Additional land was required to allow the introduction of a new junction layout at Manchester Road/Kemp Avenue. This would provide space for walking and cycling facilities, in addition to improving the movement and regulation of motor traffic through the junction. Rochdale Borough Council currently had an agreement in principle with Highfield Hospital for the acquisition of the land. Due diligence would be undertaken by Legal to ensure the land was appropriate for the proposed use. The proposed route to market was via a framework contractor in line with Star procurement and the Council’s constitution. This was necessary to give effect to the transfer of land to the Council and to promote the scheme and project Delivery Agreements. Traffic Regulation Orders were necessary to enable appropriate enforcement by the Highway Authority upon the proposed scheme becoming operational. The current process was - that should objections be received following public consultation, the matter be considered at a Township Meeting to allow Members to review the objections and agree or otherwise to ... view the full minutes text for item 39.
Word for word from the decision Rochdale published for this meeting.Source: democracy.rochdale.gov.uk
5.2Benefits of the Castleton to Rochdale Active Travel Routes 13
5.3Feedback on specific junction upgrade proposals 14
5.3.1 Proposal 1 - Manchester Road/ Bolton Road 14
5.3.2 Proposal 2 – Manchester Road/ Montgomery Street Crossing15
5.3.3 Proposal 3 – Manchester Road/ Roch Valley Way 16
5.3.4 Proposal 4 – Manchester Road/ New Barn Lane 17
5.3.5 Proposal 5 – Manchester Road/ Kemp Avenue 18
5.3.6 Proposal 6 – Manchester Road/ Tweedale Street 19
5.3.7 Proposal 7 – Manchester Road/ Drake Street 20
5.4Feedback on specific quiet street proposals 21 3
5.4.1 More greenery 21
5.4.2 Sustainable drainage e.g. flood water drainage improvements22
5.4.3 Improved footpath materials to improve the public realm and
comfort for people walking 23
5.4.4 Road re-surfacing 24
5.4.5 20mph speed limits and traffic calming measures 25
5.4.6 Improved signs and road markings for cyclists 26
5.4.7 Benches 27
5.4.8 Areas to play 28
5.4.9 Bike pumps for public use 29
5.5Feedback on maintaining on-street car parking 30
5.6Additional comments and suggestions for the scheme 32
5.6.1 Constructive comments and suggestions 32
5.6.2 Negative feedback 34
5.6.3 Facilitating more walking, wheeling and cycling journeys 36
6. Conclusions 39
7. Appendix 41
7.1Plan of Proposals 41
7.2Survey Questionnaire 42
Castleton Phase 2 Survey 4
1. Introduction
Over the last 10 years, levels of traffic have increased significantly on residential streets. This has brought more pollution, noise, and road safety risks to local streets.
The Greater Manchester Bee Network aims to provide a joined-up, world-class transport system, making it easier for people to get around by bus, tram, and train - and also delivering the UK’s largest walking, wheeling, and cycling network. These new and improved routes aim to connect every area of Greater Manchester and make it easier, safer, and more attractive for people to get active for everyday trips.
The Castleton to Rochdale active travel route scheme will build on Phase 1, which started on site in September 2022. The aim of the scheme is to encourage active travel, and the quiet streets being proposed will create a link for people travelling by foot or by bike and become spaces where people feel comfortable and are able to spend time in.
To further understand the views of local people, businesses, and road users in relation to the proposed scheme, Rochdale Borough Council commissioned Qa Research to conduct a public engagement survey. All printing and mailing of the paper surveys was undertaken by Rochdale Borough Council.
The research has been developed to help the project team and local decision-makers understand the views of local people, businesses, and road users in relation to the draft plan. Comments and feedback were welcomed to ensure the scheme delivers the maximum benefits for all.
This document sets out the findings of the survey. 5
2. Aims & Objectives
The aims of this research were to:
Measure levels of support or opposition to all of the draft proposals.
Explore other suggestions that local people have.
Identify whether any differences exist between demographic groups, or those living inside or outside the scheme area.
3. Methodology
The Castleton Phase 2 public engagement survey was distributed via a combination of online promotion and paper-based surveys sent direct to residential and business addresses in the scheme area and also made available at two events held by Rochdale Borough Council at Number One Riverside on 3rd and 17th August. This dual approach to distributing surveys was adopted to ensure that as many local people as possible had an opportunity to participate.
The questionnaire was designed so as to follow the tried and tested format of other Active Neighbourhood scheme consultations.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Finance Update 2026/27 Quarter 1That the 2026/27 forecast positions for Revenue, Capital, and the Collection Fund as at the end of June 2026, as deta...
Best Start Family Hubs ProgrammeThat the Best Start Family Hubs and Healthy Babies Programme grant funding be accepted and expenditure be approved in...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.