Resolved
That the report be noted.
Corporate Overview and Scrutiny Committee noted this item on Tuesday 14 September 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted.
1. To recommend the budget guidelines and timetable to be used in preparing the detailed 2022/23 Budget and provisional budgets for 2023/24 and 2024/25.
2. To provide an updated budget position for the Council for 2022/23 to 2024/25.
2.1Cabinet is requested to consider and approve the following:
2.1.1 The proposed budget timetable detailed at Appendix 1.
2.1.2 The revenue assumptions, detailed in Appendix 2, to be incorporated into the budget setting process.
2.1.3 The revenue budget principles detailed in Appendix 3.
2.1.4 The capital budget principles detailed in Appendix 4.
2.2Cabinet is asked to note the Revenue Budget update provided in this report.
3.1Under the Budget & Policy Framework, Cabinet is required to approve the proposed guidelines and timetable for setting the 2022/23 Budget and Provisional Budgets for 2023/24 and 2024/25 by September.
Key Points for Consideration 4.1 Timetable
4.1.1 The Council’s budget must be approved by full Council before 11th March each year. This is a statutory requirement. The process begins in July with approval being sought for the assumptions and principles on which the budget is to be based. These will be used as a part of the determination of the overall budget position.
4.1.2 Throughout the year, we consult on the budget. Financial projections are updated as further information becomes available in relation to the Local Government Finance Settlement and other known changes, including local decisions. The updated budget and feedback from any consultations are reported back to Cabinet in February with recommendations for Budget Council, who in turn set the budget.
4.1.3 Services are notified of their budgets following Budget Council in February.
4.1.4 The full budget timetable is provided at Appendix 1.
4.2Revenue Budget update 2022/23 to 2024/25
4.2.1 As part of the budget setting process, the Council makes a number of assumptions in respect of the key elements of the Council’s revenue budget. Appendix 2 provides a summary of these assumptions for 2022/23, 2023/24 and 2024/25.
4.2.2 Provisional budget assumptions for 2022/23 and 2023/24 were approved at Budget Council 3rd March 2021. The budget assumptions have been reviewed and updated in the light of the ongoing financial implications of the pandemic and other known factors. Future reports will make Cabinet aware of any changes that impact on the budget assumptions.
4.2.3 It must be noted that there is significant uncertainty as to the level of government funding for local authorities beyond the current financial year. The government provided a one-year funding settlement for 2021/22, and the wider reforms to local government funding were delayed till 2022/23 at the earliest. No further information on the proposed reforms has been released by the government at this stage.
4.2.4 There is also significant uncertainty over the ongoing impact of the pandemic on the Council’s expenditure and income levels for future years.
4.2.5 The updated Budget position for 2022/23 to 2024/25 is based on the best estimates at this point in time, and these will be reviewed throughout the budget process as more information becomes available.
4.2.6 Table 1 summarises the updated Budget position 2022/23 to 2024/35 based on the changes to budget assumptions, and the proposed mitigating actions in order to achieve a balanced budget for 2022/23. Further detail is provided in sections 4.3 to 4.6 of this report. Table 1 Updated Budget Gap 2022/23 to 2024/25
2022/23 2023/24 2024/25 £m £m £m
Budget Council March 2021 5.127 13.380 15.548
Changes to Budget Assumptions 2.673 2.672 2.664
Updated Budget Gap 7.800 16.052 18.212
Mitigating Actions (7.800) (5.900) (5.900)
Updated Budget Gap 0.000 10.152 12.312
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Budget 2022/23 to 2024/25: Guidelines, Timetable and Budget UpdateReport | 414 KB | DownloadRead as text |
Follow Corporate Overview and Scrutiny Committee at Rochdale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Sep 2026 | People Strategy Progress 2026Resolved – 1. That progress made against the People Strategy 2024-2026 be noted. 2. That the implementation of the re... | Noted | Open |
| 7 Sep 2026 | Finance Update 2026/27 Quarter 1Resolved – 1. That the 2026/27 forecast positions for Revenue, Capital, and the Collection Fund as at the end of June... | Noted | Open |
| 7 Sep 2026 | Children’s Services Q1, 2026/27 Revenue Monitoring UpdateResolved – 1. That the Children’s Services forecasted financial position for 2026/27 at Quarter 1 and related service... | Noted | Open |
| 7 Sep 2026 | Notice of Key Decisions and Private ItemsResolved - That the Notice of Key Decisions and Private Items be noted | Noted | Open |
| 7 Sep 2026 | Work Programme 2026-27 and Action Tracker 2026-27It was agreed that a report on Digital, Data and Technology be submitted to the Committee meeting scheduled for 19 Oc... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.