Report to HMR Integrated Care Partnership Committee
Recommendations
2.1Approve the opening risk position for Q1 2025/26 2.2 Approve the proposed escalations to GM as detailed in table 1.
Reason for recommendation
3.1Ensure all risks that could affect the delivery of our locality strategic objectives are identified and appropriately managed.
4. Key information
Key challenges and risk themes 4.1 In our last risk report in April, we highlighted a new emerging risk due to NHS reform. Whilst considerable work is underway to plan for the upcoming changes, there are still significant uncertainties. This is coupled with the requirement for substantial cost savings across our health and care system. These key challenges are manifesting into key risk themes: • The skills and capacity available to deliver our key priorities and the impact this has on quality, performance and finance. • The future of our locality operating model including the ability to deliver neighbourhood health and shift from hospital to community, treatment to prevention and analogue to digital • The impact of savings on service delivery and outcomes for our residents.
4.2Due to the level of uncertainty, the high scores for many of our risks are driven by the lack of control within locality and the absence of detailed plans on how NHS reform will be enacted which limits the mitigations we can put in place. All our risks are regularly reviewed through our ICPC subgroups and will be updated as new information emerges with regular updates through ICPC.
Risks requiring escalation to GM for Q1
4.3The following table provides an overview of the risks being escalated to GM in Q1 either for information or for support in mitigation.
Table 1 – Risks for Escalation to Greater Manchester Integrated Commissioning Board
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow HMR Integrated Care Partnership Committee at Rochdale and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.