That due to the ongoing issues with the budget and project for completing the pitches, that the Cabinet be requested to consider contributing funds to complete the project with the Township agreeing to underwrite the total cost of the completing the project of £18,000 from Township Capital Funds should the Cabinet be not able to provide any assistance.
Word for word from the decision Rochdale published for this meeting.Source: democracy.rochdale.gov.uk
1.1Wardle and Smallbridge Football Club has plans to extend the lower pitch from a junior size to an adult/open age sized pitch and to improve the drainage, to Football Association standards. Once planning was approval the scheme started on site on 18 August 2019. Initial works progressed well until bad weather made the site unworkable and the project team and football club agreed to close the site. The decision was made to close the site by 28 October 2019. All parties agreed the site would close until the spring of 2020.
The site became live once again on 20 April 2020 with the contractor working in line with the Government and Public Health England guidelines in respect of COVID 19. Any ground that had previously been stripped in 2019 had been stockpiled in readiness for future use. As work recommenced and the remainder of the stripping of the site was completed, a number of unforeseen elements were becoming evident:
Additional drainage exposed from the top pitch from adjustment to the embankment would need to be connected to the new drainage formed on the new lower pitch. The amount of soil stripped from the lower pitch did not achieve 200mm depth. Only 75mm could be retained. The amount of soil stripped from the grazing land area did not achieve the 400mm expected depth due to poor quality land. Only a depth of 95mm was retained from the full grazing area.
Options
Option 1: Approve the additional funding for the remainder of the 1000 ton of topsoil to ensure the criteria set by Planning of a 300mm clearance between the separation barrier and the existing ground is met. The amount required to meet this criteria is £18,000. Option 2: Do not approve the additional funding for the 1000 ton of topsoil leaving a shortfall meaning the requirement of a 300mm clearance cannot be met and the risk of the project remaining incomplete.
Option 3: Look for alternate avenues of funding. The risk being that the site becomes dormant until funds are found to complete the project.
Recommendation
2.1It is recommended that option 1 be approved for funding by Pennines Township to ensure the requirements put forward by the Planning Environmental Health Senior Officer to achieve the 300mm separation between the new and old pitch surface is met.
Reason for recommendation
3.1To ensure the sufficient funding is made available for the additional requirement to meet Planning recommendations.
3.2Remove the risk of any pitch users and to mitigate any health and safety concerns.
3.3Option 1 has met the requirement of the Planning Environmental Health Senior Officer.
3.4Future maintenance regimes will benefit from the 300mm topsoil above the separation barrier understanding there should be no impact of disturbance of waste material.
4. Key Points for Consideration
4.1Consideration given for the allowance of on-site validation of the separation layer and the testing of all imported topsoil for contaminants, to comply with a Planning condition in the interest of protecting human health. A cost was associated with this element of work which put existing contingencies under pressure. Therefore adding to pressures to the original budget of the works.
4.2Alternative options were considered such as reducing the 300mm separation layer, however, not meeting the Planning/human health requirements meant a number of options had to be disregarded and option 1 was the only viable approach to completing the works to meet specification.
5. Costs and Budget Summary
5.1Additional topsoil required 1000 ton Pennines Township Budget required £18,000 6. Risk and Policy Implications
6.1Risk of budget shortfall as unforeseen events have meant the availability of the contingency has had to be expended. The additional £18,000 would mitigate the shortfall and cover the overall budget requirement.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Pennines Township Funds 2026/27That the expenditure, commitments and balances for Pennines Township revenue and capital funds in Appendix 1 and 2 to...
Pennines Township Appointments 2026-27That the Terms of Reference (as in Appendix 1 to the report) of the Township Committee be noted; 2. That the appointm...
Pennines Township Funds 2026/27That the expenditure, commitments and balances for Pennines Township revenue and capital funds in Appendix 1 to the r...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.