AI summaryRochdale Council's Corporate Overview and Scrutiny Committee noted the ICT Disaster Recovery Policy and agreed it will be updated once the Cyber Security and Resilience Bill becomes law in 2026.
Written from the decision and the officer reportPDF Pro
OutcomeNotedCommittee also requires all staff to follow it
MoneyNo specific sums stated in the papers
What happens nextUpdate policy after 2026 BillRevised plan to come back to the committee
Who it affectsAll council staff and ICT servicesPlus the Corporate Leadership Team as decision maker
What was decided
The committee noted the ICT Disaster Recovery Policy and accepted that it will be revised once the Cyber Security and Resilience Bill is enacted in 2026. Report P2
A revised disaster recovery plan is to be resubmitted to the committee after the legislation takes effect. Report P2
All staff are to be made aware of and required to follow the policy. Report P2
Why
To make sure the council meets its compliance duties as a corporate body. Report P2
To reduce the risk of data loss, loss of statutory services, reputational damage and possible ICO fines. Report P2
The council has a statutory duty to provide certain services to residents, which the policy supports. Report P2
What happens next
Update the policy after the Cyber Security and Resilience Bill, expected in 2026, is enacted. Report P2
Bring a revised plan back to the Overview and Scrutiny Committee. Report P2
Make sure all relevant staff are aware of and follow the policy. Report P2
Options considered
Chosen: Note the policy and plan to update it after the 2026 Bill. Ensures the council stays compliant once new legislation is in force Report P2
Rejected: No alternatives considered. Officers reported that no other options were considered Report P2
Implications
Risk: Not following the policy could lead to data loss, loss of statutory services, reputational damage and possible ICO fines. Report P2
Legal: The policy supports the council's statutory duty to provide certain services to residents and will need updating for the Cyber Security and Resilience Bill expected in 2026. Report P2
Staffing: Trained ICT officers are needed to operate and implement the policy. Report P2
Financial: Existing budget covers the current solution; shorter recovery times would increase costs and need further budget approval. Report P2
Climate: Running additional data centres raises carbon emissions, so the council will use suppliers committed to Net Zero. Report P2
Who and where
All Rochdale Council staff, who must follow the policy Report P2
The Corporate Leadership Team, which decides the restoration order and can trigger a disaster recovery event Report P2
ICT officers trained to operate and implement the policy Report P2
Council residents, whose statutory services depend on the policy Report P2
Timeline
02-03-2026: Policy noted by Corporate Overview and Scrutiny Committee Report P1
Expected 2026: Cyber Security and Resilience Bill to be enacted, after which the policy will be updated Report P2
Plain English for the jargon
Disaster recovery: Steps to restore ICT systems and services after an unplanned outage or other event that stops them.
Recovery point and time objectives: How much data can be lost and how quickly systems must be restored after an outage.
Cloud-first deployment: A way of running software online through external suppliers rather than the council's own systems, shifting some recovery responsibility to those suppliers.
ICO fines: Financial penalties issued by the Information Commissioner's Office for data protection failings.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item75
Resolved
Resolved 1. That the Policy be noted. 2. That the policy will be updated after the enactment of the Cyber Security and Resilience Bill expected in 2026 be noted; 3. That the policy will be updated after the enactment of the Cyber Security and Resilience Bill expected in 2026 be noted. 4. All staff be made aware of and follow the Policy.
Word for word from the decision Rochdale published for this meeting.Source: democracy.rochdale.gov.uk
Report to Corporate Overview and Scrutiny Committee
Report title: ICT Disaster Recovery Policy Report to: Corporate Oversight & Scrutiny Date of meeting: 02-03-2026 Cabinet Portfolio Holder: Councillor Liam O’Rourke Report of: Nicola Strapps, Assistant Director Digital, ICT & Transformation Public or private: Public
1. Report summary 1.1 To outline the ICT Disaster Recovery Policy that sets out the principles and requirements of the Council’s ICT services and the Corporate Business in the restoration of systems in the event an unforeseen cessation of services. 1.2 This includes preparation for, enactment of and post event activities. 2. Recommendations 2.1 That Overview & Scrutiny Committee notes the policy. 2.2 That Oversight & Scrutiny Committee note the policy will be updated after the enactment of the Cyber Security and Resilience Bill expected in 2026. 2.3 That a revised plan be resubmitted to Oversight & Scrutiny Committee. 2.4 That Overview & Scrutiny Committee ensures all relevant staff are aware of and follow the policy. 3. Reason for recommendation 3.1 To ensure compliance by the corporate body. 4. Alternatives considered 4.1 No alternatives considered 5. Key information 5.1 ICT will take necessary steps and activity to ensure systems can be restored to a state prior to an event causing a cessation of services. 5.2 The Corporate Leadership Team is responsible for prioritising the order systems and services should be restored in the event of a multiple cessation of services. 5.3 It is the responsibility of the Corporate Leadership Team to instigate a Disaster Recovery event. 5.4 Testing and simulations of potential disaster scenarios must take place to ensure compliance with the policy and prepare all areas of the Council for an unforeseen and unplanned outage of services. 5.5 The Council will have an alternative data centre to mirror services, systems and data as a replication of the primary data centre to be used in the event of a disaster recovery scenario at a geographical alternative location. 5.6 The Council will look at Cloud-first deployments to transfer the risk and management of disaster recovery of third-party applications placing the onus on the Council to maintain connectivity. Such deployments enable business continuity through the availability of online services external to the Council’s managed network. 5.7 Authentication services should work both internal and external to the Council’s network infrastructure to enable portability for the end user whilst maintaining data security and control for the organisation. 6. Finance 6.1 Assigned budget to maintain an alternative data centre to meet the needs of the business defined recovery point and time objectives. 6.2 Existing budget already exists to cover the current solution with renewal of equipment on a regular basis to ensure service reliability. Should services require shorter recovery times, costs will increase and further budget would need to be authorised to fund these changes. 7. Legal 7.1 The council has a statutory duty to provide certain services to residents. 8. Human resource 8.1 Relevant trained ICT officers to operate and implement the policy objectives. 9. Sustainability impact 9.1 The cost of running additional data centres at full operational efficiency increases the council’s carbon emissions. Therefore, the council will use suppliers with a commitment to Net Zero to reduce the impact to energy and water resources. 10. Other considerations (corporate priorities, risks) 10.1 Should the Council not undertake systems outlined in the policy there is a significant risk of loss of data and statutory services leading to significant reputational damage and potential ICO fines. This policy is set to mitigate such risks.
Background Papers: ICT Disaster Recovery Policy – v1.3 Sustainability: Net Zero | Zen Internet Contact: David Brooks, Business Performance Manager – [email protected]
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Councillor Elizabeth AtewologunCommittee Member, absent
PH
Councillor Peter HodgkinsonCommittee Member, present
MH
Councillor Michael HollyVice-Chair, present
RJ
Councillor Richard JacksonChair, present
PJ
Councillor Peter JoinsonCommittee Member, present
AK
Councillor Andy KellyCommittee Member, present
AM
Councillor Amna MirCommittee Member, present
AR
Councillor Aasim RashidCommittee Member, present
LR
Councillor Linda RobinsonCommittee Member, present
Hear about the next one first
Follow Corporate Overview and Scrutiny Committee at Rochdale and we tell you when its next papers are published, before the meeting rather than after it.
Finance Update 2026/27 Quarter 1Resolved – 1. That the 2026/27 forecast positions for Revenue, Capital, and the Collection Fund as at the end of June...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.