That the Quarter 3 monitoring information as at December 2021 period be noted; 2. That the remaining contingencies being held for budgets not yet allocated in 2021/22 of £44k, following an allocation of £63k against the forecast overspend on the equipment store budget be noted; 3. That the forecast underspend against capital budgets of £1,422k in relation to the Disabled Facilities Grant (DFG) be noted and the carry forward of any unspent capital budgets to 2022/23 under Council procedures be agreed; 4. That it be agreed that the £150k budget previously identified for the Adaptations to Autism capital scheme be transferred to the Adult Social Care and Health Integration Hubs capital scheme. Reasons for decision: The Strategic Place Board (SPB) have ultimate sign off of the BCF budget as mandated in the BCF Policy Framework and Planning Guidance. The SPB have delegated responsibility for the BCF to the ICB. The revised 2021/22 budget for the BCF was agreed by the ICB in March 2021, this report provided an update on the forecast position against those budgets.
Word for word from the decision Rochdale published for this meeting.Source: democracy.rochdale.gov.uk
1. At its March 2021 meeting the Integrated Commissioning Board (ICB) agreed the revised 2021/22 budgets for the Better Care Fund (BCF). This report updates the ICB and the Strategic Place Board (SPB) with the Quarter 3 (April to December 2021) budget monitoring for the BCF for the financial year 2021/22.
Recommendations
2.1ICB notes the Quarter 3 monitoring information as at December 2021 period end.
2.2ICB notes the remaining contingencies being held for budgets not yet allocated in 2021/22 of £44k, following an allocation of £63k against the forecast overspend on the equipment store budget.
2.3ICB notes the forecast underspend against capital budgets of £1,422k in relation to the Disabled Facilities Grant (DFG) and recommends under Council procedures the carry forward of any unspent capital budgets to 2022/23.
2.4ICB approves that the £150k budget previously identified for the Adaptations to Autism capital scheme be transferred to the Adult Social Care and Health Integration Hubs capital scheme.
Reason for recommendation
3. The Strategic Place Board (SPB) have ultimate sign off of the BCF budget as mandated in the BCF Policy Framework and Planning Guidance. The SPB have delegated responsibility for the BCF to the ICB. The revised 2021/22 budget for the BCF was agreed by the ICB in March 2021, this report provides an update on the forecast position against those budgets.
Key Points for Consideration
4.1The BCF revised budget was set at the ICB meeting in March 2021 in line with the BCF Policy Framework and Planning Guidance for 2017-19.
4.2The partners must have a Section 75 agreement to support the BCF budget and this was approved by the ICB at its September 2017 meeting. This has been updated and forms part of the overall pooled Health and Social Care Section 75 agreement for 2021/22 reported to June 2021 ICB.
Alternatives Considered
4.3It is a requirement of the NHSE guidance to produce a budget for 2021/22 which the ICB approved at its March 2021 meeting. This report updates the monitoring against the 2021/22 budget which is a requirement of the Section 75 agreement. Therefore there are no alternatives to consider.
Costs and Budget Summary
5.1Table 1 shows the updated 2021/22 revenue budget and the forecast financial position as at the end of December 2021.
2 Table 1 Revenue Budget and Forecast at December period end (Quarter 3)
Line 2021/22 2021/22 Scheme Variance No Budget Forecast
Revenue Expenditure £'s £'s £'s
1 Funding of Social Care Services 19,925,737 19,925,737 - Additional Funding in Adult Social Care 2 notified in Spring Budget 2017 1,568,389 1,568,389 -
3 Care Act Implementation 209,094 209,094 - Carers Services Carers -universal 4 services 397,750 397,750 - Carers night sitting 5 service - dementia 81,600 81,600 - Carers sub total 479,350 479,350 - Reablement Services
Reablement - dementia 6 support workers 88,336 88,336 - Reablement - Intermediate Care 7 dementia flexible workers 65,434 65,434 - Reablement - mental health outreach 8 workers 112,852 112,852 - Reablement - memory 9 clinic dementia workers 53,743 53,743 - Reablement - carers life 10 after stroke 137,474 137,474 - Reablement - 11 equipment loan store 1,057,188 1,057,188 -
Reablement sub total 1,515,027 1,515,027 -
3 Intermediate tier service
Reablement (STAR's) 12 plus to support the new service 190,392 190,392 - Pennine Acute ITS 13 contract 6,050,076 6,050,076 - Pennine Acute CQUIN - 14 new funding from CCG 75,626 75,626 - Winter Pressure 15 Funding Expenditure 1,108,358 1,108,358 - Contingency for 16 revenue schemes 43,740 - (43,470)
Intermediate Care sub total 7,468,192 7,424,452 (43,470)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Better Care Fund Budget 2022/23That the revised revenue and capital budgets for the BCF for 2022/23 be approved; 2. That the details of the minimum ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies