To provide Cabinet with an update on the financial position of the Children’s Services directorate. This enabled effective budget management and ensured financial resources were spent in line with the budget, and were targeted towards Council’s priorities. Alternatives Considered: Not to receive budget updates – this option was not recommended as financial reporting ensured the Council complied with The Charted Institute of Public Finance and Accountancy (CIPFA) Financial Management Code and its standards for management of financial resources in the short, medium and long term, management of financial resilience to meet unforeseen demands on services, and management of unexpected shocks within financial circumstances.
Word for word from the decision Rochdale published for this meeting.Source: democracy.rochdale.gov.uk
Report title: Children’s Services Q2, 2024/25 Revenue monitoring update Report to: Cabinet Date of meeting: Tuesday 26th November, 2024 Cabinet Portfolio Holder: Cabinet Member for Children’s Services and Education Report of: Director of Children’s Services and Deputy Chief Finance Officer Public or private: Public Key Decision?: No Published on the Forward Plan: Yes
1. Report summary
1.1To inform Cabinet, and the Corporate Overview and Scrutiny Committee, of the Children’s Services current forecast 2024/25 financial position, detail of issues that are impacting on the directorate, and an update on the recovery plan. The report contains detail of: • Q2, 2024/25 financial position • 2024/25 recovery plan • Medium term recovery plan 2. Recommendations
2.1Cabinet notes the forecasted financial position for 2024/25 at Q2 and related service commentary, and plans for the remainder of 2024/25 and the medium term. 3. Reason for recommendation
3.1Cabinet Members should be kept updated on the financial position of all Council directorates, as effective budget management is critical to ensuring financial resources are spent in line with the budget, and are targeted towards the Council’s priorities. 4. Alternatives considered
4.1No alternative as financial reporting ensures the Council complies with CIPFA’s Financial Management Code and its standards for management of financial resources in the short, medium and long term, management of financial resilience to meet unforeseen demands on services, and management of unexpected shocks within financial circumstances.
5. Key information
5.1During the 2024/25 budget setting process, a number of pressures were identified in Children’s services largely in terms of increasing external placements, pressures arising from the continued growth in Education, Health and Care Plans (EHCPs) and an unstable workforce adding to the use of high costing agency staff. Additional funding was approved to address these as detailed in the table below.
Investment 2021/22 2022/23 2023/24 2024/25 2025/26 Total in Services
The funding was split into recurrent and one off funding, with additional recurrent funding added from 2024/25 to address underlying pressures. 5.2 Q2 Financial Forecast The forecast position has worsened within Q2, reporting £3.342m pressures. The forecast at Q1 was £0.6m. In addition to net forecast deficit of £3.342m, there are legal cost pressures of c £1.0m in relation to cared for children, which is being funded via a budget transfer from Treasury whilst a longer term solution is developed.
The table below explains the overall pressure in terms of sub services within the overall Children’s Directorate.
Budget Forecast Variance Service Narrative £'000 £'000 £'000 Cared for Children:- The Cared for Children numbers are higher than the planned strategy and the unit costs for existing placements have increased the forecast spend by £865k. There are cost 36,013 38,022 (2,009) pressures associated with Safeguarding children of £465k and pressures associated with Agency staffing of £499k.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Finance Update 2026/27 Quarter 1That the 2026/27 forecast positions for Revenue, Capital, and the Collection Fund as at the end of June 2026, as deta...
Best Start Family Hubs ProgrammeThat the Best Start Family Hubs and Healthy Babies Programme grant funding be accepted and expenditure be approved in...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.