Resolved 1. That the procurement of the Rochdale Highway Framework be approved; 2. That the award of the Rochdale Highway Framework to the successful bidders be delegated to the Director of Neighbourhoods in consultation with the Portfolio Holder for Highways and Housing and the Director of Corporate Services; 3. That approval to award capital and revenue work packages to the successful bidders of the Rochdale Highway Framework be delegated to the Director of Neighbourhoods and the Portfolio Holder for Highways and Housing; 4. That the Assistant Director for Legal and Governance be authorised to prepare and execute any necessary legal agreements in accordance with the Council Constitution. Reasons for the decision Cabinet approval is required to allow highway officers to engage STaR procurement to commence the procurement process and engage with potential suppliers. Delegated approval is required to authorise officers to deliver future highway capital programmes and various revenue works to the successful bidders.
Word for word from the decision Rochdale published for this meeting.Source: democracy.rochdale.gov.uk
Report title: Proposed Rochdale Highway Framework Report to: Cabinet Date of meeting: Tuesday, 14 February 2023 Cabinet Portfolio Holder: Cabinet Member for Highways & Housing Report of: Director of Neighbourhoods Public or private: Public Key Issue?: Yes – Capital expenditure in excess of £500,000 Published on the Forward Plan: January 2023
1. Report summary 1.1 The 2015-2022 Highway Maintenance contract with Balfour Beatty Living Places expired on 31 March 2022.
From the 1 April 2022 Rochdale BC capital funded highway works have been delivered via a combination of GM framework suppliers, competitively tendered contractors, and individual works orders/quotations. The procurement of these works is time consuming and onerous owing to the different procurement processes. In addition these frameworks do not always allow the Council to engage with local suppliers.
From the 1 April 2022 Rochdale BC revenue funded highway works have been delivered by the in-house highway operational service supported by local sub-contractors when necessary at times of excessive workload.
Approval is sought to procure a Rochdale Framework Contract to allow suppliers to bid for, and if successful, deliver highway capital and revenue works. 2. Recommendations 2.1 a. Cabinet approves the procurement of the Rochdale Highway Framework
b. Cabinet delegate award of the Rochdale Highway Framework to the successful bidders to the Director of Neighbourhoods in consultation with the Portfolio Holder for Highways & Housing and the Director of Resources. c. Cabinet delegate approval to award capital and revenue work packages to the successful bidders of the Rochdale Highway Framework to the Director of Neighbourhoods and the Portfolio Holder for Highways and Housing
d. The Assistant Director for Legal and Governance be duly authorised to prepare and execute any legal agreements in accordance with the Council’s Constitution 3. Reason for recommendation 3.1 Cabinet approval is required to allow highway officers to engage STaR procurement to commence the procurement process and engage with potential suppliers. Delegated approval is required by Cabinet to authorise officers to deliver future highway capital programmes and various revenue works to the successful bidders. 4. Alternatives considered 4.1 Continue to order works via the following procurement methods: Utilise existing frameworks which are available via STaR Procurement Produce bespoke competitive tenders Obtain 3 quotations/mini competition for low value works in line with Corporate Procurement Rules Place one off orders for small works in line with Corporate Procurement Rules
5. Key information 5.1 Highway capital funded works are currently being delivered via a combination of GM framework suppliers, competitively tendered contractors, and individual works orders/quotations. The procurement of these works is time consuming and onerous owing to the different processes to engage with suppliers. In addition these frameworks do not always allow the council to engage with local suppliers of highway works.
Highway revenue funded works are currently delivered via the council’s in- house operational service team. The timely delivery of these works can be put at risk by limited resources within the service. Being able to call off additional plant, labour and material supplies quickly from a single approved source will reduce the risk of the highway network deteriorating and hence bolster our ability to defend any damage claims against the council.
It is proposed to procure a bespoke Rochdale Highway Framework to deliver capital works and provide resilience for the delivery of revenue works.
Delivery of Capital Works proposed as follows: • Lot 1 – Minor Civils • Lot 2 – Carriageway Surfacing • Lot 3 – Proprietary Carriageway Treatments • Lot 4 – Road Markings & High Friction Surfacing
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Finance Update 2026/27 Quarter 1That the 2026/27 forecast positions for Revenue, Capital, and the Collection Fund as at the end of June 2026, as deta...
Best Start Family Hubs ProgrammeThat the Best Start Family Hubs and Healthy Babies Programme grant funding be accepted and expenditure be approved in...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.