Rochdale South Township Committee noted this item on Wednesday 13 September 2023. Below is the council's own wording, with the papers it was decided on.
That the content of the report be noted by the Rochdale South Township Committee. 2. That the principle that a Property Improvement Scheme for Castleton Local Centre be developed by Officers for further engagement with Members and property owners be approved. 3. That the boundaries of any scheme can be extended in line with the ongoing Bee Network scheme to include properties outside the conservation area as shown in the plan in Appendix A. 4. That Officers can be authorised to continue to engage with partners to explore external funding opportunities for the implementation of the scheme.
Word for word from the decision Rochdale published for this meeting.Source: democracy.rochdale.gov.uk
Report title: Castleton Local Centre Property Improvement Programme Report to: Rochdale South Township Committee Date of meeting: 13th September 2023 Cabinet Portfolio Holder: Councillor Daniel Meredith Report of: Mark Robinson – Director of Economy Public or private: Public Key Decision?: Yes Published on the Forward Plan: No
1. Report summary 1.1 A Property Improvement Scheme presents a major opportunity to support the ongoing regeneration of Castleton Local Centre as supported through the recently adopted Castleton Station Area Supplementary Planning Document and wider Rail Corridor Regeneration Strategy. The proposal is to improve the visual appearance and architectural quality of some commercial properties in the area whilst stimulating greater residential uses within the centre and footfall to improve the vibrancy of the centre. Building on the investment in the Bee Network Scheme and the Rochdale Rail Corridor Strategy, this project will maintain the momentum of the regeneration strategy for Castleton. 1.2 The key purpose of this report is to consult with the Township Committee and seek Members views on the parameters and principles of the scheme.
2. Recommendations It is recommended that the Rochdale South Township Committee agree that: 1. The principle that a Property Improvement Scheme for Castleton Local Centre be developed by Officers for further engagement with Members and property owners. 2. The boundaries of any scheme can be extended in line with the ongoing Bee Network scheme to include properties outside the conservation area as shown in the plan in Appendix A. 3. Comment on the draft aims and objectives of the Property Improvement Scheme as set out in this report to then be used to develop more detailed proposals. 4. Officers can be authorised to continue to engage with partners to explore external funding opportunities for the implementation of the scheme. 5. Comment on the principle that, where reasonably practicable, the agreed scheme of works would be fully grant funded. 6. Note, subject to the agreement of the Township Committee, a further detailed report setting out a proposed schedule of works, eligibility and grant criteria will be presented to Cabinet for final approval.
3. Reason for recommendation The regeneration of Castleton Local Centre has been identified as a strategic priority for the Council as part of the Castleton Area Supplementary Planning Document and Rail Corridor Regeneration Strategy. The area is experiencing considerable regeneration activity as an attractive market for new homes linked to the attraction of the railway station providing links to the strategic highway network and Manchester City Centre. In order to increase footfall and promote more sustainable residential uses within the centre, such as upper floor conversions, as well as refurbish commercial space, it is proposed to engage with property owners and funding partners to develop and undertake a programme of property repairs and refurbishment. 4. Alternatives considered Recommendation Reason for Recommendation 1. Do Nothing This would result in commercial properties not being improved and a financial responsibility remaining with business and property owners.
5. Key information 5.1 The regeneration of Castleton Local Centre has been identified as a strategic priority for the Council as part of the Castleton Area Supplementary Planning Document and Rail Corridor Regeneration Strategy. The area is experiencing considerable regeneration activity as an attractive market for new homes linked to the attraction of the railway station providing links to the strategic highway network and Manchester City Centre.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Appointments to the Norman Barnes FundThat Councillor Aasim Rashid, Councillor A. Smith and Billy Sheerin be appointed as Trustees to the Norman Barnes Fun...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.