Cabinet, Tuesday 17 December 2024 at 6.00pm

Capital Programme 2025/26 to 2029/30

Noted Executive 2 papers

Cabinet noted this item on Tuesday 17 December 2024. Below is the council's own wording, with the papers it was decided on.

Item125

Resolved

The proposed changes to the Capital Programme 2024/25, which was now £116.903m be noted; 2. That the Capital Programme for 2025/26 of £176.652m, and provisional programmes for 2026/27 to 2029/30, as a basis for consultation, subject to confirmation of grant funding allocations, as detailed in Appendix 1 of the report be approved; 3. That it be noted that: a. The additional revenue cost of new capital schemes and inflation was £0.120m in 2025/26 rising to a future year full year effect of £0.491m by 2029/30; b. A review of the phasing of the existing Capital Programme and the use of £2.4m of reserves to fund shorter life schemes had resulted in reduced revenue costs of circa £1.16m in 2025/26, with reduced savings across future years. This had resulted in a net revenue cost reduction in 2024/25 of £0.984m, in 2025/26 of £0.330m, and in 2026/27 of £0.042m after taking account of the new scheme costs; 4. That it be agreed that where new funding was confirmed relating to schemes with a prudential borrowing implication for the Council such as Highways maintenance / pothole funding, this would be used to reduce the Councils borrowing requirement; 5. That the next steps of the consultation process which would take place over the autumn be approved. Reason for decision: Cabinet members were required to recommend a balanced 2025/26 Revenue Budget to Budget Council, and provisional budgets for 2026/27 to 2027/28, and the capital programme was a key element of the budget setting process and had a direct impact on revenue budgets. The Council was required to set a balanced budget for 2025/26 by 11th March 2025. Alternatives considered and rejected: The Council was legally obliged to set a balanced budget. The budget setting process was complex and had to be undertaken in a planned way. It was equally important that assumptions used in the preparation of the budget were agreed , reasonable and consistently applied by all services. A number of alternative elements of the Capital Programme were considered in the development of the ... view the full minutes text for item 125.
Word for word from the decision Rochdale published for this meeting. Source: democracy.rochdale.gov.uk

Follow this further

Built from Rochdale's papers

What the report saysPro

Report to Cabinet

Appendix 1 Capital Programme 2025/26 to 2029/30

DIRECTORATE SCHEME SCHEME DESCRIPTION FUNDING SOURCE 2025/26 2026/27 2027/28 2028/29 2029/30 NAME £’000 £’000 £’000 £’000 £’000 Adult Care Disabled The legislative framework External Grant / Contribution 3,257 3,257 3,257 3,257 3,257 Facilities governing DFGs is provided Grant by the 'Housing Grants, Prudential Borrowing 270 Construction and Regeneration Act 1996'. Since 1990, local authorities have been under a statutory duty to provide grant aid to disabled people for a range of adaptations in their homes. Adult Care Care Home Providing Solar Panels to External Grant/ Contribution 1,845 Solar Panel local care homes. Renewable programme energy is better for (Energy environment and can efficient and considerably reduce energy sustainable) costs this is a viable option in being able to support care providers in a different way. Appendix 1 Capital Programme 2025/26 to 2029/30

DIRECTORATE SCHEME SCHEME DESCRIPTION FUNDING SOURCE 2025/26 2026/27 2027/28 2028/29 2029/30 NAME £’000 £’000 £’000 £’000 £’000 Adult Care Tech Enabled When technology is Prudential Borrowing 333 Care embedded seamlessly into care and support services, it Revenue Contribution to 333 can be transformative, Capital Outlay helping people to live happy, fulfilled lives in their homes and communities. It is generally widely accepted that the introduction of Technology Enabled Care (TEC) – previously known as Assistive Technology, has many benefits for the health and social care sector. TOTAL ADULT 5,435 3,860 3,257 3,257 3,257 CARE Appendix 1 Capital Programme 2025/26 to 2029/30

DIRECTORATE SCHEME NAME SCHEME DESCRIPTION FUNDING SOURCE 2025/26 2026/27 2027/28 2028/29 2029/30 £’000 £’000 £’000 £’000 £’000 Children's Services Devolved Formula Schools will develop and External Grant / 445 445 445 445 445 Capital commission individual schemes Contribution to improve condition and suitability within their buildings with guidance and approval from the Council. Academy conversions may reduce the Department for Education allocation in future years. Children's Services New Place Provision of additional school External Grant / 31,000 Planning places to meet statutory duty Contribution through a programme of works combining internal remodelling, new build or demountable classroom units. Future years funding allocations determined by the Department for Education. Estimated figures and may change. Appendix 1 Capital Programme 2025/26 to 2029/30

DIRECTORATE SCHEME NAME SCHEME DESCRIPTION FUNDING SOURCE 2025/26 2026/27 2027/28 2028/29 2029/30 £’000 £’000 £’000 £’000 £’000 Children's Services Schools Capital Development of a programme External Grant / 3,308 1,808 1,808 1,808 1,808 Condition of works to resolve major Contribution Programme condition and improvement issues in school buildings in line with the Local Authority's Asset Management Strategy and Local Policy Statement. Academy conversions may reduce the Department for Education allocation in future years. Children's Services High Needs The High Needs Provision External Grant / 11,500 - - - - Provision Capital Capital Allocations (HNPCA) to Contribution Allocation support local authorities to deliver new places and improve existing provision for children and young people with Special Educational Needs and Disabilities (SEND), particularly those with more complex needs, and for those pupils that require alternative provision, which we collectively refer to as ‘high needs’ provision. TOTAL CHILDREN’S 46,253 2,253 2,253 2,253 2,253 SERVICES Appendix 1 Capital Programme 2025/26 to 2029/30

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Append. 1 for Capital Programme 2025/26 to 2029/30Report 182 KB DownloadRead as text
PDF
Capital Programme 2025/26 to 2029/30Report 180 KB Download

At this meeting

Whole meeting

Who was there

7 of 18 attended
AS
Abu SiddiqueCouncil Staff, expected
NT
Nichola ThompsonOfficer, in attendance
SH
Sharon HubberOfficer, in attendance
SS
Samantha SmithOfficer, in attendance
JM
Julie MurphyOfficer, in attendance
SR
Steve RumbelowOfficer, in attendance
DA
Councillor Daalat AliCommittee Member, present
NE
Councillor Neil EmmottChair, present
IA
Councillor Iftikhar AhmedCommittee Member, apologies
CW
Councillor Carol WardleCommittee Member, present
RM
Councillor Rachel MasseyCommittee Member, present
DM
Councillor Daniel MeredithCommittee Member, present

All 18 on the meeting page

On this subject at Rochdale

Search all
  1. Capital Programme 2025/26 to 2029/30This decision
  2. Local Transport Plan Highways Capital Programme 2024 to 2026 - Update ReportNoted
  3. Capital Programme for Consultation 2026/27-2030/31Noted
  4. Capital Programme for Consultation 2026/27-2030/31Noted
  5. LTP Highways Capital Programme 2024 to 2026 - Update ReportDeferred
  6. Capital Programme 2025/26 - 2029/30Noted

More from Rochdale Cabinet

All decisions
MeetingDecisionOutcome
25 Aug 2026 Pride in Place UpdateThat the membership of the Hurstead, Smallbridge and Belfield Neighbourhood Board appointed by the Council and Member... Noted Open
25 Aug 2026 Greater Manchester’s Integrated Settlement Grant for Employment and Skills SupportThat Rochdale Borough Council accept the £892,127 GMIS Grant for the period 2026/2027 so it can continue to deliver t... Agreed Open
25 Aug 2026 Finance Update 2026/27 Quarter 1That the 2026/27 forecast positions for Revenue, Capital, and the Collection Fund as at the end of June 2026, as deta... Noted Open
25 Aug 2026 Children’s Services Q1, 2026/27 Revenue Monitoring UpdateResolved that the forecasted financial position for 2026/27 at Q1 and related service commentary, and plans for the r... Noted Open
25 Aug 2026 Best Start Family Hubs ProgrammeThat the Best Start Family Hubs and Healthy Babies Programme grant funding be accepted and expenditure be approved in... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies