Resolved
RESOLVED – 1. That the Corporate Services Directorate Plan 2025-26: Quarter 4 Performance Update be noted. 2. That further details in relation to the points set out above be circulated to the Corporate Overview and Scrutiny Committee.
AI summaryRochdale's Corporate Overview and Scrutiny Committee noted the Q4 performance update for the 2025-26 Corporate Services Directorate Plan and asked for further details on issues raised.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
RESOLVED – 1. That the Corporate Services Directorate Plan 2025-26: Quarter 4 Performance Update be noted. 2. That further details in relation to the points set out above be circulated to the Corporate Overview and Scrutiny Committee.
Corporate Services Directorate Plan 2025-26 Action Plan Due Date Status % Complete
COR2501 Continue with the positive work on Equality, Diversity and Inclusion (EDI) 31 March 2026 65%
Ref. Name Due Status % Complete
COR2501.A Finalise a new process to ensure ongoing compliance with the Public Sector Equality Duty 30 September 2025 50%
The Service Data Annual Report has been drafted following the implementation of a new process. The report is scheduled for presentation to the Adults’, Children’s and Health Equality, Diversity and Inclusion Board in February and will be finalised by late summer 2026.
To develop an improved SIA (Sustainability Impact Assessment) and EIA (Equality Impact COR2501.B 31 March 2026 95% Assessment) process and take new processes through leadership and political sign off New templates, training packages and governance processes have been developed for the EIA and SIA. The templates have been piloted with a small number of service areas to test how they work in practice. The item is currently going through the sign off process.
COR2501.C Develop and produce a new Equity, Diversity and Inclusion Strategy 31 March 2026 50%
Capacity constraints have limited progress against the strategy, resulting in slower development than originally anticipated. Competing external priorities have further delayed completion of the final elements of the strategy. These remaining components are now scheduled for completion by late Summer 2026.
COR2502 To refresh the Climate Change strategy and action plan 31 March 2026 100%
Ref. Name Due Status % Complete
COR2502.A Engage with key stakeholders 31 July 2025 100%
Before signing off by Cabinet, the strategy and action were shared with the climate emergency working group, climate cooperators, climate change officers steering group and scrutiny.
Directorate Plan New. v4_2 Page 1 Of 11 Corporate Services Directorate Plan 2025-26 Action Plan Due Date Status % Complete
COR2502.B Finalise strategy and action plan 31 July 2025 100%
The strategy and action plan was approved by leadership team before being submitted to Cabinet in August,
COR2502.C Strategy approved by Cabinet 30 September 2025 100%
The strategy and action plan was approved by Cabinet in August.
COR2503 To finalise the Council’s approach to performance management of the Council Plan 31 March 2026 100%
Ref. Name Due Status % Complete Agree Key Performance Indicators (KPIs) for the Council Plan and agree the structure of the COR2503.A 31 May 2025 100% Annual Report
The key performance indicators were agreed by leadership team before being included in the annual report which was agreed by September's Cabinet.
COR2503.B First draft of the Annual Report to Leadership Team 30 June 2025 100%
The Annual Report was shared with leadership before it was submitted to Cabinet in September.
COR2503.C Redesigned leadership dashboard produced 30 September 2025 100%
The dashboards have been created and are now being implemented and embedded within the reporting cycle.
COR2503.D Annual Report agreed at Cabinet 31 October 2025 100%
The Annual Report was agreed by members in September.
COR2503.E Further proposals drafted for a new corporate performance framework 31 March 2026 100%
Directorate Plan New. v4_2 Page 2 Of 11 Corporate Services Directorate Plan 2025-26 Action Plan Due Date Status % Complete
Proposals have been presented to members, including through scrutiny and a detailed project plan for its implementation is being developed.
COR2504 Review of Recruitment in line with the Council’s People Strategy 31 March 2026 83%
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Append. 1 for Corporate Services Directorate Plan 2025-26: Quarter 4 Performance UpdateReport | 226 KB | DownloadRead as text |
PDF |
Corporate Services Directorate Plan 2025-26: Quarter 4 Performance UpdateReport | 138 KB | Download |
Follow Corporate Overview and Scrutiny Committee at Rochdale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Sep 2026 | People Strategy Progress 2026Resolved – 1. That progress made against the People Strategy 2024-2026 be noted. 2. That the implementation of the re... | Noted | Open |
| 7 Sep 2026 | Finance Update 2026/27 Quarter 1Resolved – 1. That the 2026/27 forecast positions for Revenue, Capital, and the Collection Fund as at the end of June... | Noted | Open |
| 7 Sep 2026 | Children’s Services Q1, 2026/27 Revenue Monitoring UpdateResolved – 1. That the Children’s Services forecasted financial position for 2026/27 at Quarter 1 and related service... | Noted | Open |
| 7 Sep 2026 | Notice of Key Decisions and Private ItemsResolved - That the Notice of Key Decisions and Private Items be noted | Noted | Open |
| 7 Sep 2026 | Work Programme 2026-27 and Action Tracker 2026-27It was agreed that a report on Digital, Data and Technology be submitted to the Committee meeting scheduled for 19 Oc... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.