RESOLVED 1. That the Draft Lower Falinge Supplementary Planning Document be approved for consultation. 2. That the Head of Planning be approved to amend the document prior to consultation. Reason for consultation Supplementary Planning Documents build upon and provide more detailed advice or guidance on the policies in the Local Plan. Regulations 11 to 16 of the Town and Country Planning (Local Planning) (England) Regulations 2012 set out the requirements for producing SPDs. Regulation 12 requires that consultation is undertaken prior to the adoption of an SPD.
Word for word from the decision Rochdale published for this meeting.Source: democracy.rochdale.gov.uk
DRAFT LOWER FALINGE SUPPLEMENTARY PLANNING DOCUMENT (SPD)
STATEMENT OF CONSULTATION
February 2021
0 CONTENTS
Page
1. Introduction 2
2. Participation and consultation 2
3. Location where documents can be viewed 6
4. Advice and Assistance 6
Appendices 7
1 1. INTRODUCTION
1.1The Lower Falinge Supplementary Planning Document (SPD) has been produced by the Council to guide redevelopment of this area. In order to ensure that appropriate public consultation takes place, Supplementary Planning Documents (SPD) are required to be accompanied by a statement setting out how the Local Planning Authority will comply with the Council’s Statement of Community Involvement (SCI).
1.2This Consultation Statement has been prepared in line with Regulation 12 (a) of the Town and Country Planning (Local Planning) (England) Order 2012, which states that, before a council adopts a Supplementary Planning Document (SPD), it must produce a statement setting out: i. The persons the local planning authority consulted when preparing the supplementary document; ii. A summary of the main issues raised by those persons; iii. How those issues have been addressed in the supplementary document.
1.2This statement sets out how the public and other stakeholders will be consulted upon the SPD. Following the consultation period, this statement will be expanded to summarise the comments received during the consultation period, including details of how the issues raised have been dealt with in working towards a final SPD for adoption.
1.3This SPD has been produced in accordance with the Town and Country Planning (Local Planning) (England) Regulations 2012.
2. PARTICIPATION AND CONSULTATION
Early Consultation
2.1Lower Falinge has been recognised as needing investment in order to provide the tenants and residents with a better mix and quality of homes and better opportunities. Rochdale Boroughwide Housing (RBH) commissioned Levitt Bernstein and GVA (now Avison Young) in early 2017 to produce a Masterplan for an area that included Lower Falinge to explore possible options for long term investment in the area.
2.2A Draft SPD for a wider area was produced and consulted on in 2019. However, as a result of comments raised during consultation of the SPD, in respect of part of the area covered by that SPD it was decided that the document would be amended to remove that area from the document before consultation was undertaken on a revised document.
2.3As such, the Draft SPD now relates to an area principally focussed on the Lower Falinge estate and the land to the east up to Whitworth Road. The boundary on the area covered by the SPD is shown on the map within the Draft SPD.
2.4The RBH Masterplan was subject to consultation with residents, businesses and local stakeholders within the area. The public consultation process included the distribution of leaflets, letters, surveys, online consultation portal, drop-in sessions and a series of workshops in order to introduce various development options. To date there have
2 been a series of public workshops from 2017 to date, attended by the local community, stakeholders and Elected Members. These workshops, which have helped to inform the key aims and objectives of the neighbourhood and to develop the options for future investment. Although this consultation did include areas that are no longer within the SPD boundary, the feedback in relation to Lower Falinge area is still considered relevant in terms of this SPD.
2.5The Masterplan was developed from January - Summer 2017 across three workshops, which have helped to inform the key aim and objectives of each neighbourhood. There have been a number of workshops since this date and online consultations.
Workshop 1
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Appointment of Opposition SpokespersonThat it be noted that there was no constitutional requirement to appoint an Opposition Spokesperson; 2. That no Oppos...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.