Health & Social Care Better Care Fund Budget Outturn Report 2022/23
NotedCommittee1 paper
HMR Integrated Care Partnership Committee noted this item on Tuesday 30 May 2023. Below is the council's own wording, with the papers it was decided on.
That it be noted that the revenue spend for 2022/23 was on budget; 2. That it be noted that there was an overspend on Social Care Services which was mitigated by a underspend against the equipment loan store; 3. That the £82k equipment loan store budget underspend be allocated to funding of Social Care Services to mitigate the reported pressure in Adult Care for the increased costs in placements; 4. That the underspend against capital budgets of £1,492k in relation to the Disabled Facilities Grant (DFG) and £71k the Health Integration Hubs be noted and that, under Council procedures, the carry forward of any unspent capital budgets to 2023/24 be agreed. Reasons for decision: The Locality Board have responsibility for the BCF budget as mandated in the BCF Policy Framework and Planning Guidance. The NHS GM ICB and the Council have delegated responsibility for the BCF to the Locality Board. The revised 2022/23 budget for the BCF was agreed by the ICB in May 2022, this report provides an update on the forecast position against those budgets. Alternatives considered: It is a requirement of the NHSE guidance to produce a budget for 2022/23 which the ICB approved at its May 2022 meeting. This report updates the monitoring against the 2022/23 budget which is a requirement of the Section 75 agreement. Therefore there are no alternatives to consider.
Word for word from the decision Rochdale published for this meeting.Source: democracy.rochdale.gov.uk
Report to HMR Integrated Care Partnership Committee
Report title: Health & Social Care Better Care Fund Budget Outturn Report 2022/23 Report to: Locality Board Date of meeting: 30th May 2023 Cabinet Portfolio Holder: Cabinet Member for Finance and Corporate Report of: Jonathan Evans (Locality Director of Strategic Performance – Health & Social Care) Public or private: Public Key Issue?: No Published on the Forward Plan: Yes
1. Report summary
1.1At its May 2022 meeting the Integrated Commissioning Board (ICB) agreed the 2022/23 budgets for the Better Care Fund (BCF). This report updates the Locality Board with the financial outturn position for the BCF for the financial year 2022/23. 2. Recommendations
2.1Locality Board notes the revenue spend for 2022/23 was on budget.
2.2Locality Board notes that there is a overspend on Social Care Services which is mitigated by a underspend against the equipment loan store.
2.3Locality Board are asked to approve the £82k equipment loan store budget underspend is allocated to funding of Social Care Services to mitigate the reported pressure in Adult Care for the increased costs in placements.
2.4Locality Board notes the underspend against capital budgets of £1,492k in relation to the Disabled Facilities Grant (DFG) and £71k the INT Hubs and recommends under Council procedures the carry forward of any unspent capital budgets to 2023/24. 3. Reason for recommendation
3.1The Locality Board have responsibility for the BCF budget as mandated in the BCF Policy Framework and Planning Guidance. The NHS GM ICB and the Council have delegated responsibility for the BCF to the Locality Board. The revised 2022/23 budget for the BCF was agreed by the ICB in May 2022, this report provides an update on the forecast position against those budgets. 4. Alternatives considered
4.1It is a requirement of the NHSE guidance to produce a budget for 2022/23 which the ICB approved at its May 2022 meeting. This report updates the monitoring against the 2022/23 budget which is a requirement of the Section 75 agreement. Therefore there are no alternatives to consider. 5. Key information
5.1The BCF revised budget was set at the ICB meeting in May 2022 in line with the BCF Policy Framework and Planning Guidance.
5.2The partners must have a Section 75 agreement to support the BCF budget. A signed section 75 was in place for the earlier part of 2022/23 but due to the changes in health and the ceasing of the CCG a revised agreement between the Council and NHS GM IC was taken to January’s Locality Board (and has been subsequently ratified). The revised version covers the health budgets held at Locality following delegation from NHS GM IC. The budgets delegated by the Council will not change from the original section 75. 6. Finance
6.1Table 1 shows the updated 2022/23 revenue budget and the outturn financial position.
Table 1 Revenue Budget and Outturn Position 2022/23
Line 2022/23 2022/23 2022/23 Scheme No Budget Outturn Variance Revenue Expenditure £'000s £'000s £'000s 1 Funding of Social Care Services 21,320 21,402 82 2 Additional Funding in Adult Social Care (notified in Spring Budget 2017) 1,568 1,568 - 3 Care Act Implementation 212 212 - Carers Services 4 Carers -universal services 400 400 - 5 Carers night sitting service – dementia 83 83 -
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow HMR Integrated Care Partnership Committee at Rochdale and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.