Economy & Place Directorate Plan 2025-26: Quarter 2 Performance Update

Noted Scrutiny 3 papers

AI summaryRochdale scrutiny committee noted the Economy and Place Directorate's Q2 2025-26 performance update and asked officers to share equity mapping materials with members.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedOfficers asked to share equity mapping materials
MoneyMultiple funding lines securedSee money lines below for figures
What happens nextLocal Plan to Cabinet in NovemberMDC business case in preparation
Who it affectsBorough residents and businessesTown centres, housing, skills, climate

What was decided

The committee noted the Economy and Place Directorate Plan 2025-26 Quarter 2 performance update report covering regeneration, housing, town centres, climate and commercial activity. Report P1

Members asked officers to share equity mapping materials with the committee.

Why

The committee was reviewing progress against the 2025-26 Directorate Plan at mid-year, with reported completion rates ranging from 25% to 100% across the ten priorities. Report P2, P13, P29, P78, P108, P121, P133

Members asked for equity mapping to scrutinise how the directorate is addressing inequalities across its work.

What happens next

Draft Local Plan to be taken to Cabinet in November 2025, with Regulation 18 consultation to follow shortly afterwards. Report P18

A Mayoral Development Corporation for Northern Gateway to be submitted to the Secretary of State for final approval in the coming months. Report P16

Bury and Rochdale to submit Heywood neighbourhood investment plans to Government by end of November 2025, with the new Town Centre Programme Board due to meet in Q3. Report P54, P58

The money

  • £15m Sustainable Materials and Manufacturing Centre (SMMC) on Kingsway Business Park, enabling work has commenced Report P19, P30
  • £600k Castleton shop front improvement scheme consultation Report P62
  • £75k GMCA funding secured for Rochdale town centre framework, with match from RBC Report P59
  • £70,000 CRSTS1 Revenue Funding for concept design and feasibility study for a new multi-storey car park at Littleborough rail station Report P61
  • £175K Investment secured from Arts Council England by 6 organisations this quarter Report P66
  • £22K Sponsorship secured from local businesses for the Town of Culture programme Report P67
  • £100k GMCA Mayoral Renewable Fund grant for EV charging and battery storage at Heywood Sports Village Report P114
  • Just under £500,000 Additional CRSTS1 revenue funding secured from TfGM for active travel scheme development Report P134
  • circa £900,000 Investment Zone Skills funding secured over the next four years, subject to cabinet approval Report P134
  • £2.5m Provisional Brownfield Land Funding secured, subject to further due diligence Report P134

Implications

  • Financial: Multiple external funding streams secured, but the digital inclusion service may struggle to meet demand after December unless additional funding is found. Report P8
  • Risk: An initial funding bid for the inclusive parks project was unsuccessful; a new bid is being prepared with partner organisations. Report P12
  • Climate: 60kWp of Solar Car Ports completed at Heywood Sports Village, with further decarbonisation work on schools and council assets underway. Report P114, P115, P116
  • Equalities: Digital inclusion work in deprived neighbourhoods is being expanded through Mesh network bids to DSIT, with current coordinator and apprentice capacity at risk after December. Report P8
  • Staffing: Members asked to see equity mapping materials to understand how the directorate is addressing inequalities across its work.
  • Other: Temporary accommodation procurement framework being designed to align with best practice, value for money and quality standards; exercise scheduled to commence in autumn. Report P89

Who and where

  • Borough residents, including those experiencing homelessness and those needing digital or skills support Report P8, P38, P88
  • Local businesses, including Kingsway and Stakehill occupiers and Castleton shop fronts Report P20, P24, P62
  • Visitors to Rochdale Town Hall and the wider visitor economy Report P43, P66
  • Council tenants and households in temporary accommodation, with refurbishment of Leopold Court and expansion of family TA from 33 to 60 units with RBH Report P97

Timeline

  • September 2025: Rochdale Film Office website officially launched; 70 locations signed up Report P124
  • October 2025: EV footway channel policy scheduled for Overview and Scrutiny consideration before Cabinet Report P102
  • November 2025: Draft Local Plan and Township naturalisation proposals to be presented Report P18, P76
  • Q3 2025-26: Town Centre Programme Board to meet; Station Gardens construction to start; Corner Plot demolition to start Report P58, P60
  • Q4 2025-26: Corner Plot build work and Rochdale Station Square construction due to start on site Report P60
  • March 2026: Heywood Sports Village EV and battery storage project must complete to draw down GMCA grant Report P114
  • Late 2026: Sustainable Materials and Manufacturing Centre due to complete Report P19

Plain English for the jargon

  • MDC: Mayoral Development Corporation, a GMCA-led body with planning powers for a designated area
  • CRSTS: City Region Sustainable Transport Settlement, a government funding programme for transport schemes
  • SMMC: Sustainable Materials and Manufacturing Centre, a new facility on Kingsway Business Park
  • TfGM: Transport for Greater Manchester
  • DSIT: Department for Science, Innovation and Technology
  • GMCA: Greater Manchester Combined Authority
  • BID: Business Improvement District, a levy-funded body for a defined commercial area
  • SOBC: Strategic Outline Business Case
  • TA: Temporary Accommodation provided to households experiencing homelessness
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item126

Resolved

That the report be noted; 2. That Officers share with the Committee equity mapping materials.
Word for word from the decision Rochdale published for this meeting. Source: democracy.rochdale.gov.uk

Follow this further

Built from Rochdale's papers

What the report saysPro

Report to Communities, Regeneration and Environment Overview and Scrutiny Committee

Economy & Place Directorate Plan 2025-26 Action Plan Due Date Status % Complete

EP2501 Consult, engage, and involve all our communities to ensure their needs are addressed in our 31 March 2026  46% plans to make the Borough a great place to live, work and play

Ref. Name Due Status % Complete Ensure the views of all communities are secured through consultation and in the delivery of EP2501.A regeneration programmes and projects e.g. Bee Network, Town Centres, Long Term Plan for 31 March 2026  50% Neighbourhoods Consultation for Heywood went well and the outcome of the public consultation has been shared with stakeholders in anticipation of progressing to the next stage of business case approval.

The Rochdale to Oldham Improving Journeys project has also seen a final round of consultation and the comments from this are expected to be analysed and discussed with Members.

A 6-month programme of workshops and activities to encourage young people to be more engaged in shaping the development of the built environment and broader regeneration activity began in September with a focus on Heywood and Rochdale.

The Culture and Placemaking continues to support the Heywood Towns Board and High Streets and Culture sub-group in the planning and delivery of interventions.

Heywood Live Project, a 5-week project with Sheffield School of Architecture started in October, working with local residents and businesses to explore and identify opportunities to deliver on the ambitions of the local community and Heywood Towns Board.

Castleton Shop Front Improvements – Letter drop took place at the end of July and business engagement sessions for the shop front improvement schemes held in August and an extra session in September. Businesses have been invited to submit their proposals and costs. No deadline has been set but businesses have been advised that bids be assessed as they come forward until the committed budget has been fully spent. Reduce digital inequalities by providing free broadband to the most deprived neighbourhoods and EP2501.B support residents to access and gain digital skills to improve lives through access to services and 31 March 2026  50% opportunities We are working with colleagues in Digital & ICT to roll out the Mesh network to other parts of the borough. This will make it more sustainable to manage and be less reliant on people outside the council to provide the technical support. We have also submitted a bid to DSIT to support the development of a Mesh network in Heywood, which is short term funding but if successful will provide us with funding to resource the technical support and equipment needed. We have also included funding for member of staff to provide the additional digital support. We currently only have one coordinator and a business admin support delivering all the sessions with the help of an apprentice, who is due to finish at the end of the year. There is increasing demand on the service that is provided so we will struggle to meet the level of need after December unless additional funding is secured.

Directorate Plan New. v4_2 Page 1 Of 13 Economy & Place Directorate Plan 2025-26 Action Plan Due Date Status % Complete

This Quarter we have had 233 referrals, provided data to 109 residents, loaned 101 devices, provided phones to 12 people that were donated, delivered 47 sessions, provided 1:1 support to 13 people, referred 8 people onto accredited courses, supported 3 people into employment and signposted 6 people on to additional support.

EP2501.C Deliver the inclusive parks project across the Borough 31 March 2026  40%

Funding bid not successful. New Income Generation Manager has assessed the grant application for weaknesses, partner organisations engaged to go again with other funding opportunities. Meeting being arranged to pull together funding action plan.

EP2502 Deliver new economic investment, sustainable development, and business growth 31 March 2026  58%

Ref. Name Due Status % Complete

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Append. 1 for Economy & Place Directorate Plan 2025-26: Quarter 2 Performance UpdateReport 345 KB DownloadRead as text
PDF
Append. 2 for Economy & Place Directorate Plan 2025-26: Quarter 2 Performance UpdateReport 2.9 MB Download
PDF
Economy & Place Directorate Plan 2025-26: Quarter 2 Performance UpdateReport 133 KB Download

At this meeting

Whole meeting

Who was there

10 of 16 attended
SA
Councillor Stephen AnsteeVice-Chair, present
TB
Councillor Tom BesfordChair, present
AB
Councillor Adam BrantonCommittee Member, apologies
KM
Councillor Kathryn Mary BromfieldCommittee Member, present
AB
Councillor Angela BrownCommittee Member, present
SE
Steph EverettOfficer, in attendance
IF
Councillor Iram FaisalCommittee Member, present
FF
Fabiola FuschiSecretary, in attendance
RM
Rafael MartinezOfficer, in attendance
BP
Councillor Bev PlaceCommittee Member, present
FR
Councillor Faisal RanaCommittee Member, present
MR
Mark RobinsonOfficer, in attendance

All 16 on the meeting page

On this subject at Rochdale

Search all
  1. Economy & Place Directorate Plan 2025-26: Quarter 2 Performance UpdateThis decision
  2. Economy & Place Directorate Plan 2025-26: Quarter 4 Performance UpdateNoted
  3. Economy and Place Directorate Plan 2026-27Noted
  4. Economy & Place Directorate Plan 2025-26: Quarter 1 Performance UpdateNoted
  5. Economy & Place Directorate Plan 2024-25: Quarter 4 Performance UpdateNoted
  6. Economy and Place Directorate Plan 2025-26Noted

More from Rochdale Communities, Regeneration and Environment Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 GMCA Joint Health Scrutiny CommitteeResolved that the minutes of the meetings held on 16 th June 2026 and on 14 th July 2026 be noted. Noted Open
8 Sep 2026 GMCA Police, Fire and Crime PanelResolved that the minutes of the meeting held on 29 th June 2026 be noted. Noted Open
8 Sep 2026 Notice of Key Decisions and Private ItemsResolved that the key decision document and notice of private items be noted. Noted Open
8 Sep 2026 Work Programme 2026-27Resolved that the proposed Work Programme for 2026/27 be noted. Noted Open
21 Jul 2026 GMCA Joint Health Scrutiny CommitteeResolved that the minutes of the held on 17 th March 2026 be noted. Noted Open