That planning permission be granted, subject to the Conditions that were detailed in the Committee’s submitted report and in the Planning Officer’s Update Report (published on the day of the meeting ) and to the completion of a Section 106 agreement to secure: (i) The provision of affordable housing on site in accordance with the approved plans and the affordable housing scheme; (ii) A financial contribution towards the provision of additional primary school places calculated by the pupil yield of the development multiplied by the relevant basic need funding allocation (currently £308,000.25 but the final calculation shall be based on the multipliers in place at the relevant time); (iii) A financial contribution towards the provision of additional secondary school places calculated by the pupil yield of the development (0.1 per dwelling) multiplied by the relevant basic need funding allocation (currently £ 154,000.1 but the final calculation shall be based on the multipliers in place at the relevant time); (iv) A financial contribution towards the provision of outdoor sport and recreation facilities at Littleborough Sports Centre in accordance with the Council’s SPD: Provision of Recreational Open Space in New Housing; (v) A scheme for the provision, implementation and management of a Local Area of Play (LAP). 2. The Head of Planning Services be authorised to grant planning permission upon execution of the above S106 agreement.
Word for word from the decision Rochdale published for this meeting.Source: democracy.rochdale.gov.uk
3.1It is recommended that the Planning and Licensing Committee resolves it is minded to GRANT planning permission subject to completion of a Section 106 agreement to secure:
(i) The provision of affordable housing on site in accordance with the approved plans and the affordable housing scheme; (ii) A financial contribution towards the provision of additional primary school places calculated by the pupil yield of the development multiplied by the relevant basic need funding allocation (currently £308,000.25 but the final calculation shall be based on the multipliers in place at the relevant time); (iii) A financial contribution towards the provision of additional secondary school places calculated by the pupil yield of the development (0.1 per dwelling) multiplied by the relevant basic need funding allocation (currently £154,000.1 but the final calculation shall be based on the multipliers in place at the relevant time); (iv) A financial contribution towards the provision of outdoor sport and recreation facilities at Littleborough Sports Centre in accordance with the Council’s SPD: Provision of Recreational Open Space in New Housing; (v) A scheme for the provision, implementation and management of a Local Area of Play (LAP).
Reason for recommendation
4.1Although there would be an increase of 4 dwellings since the previous permission for 96 houses on the site (Ref: 19/00262/FUL), revised plans show that the proposed development would still sympathetically integrate itself into the existing urban grain of the surrounding area. The site layout has been reconfigured due to Environment Agency (EA) guidance and requirements to cap the borehole for contamination and safety reasons. As a consequence of this the previously approved artesian stream feature is proposed to be infilled.
The revisions made are considered to maintain an attractive relatively green and spacious modern housing scheme, with ample public open space and connections to neighbouring developments. Sufficient separation distances and relationships between proposed and existing properties would also be provided to ensure that the living conditions of neighbouring residents and future occupiers would not be unduly affected.
The previously approved ground works and re-profiling of levels have been completed on site. An email has been received from the EA which confirms that the levels are agreed in line with the submitted FRA (which are identical to the previously approved site levels). The EA has also confirmed that they are now completing the review of the modelling received to allow them to update the Flood Risk Maps in due course. On the balance of probabilities, the LPA are therefore satisfied that the area of the site in which the proposed houses are to be sited no longer lies within FZ2. In these circumstances, the carrying out of a flood risk sequential test is therefore considered to be unreasonable and unnecessary.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.