Highway Maintenance Term Service Contract - Progress Report: April-October 2020
NotedScrutiny1 paper
Communities, Regeneration and Environment Overview and Scrutiny Committee noted this item on Thursday 26 November 2020. Below is the council's own wording, with the papers it was decided on.
That the Highways Maintenance Term Service Contract presentation be noted and welcomed. 2. That future presentations be presented to the Committee twice per municipal year and include more specific information and data relating to the ‘key performance indicators’ that are set out in the Highways Maintenance Term Service Contract. 3. That the next presentation to the Committee include specific information with regard to lining and road marking across the Borough.
Word for word from the decision Rochdale published for this meeting.Source: democracy.rochdale.gov.uk
Report to Communities, Regeneration and Environment Overview and Scrutiny Committee
Overview and Scrutiny Committee Slides November 2020 Summary In March 2019 Balfour Beatty presented to RBC and members. In the presentation we made 8 commitments to the council should we be awarded the 2 year contract extension. Commitments: 1. We offered a 3.8% discount on future capital spend. Plus a £50,000 lump sum for the £7m already spent (this equated to a minimum lump sum discount of £225,000) 2. We committed to delivering a minimum of 20% in social value of the contract value in the extension period. 3. We committed to maintaining our dedicated team in Rochdale 4. Maintain productivity levels for routine gulley maintenance (i.e. maintain resource levels as this year). This involved the provision of an additional gully cleaning waggon when required 5. Maintain productivity levels for pothole repairs and maintain overdue orders at an acceptable level 6. Work closely with RBC Highways Team to deliver a better pothole service 7. A report direct to Overview and Scrutiny Committee (Performance & Social Value) 8. Detailed monthly activity/productivity report sent to Highway Champions
2 What We Achieved – 1. Discount
Discount.
• The first two payments of discount equating to £100,000 (£50,000 each) has now been released to the council. This can now be re-invested back into the highways network.
• The proposed discount was £225,000 (based on a percentage discount on works delivered outside of the highways capital programme), however the current discount now amounts to £243,000.
• There are still schemes and works to be completed in 2021/22 which means more discount will be applied before contract completion.
3 2. Delivering Social Value
Our social value infographic is updated every quarter and highlights the added benefit in the contract including: We have delivered 22% of the contract in social value to date.
• £12.9M realised in social value to date • 5 apprentices on the contract (including 3 being sponsored for degrees) • 8.4M litres of rain water harvested used • 90% of staff employed are local • Multi-use hybrid vehicles on site including several electric Vans • 72% of all expenditure spent local
4 Social Value- Magazine donation
- We procured 1600 magazines from a magazines publishing house as well as 20 pallets of thermal socks and bedding which we distributed to charities across Rochdale in partnership with RBC. To help the vulnerable during the COVID-19 pandemic
5 Social Value – NHS and Poppy
We recently undertook lining across the borough to mark the celebration of key workers and remembrance day.
6 3. Dedicated Team
We have increased our staffing levels over the past few months to accommodate the growing programme of work and supply more supervisors and commercial resource.
We also have a full time dedicated health and safety advisor on the contract.
Our team on the right:
7 Dedicated Team – Continued
85% of our workforce live in Rochdale
30% of our workforce are either Graduates or apprentices
Contract has 5 current apprentices and 3 No Graduates
Training plan in place for all staff to maintain and develop their skills
We are sponsoring 3 apprentices through degrees
We have access to a pool of 30 employees from our neighbouring Manchester contract were we share resilience.
8 4. Routine Gulley Maintenance As part of the extension we agreed to ensure we always maintained enough gully cleaning vehicles to manage the service and complete the 44,000 gullies on time. As per the below we are in front of target and are looking to finish the annual clean early. April May June July Aug Sept Oct Nov Dec Jan Feb March Target Cumulative 2651 7015 11226 15775 20717 25659 30601 34136 35820 38504 41350 44000 Actual Cumulative 6761 10255 13478 17286 21391 25852 30631
9 5. Maintain Productivity Levels for Potholes
● As part of the extension we agreed to procure additional resource, should we fall more than 50 orders behind.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Communities, Regeneration and Environment Overview and Scrutiny Committee at Rochdale and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.