Report to HMR Integrated Care Partnership Committee
Greater Manchester Integrated Care Partnership
Sustainability Plan
Locality Boards October 2024 1.0 Introduction
1.1Greater Manchester (GM) Integrated Care Partnership provides healthcare for 3m people living in 10 places. As a system, GM has sought to improve population health through working with partners whilst at the same time improving the NHS financial position and health service performance.
1.2Working with partners, we have developed a Sustainability Plan. This was approved at the GM Integrated Care Board on 18th September. The Sustainability Plan slides are included in this agenda pack.
1.3The Sustainability Plan is based on the recognition that system sustainability rests on addressing the challenges we face across finance, performance and quality and population health - and the relationship between these.
1.4The Plan shows both how the system both returns to financial balance through addressing the underlying deficit and secures a sustainable future through addressing future demand growth and implementing new models of care year on year.
1.5In developing the plan, the financial and performance position of NHS providers has been considered, along with plans to transform and optimise care provision, in order to address the underlying financial deficit by the end of the 2026/7 financial year.
1.6A population-based approach to developing the plan has set out the current and future pattern of demand and associated costs attributable to Non-Demographic Growth (NDG), quantified the opportunities to improve population health, and set out the immediate priorities to inform phasing and sequencing of these opportunities over time.
1.7The plan shows how the current deficit may be compounded by approximately £600m of additional demand but can be addressed over time through a combination of population health measures, system collaboration and provider efficiencies.
1.8There are five pillars of sustainability against which the delivery programmes are set out:
Cost Improvement
System Productivity and Performance
Reducing Prevalence
Proactive Care
Optimising Care
1 1.9. Within the plan, we show how the projected remaining financial deficit could be eliminated over three years through:
• Consistent and complete implementation of existing Cost Improvement Plans (CIPs)
• Complete implementation of system wide plans already developed across GM along with assumptions about those not yet detailed
• Assumptions on reconfiguration of parts of the system which have not yet been planned in detail
• Assumptions on reducing the number and scope of procedures of limited clinical value (PLCV) and associated pathways, although this is not yet detailed
1.10The plan shows that with additional investment, the impact of Non-Demographic Growth (NDG) could be mitigated through:
• Assumptions about the impact of reducing prevalence and enabling proactive care on the health of the population
2.0Delivery of the Sustainability Plan in Localities
2.1Ultimately, the sustainability of the health and care system in GM rests on our ability to support people to stay in good health for longer. This requires an integrated, whole- system response from both within health and care and beyond.
2.2We need to act both on reducing the prevalence of poor health through prevention activities and to ensure we provide early intervention and proactive care to stem further deterioration. The Sustainability Plan is clear that the projected non-demographic growth in demand and costs can only be addressed through radical changes in both our care model and in tackling the social determinants of health. We will need to apply our place model with greater pace and scale and with more consistency. This will need to include:
• Consistent, at scale, delivery of an integrated neighbourhood model – including same day GP access where clinically appropriate, community services delivered to a core GM standard and underpinned by our Live Well model
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow HMR Integrated Care Partnership Committee at Rochdale and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.