Member, expected
Hear about the next one first
Follow Communities, Regeneration and Environment Overview and Scrutiny Committee at Rochdale and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.