Rochdale Metropolitan Borough Council
Cabinet, Tuesday 17 March 2026 at 6.00pm

2026-27 Capital Investments in Schools

Approved Executive 2 papers

AI summaryRochdale Cabinet accepts £10.27 million of Department for Education grants and approves a £10.19 million schools capital programme for 2026-27, covering building condition works, primary places, and Redwood Special School expansion.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedDfE grants accepted and capital programme endorsed
Money£10,185,791total programme value detailed at Appendix A
What happens nextProcurement and deliverydelegated to Director of Children's Services
Who it affectsLA maintained schoolsmainly primary and non-PFI schools in the borough

What was decided

Cabinet accepted five Department for Education grants covering School Condition Allocations, Devolved Formula Capital, and Basic Need for 2026-27 and 2027-28. Report P4, 2.2

Cabinet approved the capital expenditure programme set out in the private Appendix A, totalling £10,185,791. Report 2.2, P19

Cabinet gave the Director of Children's Services delegated authority to run procurement, award contractors, amend PFI deeds of variation, and vire funding between projects, reporting through the Quarterly Financial Update. Report 2.3, 2.4

Why

Repairs to the local authority maintained school estate are needed to address the most significant condition issues alongside continued Devolved Formula Capital allocations to schools. Report P8

The programme is required to meet the council's statutory duty to secure sufficient school places and continued education. Report 3.2, P20

Major priorities for the year are additional pupil place planning and a school building condition works programme targeting the highest priority issues. Report P17

What happens next

The Director of Children's Services will run procurement, award contractors, and complete any PFI deed variations needed to deliver the schemes. Report 2.3

Virements between projects will be reported to Cabinet through the Quarterly Financial Update. Report 2.4

Further Cabinet reports will be brought only for new schemes that cannot be managed through the urgent health and safety contingency allocation.

The money

  • £1,800,000 DfE School Condition Allocation, indicative for 2026/27 Report P4
  • £481,429 Additional DfE School Condition Allocation received in 2025/26 Report P4
  • £400,000 Devolved Formula Capital to schools, indicative for 2026/27 Report P4, 3.9
  • £4,642,127 DfE Basic Need Allocation for 2026/27 Report P4, 3.6
  • £2,944,435 DfE Basic Need Allocation for 2027/28 Report P4, 3.6
  • £10,185,791 total value of proposed schemes, programmes and commitments at Appendix A Report P19

Options considered

  • Chosen: Put forward the proposed programme in line with previously approved priorities and commitments. Priorities of additional pupil place planning and addressing the highest priority building condition issues Report P17

Implications

  • Legal: Section 14(1) of the Education Act 1996 places a duty on the council to secure sufficient school places. Report P20
  • Legal: Procurement must comply with the Public Contracts Regulations 2015, the Procurement Act 2023, and the council's Contract Procedure Rules, with support from Star Procurement and Star Legal. Report P21
  • Financial: The programme is fully funded from Department for Education grants, with each project given its own cost centre to track spend. Report P19
  • Risk: The programme must reflect the potential risk of irrecoverable VAT liability on voluntary aided schemes.
  • Staffing: There are no human resource implications from this proposal. Report P22
  • Climate: New works will follow current building control guidance, with the most carbon efficient, low energy options used where possible. Report P23

Who and where

  • Local authority maintained primary schools and non-PFI special schools in the borough Report 3.4, 3.5
  • Redwood Special School and its Phoenix Centre site in Heywood, including sixth form expansion Report 3.8
  • Norden Primary School, where a SEN unit for up to 22 children is planned under a 5-year lease Report 3.8
  • Pupils needing additional primary and special school places across the borough Report 3.6, 3.7

Timeline

  • 1st October 2024: Following academy conversions, the council is no longer financially responsible for any secondary school building maintenance Report 3.4
  • 24 February 2025: Procurement Act 2023 came into force Report P21
  • September 2025: 20 additional children accommodated at Redwood main site through the Phoenix Centre catering hub for sixth formers Report 3.8
  • 16th December 2025: Cabinet approved earlier reports on Basic Need school place planning Report 3.6
  • Tuesday, 17 March 2026: Cabinet meeting approving this report Report P1
  • September 2026: Redwood sixth form to expand at the Phoenix Centre, with a redesign of the sixth form REEC centre in Middleton Report 3.8
  • 2026/27: Indicative receipt of School Condition Allocation and Devolved Formula Capital Report P4
  • 2027/28: Further Basic Need allocation to be used alongside the 2026/27 grant Report 3.6, 3.7
  • By September 2028: Additional school places funded by the Basic Need allocation must be in place Report 3.6

Plain English for the jargon

  • DfE: Department for Education
  • DFC: Devolved Formula Capital, paid directly to schools for condition priorities
  • Basic Need: DfE grant given to councils to provide new school places
  • SCA: School Condition Allocation, DfE grant for school building condition works
  • PFI: Private Finance Initiative, a long-term contract for school building provision
  • SEN: Special Educational Needs
  • Virement: Moving budget from one project or heading to another within the programme
  • STAR Procurement: Shared procurement service used by the council to tender contracts
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item172

Resolved

That the Department for Education (DfE) grants be accepted as follows: 1.1. DfE School Condition Allocations (indicative figure expected for receipt in year 2026/27): £1,800,000 1.2. Additional DfE School Condition Allocation received in 2025/26: £481,429 1.3. Devolved Formula Capital granted to schools (indicative figure expected for receipt in 2026/27): £400,000 1.4. Basic Need Allocation for 2026/27: £4,642,127 1.5. Basic Need Allocation for 2027/28: £ 2,944,435 2. That expenditure as outlined at private Appendix A to the report be approved; 3. That the Director of Children’s Services be given delegated authority to undertake the necessary procurement processes and award of contractors for the schemes detailed in the report including the authority to amend PFI deeds of variation (where necessary) and enter into any incidental and ancillary documentation for the delivery of schemes; 4. That delegated authority be given to the Director of Children’s Services to allocate and vire funding between projects within the programme to support needs within the financial envelope of the funding allocations and report these to Cabinet through the Quarterly Financial Update as necessary. Reason for decision: Background Repairs to the LA maintained school estate had considered all commitments and urgent demands before making recommendations to address the most significant issues, in conjunction with continued DFC allocations to schools. As well as on-going support for the current phases of capital works already committed, the service is proposing a new programme of works to address major condition needs based on Asset Management information, recently commissioned and prioritised full building condition survey information and priority place planning demands in order to ensure that the LA’s statutory obligations for the provision of school places and continued education are satisfied. Full recommendations for inclusion in this year’s capital programme are outlined in Appendix A to this report, including costs estimated by the Council’s Property Services Team. It is proposed that the Buildings Maintenance revenue budget would be used, as in previous years, to support programme development costs, emergency/unplanned repairs and ongoing obligations related to the inspection of the schools building stock. Alternatives considered and rejected: Proposals were put forward in line with priorities and commitments approved in previous Cabinet reports. Major priorities for the forthcoming year would be additional pupil place planning and a school building condition works programme to address the highest priority issues.
Word for word from the decision Rochdale published for this meeting. Source: democracy.rochdale.gov.uk

Follow this further

Built from Rochdale's papers

What the report saysPro

Report to Cabinet

Report title: Capital Investment In Schools 2026/2027 Report to: Cabinet Date of meeting: Tuesday, 17 March 2026 Cabinet Portfolio Holder: Cabinet Member for Children’s Services and Education Report of: Director of Children's Services Public or private: Public Report with Private Appendix Key Decision? Y It is significant in terms of its effect on communities living or working in an area comprising one or more wards Published on the Forward Plan: Y 1. Report summary

1.1The report seeks approval for proposed expenditure on the proposed programmes detailed within this report as outlined in Appendix A, in accordance with the Council’s Financial Regulations. These regulations provide that Cabinet approval should be obtained before new expenditure can be incurred. This report requests approval and direct tender issue and acceptance for the outlined and reserve schemes proposed, contingency and other specified budgets, and the approval of revenue and capital expenditure for the proposed expansion of Redwood Special School at the Phoenix Centre in Heywood.

1.2It is recommended that Cabinet Members accept the Department of Education grant funding received from Basic Need and School Condition Allocation funding to support the needs of provision for school places and the works to address condition needs of school buildings and estates.

2. Recommendations 2.1 To accept the Department for Education (DfE) grants as follows: • • DfE School Condition Allocations £1,800,000 (indicative figure expected for receipt in year 2026/27) Additional DfE School Condition Allocation £481,429 received in 2025/26 • Devolved Formula Capital granted to schools £400,000 (indicative figure expected for receipt in 2026/27) Basic Need Allocation for 2026/27 £4,642,127 Basic Need Allocation for 2027/28 £2,944,435

2.2Approve expenditure as outlined at Appendix A.

2.3To delegate to the Director of Children’s Services the authority to undertake the necessary procurement processes and award of contractors for the schemes detailed in the report including the authority to amend PFI deeds of variation (where necessary) and enter into any incidental and ancillary documentation for the delivery of schemes.

2.4Delegate to the Director of Children’s Services the authority to allocate and vire funding between projects within the programme to support needs within the financial envelope of the funding allocations and report these to Cabinet through the Quarterly Financial Update as necessary.

3. Reason for recommendation Background 3.1 Repairs to the LA maintained school estate have considered all commitments and urgent demands before making recommendations to address the most significant issues, in conjunction with continued DFC allocations to schools.

3.2As well as on-going support for the current phases of capital works already committed, we are proposing a new programme of works to address major condition needs based on Asset Management information, recently commissioned and prioritised full building condition survey information and priority place planning demands in order to ensure that we satisfy the LA’s statutory obligations for the provision of school places and continued education. Our full recommendations for inclusion in this year’s capital programme are outlined in Appendix A, including costs estimated by the Council’s Property Services Team.

3.3It is proposed that the Buildings Maintenance revenue budget will be used, as in previous years, to support programme development costs, emergency/unplanned repairs and ongoing obligations related to the inspection of the schools building stock.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2026-27 Capital Investments in SchoolsReport 153 KB DownloadRead as text
PDF
Append. 2 for 2026-27 Capital Investments in SchoolsReport 54 KB Download

At this meeting

Whole meeting

Who was there

8 of 16 attended
AS
Abu SiddiqueCouncil Staff, expected
NT
Nichola ThompsonOfficer, in attendance
SS
Samantha SmithOfficer, in attendance
JM
Julie MurphyOfficer, in attendance
DA
Councillor Daalat AliCommittee Member, present
NE
Councillor Neil EmmottChair, present
IA
Councillor Iftikhar AhmedCommittee Member, present
CW
Councillor Carol WardleCommittee Member, present
RM
Councillor Rachel MasseyCommittee Member, present
DM
Councillor Daniel MeredithCommittee Member, present
LO
Councillor Liam O'RourkeCommittee Member, apologies
SS
Councillor Susan SmithCommittee Member, apologies

All 16 on the meeting page

On this subject at Rochdale

Search all
  1. 2026-27 Capital Investments in SchoolsThis decision
  2. Capital Investments in Schools 2025/26Noted

More from Rochdale Cabinet

All decisions
MeetingDecisionOutcome
25 Aug 2026 Pride in Place UpdateThat the membership of the Hurstead, Smallbridge and Belfield Neighbourhood Board appointed by the Council and Member... Noted Open
25 Aug 2026 Greater Manchester’s Integrated Settlement Grant for Employment and Skills SupportThat Rochdale Borough Council accept the £892,127 GMIS Grant for the period 2026/2027 so it can continue to deliver t... Agreed Open
25 Aug 2026 Finance Update 2026/27 Quarter 1That the 2026/27 forecast positions for Revenue, Capital, and the Collection Fund as at the end of June 2026, as deta... Noted Open
25 Aug 2026 Children’s Services Q1, 2026/27 Revenue Monitoring UpdateResolved that the forecasted financial position for 2026/27 at Q1 and related service commentary, and plans for the r... Noted Open