Draft Simister Bowlee (Northern Gateway) Development Framework Supplementary Planning Document
AgreedExecutive2 papers
AI summaryRochdale Cabinet approves draft Simister Bowlee Development Framework SPD for at least four weeks of public consultation starting February 2026, covering the joint Bury-Rochdale allocation for up to 1,550 homes.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedAuthority delegated to Assistant Director of Economy for minor edits
MoneyNot stated in the reportNo financial figures in the papers supplied
What happens nextPublic consultation from February 2026Minimum four weeks; final draft to Cabinet for adoption
Who it affectsFuture planning applicants on JPA1.2Landowners, Bury and Rochdale residents, developers
What was decided
The Cabinet approved the draft Simister Bowlee (Northern Gateway) Development Framework SPD as the basis for public consultation, running for at least four weeks from February 2026.
The Cabinet gave the Assistant Director of Economy delegated authority to make minor, non-material modifications to the draft SPD before consultation begins.
Why
Regulation 12 of the Town and Country Planning (Local Planning) (England) Regulations 2012 requires public consultation before an SPD can be adopted, giving stakeholders the chance to comment.
The framework guides the delivery of around 1,550 new homes on land allocated under Places for Everyone Policy JPA1.2, straddling Bury and Rochdale at the M60, M62 and M66 junction. Report P25, P27, P34
The document will carry planning weight as a material consideration when determining future planning applications on the JPA1.2 site. Report 1.1
What happens next
Public consultation on the draft SPD will run for at least four weeks from February 2026, with feedback to be incorporated into a final draft. Report 1.1
A separate Infrastructure Phasing and Delivery Strategy (IPDS) is being prepared to sit alongside the SPD and will be a live document updated outside the SPD process. Report 1.1
The final draft SPD, with consultation feedback reflected, will return to each Council's Cabinet for formal adoption. Report 1.1
Options considered
Chosen: Approve draft SPD for public consultation. Required by Regulation 12 of the 2012 Planning Regulations to allow stakeholder comment before adoption.
Rejected: Not approve the draft SPD for consultation. No reasonable alternative identified; without consultation the SPD could not be lawfully adopted.
Implications
Legal: Approving the draft for consultation is a legal prerequisite to adopting the SPD under Regulation 12 of the 2012 Regulations.
Legal: The SPD will become a material consideration in determining future planning applications on the JPA1.2 site, though it introduces no new planning policy. Report 1.1
Climate: The draft requires a sustainability strategy promoting carbon neutrality of new development by 2028 and on-site low carbon energy generation. Report P27
Other: The framework requires 10% biodiversity net gain, protection of Bradley Hall Farm SBI, and a 30%+ affordable housing provision in line with local policy. Report P79
Who and where
Future residents of the JPA1.2 development (up to 1,550 homes, around 200 in Rochdale and 1,350 in Bury) Report P25, P27
Bury and Rochdale Councils, as joint preparing authorities and decision-makers Report 1.1, P28
Landowners and developers bringing forward planning applications on the site Report 1.1
Existing residents of Simister, Bowlee, Middleton, Prestwich, Rhodes and surrounding communities Report P27, P105
Statutory consultees including Transport for Greater Manchester and the Environment Agency Report 1.1, P215
Timeline
March 2025: Separate Development Framework SPD for the adjoining JPA1.1 Heywood/Pilsworth allocation was adopted. Report 1.1
January 2026: Atom Valley Mayoral Development Corporation established, covering JPA1.1 and JPA1.2. Report P87
February 2026: Draft Simister Bowlee Development Framework SPD approved for at least four weeks of public consultation.
At least four weeks from February 2026: Public consultation period on the draft SPD.
Plain English for the jargon
SPD: Supplementary Planning Document: a document that adds detail to policies in the adopted Development Plan and is a material consideration in planning decisions.
JPA1.2: Places for Everyone Joint Development Plan Policy Allocation 1.2 (Simister and Bowlee / Northern Gateway), the policy designating the site for residential-led development.
PfE: Places for Everyone, the statutory joint development plan covering the nine Greater Manchester authorities.
Atom Valley MDZ: Atom Valley Mayoral Development Zone, covering Northern Gateway (JPA1.1 and JPA1.2), Stakehill and Kingsway Business Park.
IPDS: Infrastructure Phasing and Delivery Strategy, a separate live document to be prepared alongside this SPD.
BNG: Biodiversity Net Gain, a requirement that development delivers an overall increase in biodiversity, here stated at 10%.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item127
Resolved
That the draft Simister Bowlee (Northern Gateway) Development Framework (NGDF) SPD (outlined in Appendix 1 to the report) be agreed as the basis for public consultation for at least four weeks commencing in February 2026; 2. That the Assistant Director of Economy be given delegated authority to make minor, non-material modifications to the draft Simister/Bowlee (Northern Gateway) Development Framework Supplementary Planning Document before consultation commences. Reason for decision: Regulation 12 of the Town and Country Planning (Local Planning) (England) Regulations 2012 required that public consultation was undertaken prior to the adoption of an SPD. This enabled stakeholders to have the opportunity to provide comments on the draft SPD before it was formally adopted. Alternatives considered and rejected: There were not considered to be any reasonable alternative options. If the draft SPD was not approved for consultation, it would prevent stakeholders from having the opportunity to comment on it. This would mean that the SPD could not be adopted as it would be contrary to planning regulations.
Word for word from the decision Rochdale published for this meeting.Source: democracy.rochdale.gov.uk
7.9Local Centre 78 9. Sustainability Strategy 97 7.10 Green Infrastructure 79
7.11Green Belt 84 9.1 Delivering Low Carbon, Sustainable Homes 97 7.12 Trees and Woodland 84 9.2 Promoting carbon neutrality of new development by 2028 98 7.13 Digital Connectivity 85 9.3 Improving energy efficiency and the generation of renewable and low carbon energy 100 7.14 Pollution Control 85
Foreword The recently adopted Places for Everyone Joint Development Plan allocates the Simister Bowlee site for up to 1,550 new homes.
To support the new community, the development will be required to provide specific infrastructure. This includes an upgraded local highway network, improved public transport, green spaces, a new primary school, community facilities and more routes for walking and cycling. Traffic restrictions will also be required on Simister Lane, to prevent this route from being a form of access/egress to and from the site.
The Simister Bowlee site lies between the towns of Prestwich and Middleton, spanning the districts of Bury and Rochdale. Strategically positioned at the junction of the M60, M62, and M66 motorways, it forms a major residential development area within the wider Northern Gateway. The site plays a critical role in delivering a well-planned neighbourhood that complements the largest combined employment and housing growth initiative in the North of England. The development will provide approximately 1,350 new homes in Bury and around 200 new homes in Rochdale.
Bury and Rochdale Councils are pleased to present the Simister Bowlee Development Framework which presents a clear long-term vision for the site, identifies guiding development principles and outlines the infrastructure needed to support the site’s long-term development. This framework will guide consideration of future planning applications.
Finance Update 2026/27 Quarter 1That the 2026/27 forecast positions for Revenue, Capital, and the Collection Fund as at the end of June 2026, as deta...
Best Start Family Hubs ProgrammeThat the Best Start Family Hubs and Healthy Babies Programme grant funding be accepted and expenditure be approved in...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.