Resolved
That the Neighbourhoods Directorate Plan 2022-23: Quarter 1 Performance Update be noted. 2. That the additional information, as detailed above, be circulated to the Committee.
Communities, Regeneration and Environment Overview and Scrutiny Committee noted this item on Tuesday 20 September 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Neighbourhoods Directorate Plan 2022-23: Quarter 1 Performance Update be noted. 2. That the additional information, as detailed above, be circulated to the Committee.
Neighbourhoods Directorate Plan 2022-23 Action Plan Due Date Status % Complete
N2201 Support the Council in reaffirming its strategic and corporate priorities over the next 3 years 31 March 2023 17%
Ref. Name Due Status % Complete
N2201.A Complete draft corporate plan 31 December 2022 35%
Desk top research carried out to capture priorities in other council strategies and plans to ensure there will be synergy across key council documents. Consultation undertaken with council employees at staff engagement sessions - feedback will inform the drafting. Further consultation planned including with senior leaders, residents and partners - hoping to facilitate an online survey and face to face workshops during Sept/Oct. Develop and finalise a new Corporate Plan for 23/24-26/27 through appropriate N2201.B 31 March 2023 0% stakeholder engagement Desk top research carried out to capture priorities in other council strategies and plans to ensure there will be synergy across key council documents. Consultation undertaken with council employees at staff engagement sessions - feedback will inform the drafting. Further consultation planned including with senior leaders, residents and partners - hoping to facilitate an online survey and face to face workshops during Sept/Oct.
N2202 Support rollout of the Census 2021 outputs 30 September 2022 20%
Ref. Name Due Status % Complete Make available the results of the Census 2021 by publishing data in appropriate formats N2202.A 30 September 2022 20% and disseminating to key stakeholders in line with ONS timescales for data release Original due date for this indicator was Sept 2022. This has been amended to March 2023 to align with the Office for National Statistics (ONS) timetable for data releases. The first data was published on 21 March 2022 (population and household estimates). The data is available to the public via the ONS website. The Corporate Policy Team prepared a summary document which was circulated across the council. The next data releases are as follows:
Topic summary data (e.g. ethnicity, education, health etc.) - Autumn / Winter 2022
Area profiles (will allow for comparisons of data for different topics and local areas) - Autumn/ Winter 2022
Cross tabulated data (will allow for exploration of relationships between the data) - Winter 2022 - Autumn 2023
Directorate Plan New. v4_2 Page 1 Of 23 Neighbourhoods Directorate Plan 2022-23 Action Plan Due Date Status % Complete
N2203 Progress the climate change policy agenda by implementing and overseeing key actions from 31 March 2023 40% the Climate Change Strategy and Action Plan.
Ref. Name Due Status % Complete Ensure successful delivery of Phase 1 of the Public Sector Decarbonisation Scheme is N2203.A 30 June 2022 90% completed
We have now completed most of our projects under phase 1 of the PSDS. Some commissioning of projects and electrical connection work will continue into August and September. The final grant claim submitted to the Greater Manchester Combined Authority for our projects was successfully submitted before the deadline date of the end of July along with the certification (audit) letter which was signed off by the s.151 officer. The final grant total for our PSDS projects was £11,593,064. Before the PSDS1 programme closed down, we became aware that there was an underspend on the overall Greater Manchester programme which would be returned to Salix at the end of the programme. We approached GMCA about potential funding for Solar PV and battery storage projects for a number of our maintained schools and successfully obtained an additional £571k grant to implement Solar PV and battery storage schemes for Alkrington, Shawclough and Lowerplace Primary Schools.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix: Neighbourhoods Directorate Plan Actions: Q1 2223Appendix | 1.4 MB | DownloadRead as text |
PDF |
Neighbourhoods Directorate Plans 2022-23: Quarter 1 Performance UpdatePlan | 164 KB | Download |
Follow Communities, Regeneration and Environment Overview and Scrutiny Committee at Rochdale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Sep 2026 | GMCA Joint Health Scrutiny CommitteeResolved that the minutes of the meetings held on 16 th June 2026 and on 14 th July 2026 be noted. | Noted | Open |
| 8 Sep 2026 | GMCA Police, Fire and Crime PanelResolved that the minutes of the meeting held on 29 th June 2026 be noted. | Noted | Open |
| 8 Sep 2026 | Notice of Key Decisions and Private ItemsResolved that the key decision document and notice of private items be noted. | Noted | Open |
| 8 Sep 2026 | Work Programme 2026-27Resolved that the proposed Work Programme for 2026/27 be noted. | Noted | Open |
| 21 Jul 2026 | GMCA Joint Health Scrutiny CommitteeResolved that the minutes of the held on 17 th March 2026 be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.