That approval in principle be given to the disposal of a parcel of land at Heywood Sports Village, by way of a 125 year lease, as the preferred option for a new Special Free school, subject to the agreement of Sport England as a statutory consultee on the development process and subject to all necessary due diligence being undertaken to ensure the site is fit for the purpose of a Special Free School. 2. That approval in principle be given to the disposal of the alternative site at Bullough Moor playing fields, by way of a 125 year lease, in the event that Sport England is unwilling to support the site at Heywood Sports Village. This would be subject to all necessary due diligence being undertaken to ensure the site is fit for the purpose of a Special Free School. If this option was chosen it was noted that the current community playing fields would also need to be shared with Woodlands Primary School. 3. That authority be delegated to the Assistant Director - Resources (Legal, Governance and Workforce) to carry out the necessary legal due diligence on the preferred site and, if necessary, on the alternative site. 4. That authority be delegated to the Director of Economy to negotiate the Heads of Terms for the disposal of the preferred site or, if necessary, the alternative site. 5. That it be noted that a further report will be submitted once the due diligence exercise had been completed and the proposed Heads of Terms had been negotiated.
Word for word from the decision Rochdale published for this meeting.Source: democracy.rochdale.gov.uk
1.1A bid was submitted from the authority to the DfE for a centrally funded new Special School. The authority has been notified of the successful outcome and the DfE Free School Directorate want to discuss Heads of Term on the proposed disposal of land for the site of the new school.
1.2At a previous meeting of the Informal Cabinet on the 5th Feb 2019 Members of the Cabinet were asked for their views on the short list of possible sites named for the school.
1.3Feedback from Members showed that a new special school on the site of Heywood Sports Village, in an area of currently unused because of sub- surface rubble, was the preferred option.
Recommendation
2.1That Cabinet approves, in principle, to the disposal of a parcel of land at Heywood Sports Village, this would be by way of a 125 year lease, as its preferred option for a new Special Free school, subject to the agreement of Sport England as a statutory consultee on the development process and subject to all necessary due diligence being undertaken to ensure the site is fit for the purpose of a Special Free School.
2.2That Cabinet approves, in principle, to the disposal of the alternative site at Bullough Moor playing fields, by way of a 125 year lease, in the event that Sport England is unwilling to support the site at Heywood Sports Village. This would be subject to all necessary due diligence being undertaken to ensure the site is fit for the purpose of a Special Free School. If this option is chosen members should note that the current community playing fields would also need to be shared with Woodlands Primary School.
2.3That Cabinet delegates authority to the Assistant Director - Resources (Legal, Governance and Workforce) to carry out the necessary legal due diligence on the preferred site and, if necessary, on the alternative site.
2.4That Cabinet delegates authority to the Director of Economy to negotiate the Heads of Term for the disposal of the preferred site or, if necessary, the alternative site.
2.5That Cabinet notes that a further report will be submitted once the due diligence exercise has been completed and the proposed Heads of Term have been negotiated.
Reason for recommendation
3.1A site of approximately 1 to 1.4 Hectares is needed for a Special School Site. Special Schools in particular need additional parking and direct drop off access to give a door to door service to some of its most vulnerable children.
3.2An initial list of 21 possible sites was drawn up and discussed with Estates and Planning within the council.
3.3A list of 5 sites was presented to informal Cabinet on the 5th February 2019 and Members were asked their views.
3.4Feedback from Members showed that a new special school on the site of Heywood Sports Village, in an area that is currently unused because of sub- surface rubble, and identified in the Playing Pitch Strategy as having the potential to be released for development, was the preferred option.
3.5As a statutory consultee to any planning application on the Heywood Sports Village site, Sport England has been asked for pre-application advice and has concluded that they would have no objection to the release of this land, for a new autism school, subject to mitigation for the loss of the playing field land. An appropriate level of mitigation for any playing field loss will be discussed with Link4Life, the Football Foundation and Sport England, being mindful of issues highlighted within the boroughs Playing Pitch Strategy. The appropriate mitigation will need to be agreed prior to the submission of the planning application and form part of the proposals.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Finance Update 2026/27 Quarter 1That the 2026/27 forecast positions for Revenue, Capital, and the Collection Fund as at the end of June 2026, as deta...
Best Start Family Hubs ProgrammeThat the Best Start Family Hubs and Healthy Babies Programme grant funding be accepted and expenditure be approved in...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.