RESOLVED 1. That the Integrated Commissioning Board approves the extension of the Living Well Service contract by a period of six months to 30 th September 2020. 2. That the contract value for the service will remain £1,305,370 per annum for the extension period.
Word for word from the decision Rochdale published for this meeting.Source: democracy.rochdale.gov.uk
1.1The current Living Well Service contract expires on 31st March 2020. There is provision in the contract to extend up to a maximum of two years until 31st March 2022.
1.2This reports seeks Integrated Commissioning Board approval of the extension to the Living Well Service contract for six months until 30th September 2020. This will allow sufficient time to remodel the Rochdale Borough prevention offer and deliver some financial efficiencies.
1.3There is no proposed change to the contract value for the service for the extension period and will remain £1,305,370 per annum.
1.4The Living Well Service is delivered by The Big Life Group and is the current community and family prevention service in the Borough. It offers a wide range of services including support to stop smoking, oral health improvement, healthy weight and physical activity interventions for families along with wellbeing coaches to support people’s motivation and resilience to live a healthy life.
1.5The service also co-ordinates the Community Champions programme, along with a comprehensive volunteering offer which helps support improvements in health and wellbeing e.g. volunteer-led health walks across the Borough.
Recommendation
2.1Integrated Commissioning Board to approve the extension of the Living Well Service contract by a period of six months to 30th September 2020.
2.2The contract value for the service will remain £1,305,370 per annum for the extension period. Reason for Recommendation
3.1The initial contract term for the Living Well Service is soon to expire in March 2020 and to ensure no break in service provision occurs a six month extension has been requested.
3.2An opportunity has been identified to look at re-modelling the current prevention offer in the borough to be able to both achieve some financial efficiencies, improve outcomes and system function. Due to this potential, this is why only a six month extension has been requested despite there being provision in the contract for two years.
3.3At this point there is not time to conduct a full procurement process before the contract expires so at least some level of extension would be required whilst that is carried out should this paper not be approved.
3.4The service is broadly performing well within its current remit so there is low risk in terms of performance in relation to extending the current provision.
Key Points for Consideration
Milestones of the prevention offer review
4.1Below are the key milestones for the prevention offer redesign which is well underway and is based on the premise of the six month contract extension being granted for the Living Well Service.
Milestone Date Scoping phase to establish the remit of the project July -Sept 19
Design phase – develop revised service model in consultation with all key Sept - Nov 19 stakeholders including: Think Tank 7th Oct 19 Presentation for discussion to Public Health Team meeting 24th Oct 19 Wider stakeholder workshop 29th Oct 19
Secure agreement to extend the Health Improvement contract by 6 months End Oct 19 and Inform provider of agreed commissioning intentions
Proposal to ICB / Health and Care SMT 3rd Dec 19 Paper deadline 4th Nov 19
Specification finalised Dec 19
Market engagement event Jan 20
Procurement ITT issued Feb 20
Contract award May 20
New service go-live Oct 20 Costs and Budget Summary
5.
Service Provider Contract End Value of Spend Per date Annum Living Well Service The Big Life Group 30/09/2020 £1,305,370
Risk and Policy Implications
6.1There would be a high risk to service users if this extension was not approved as the provider’s would cease to deliver the services from 01/04/2020. This would have a significant negative impact on the health of our population.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Better Care Fund Budget 2022/23That the revised revenue and capital budgets for the BCF for 2022/23 be approved; 2. That the details of the minimum ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.