Resolved :- (1) That funding be made available for the works to the Civic Theatre. (2) That further intrusive survey work be carried out and estimated costs re-assessed and a further report submitted if the revised costs are above the sum approved, (3) That the works be carried out as soon as possible subject to being within funding limits and considering any implications on current service delivery commitments, concentrating on the HIGH priority items. (4) That a further report be submitted to the Cabinet covering alternatives to support the ongoing delivery and development of theatre provision in Rotherham town centre.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
5.1This report requests approval to fund and proceed with works at the Civic Theatre. These works are required as a high priority to enable continued use of the building for up to 10 years. The budget estimate for these works is £540,000. It should be noted that prior to any works being ordered a detailed condition survey should be undertaken to enable more accurate estimating to be undertaken.
Recommendations
6.1It is recommended that:
a) the Council makes funding available for these works,
b) further intrusive survey work be carried out and estimated costs re-assessed. A further report may be required if the revised costs are above the sum approved,
c) the works are carried out as soon as possible subject to being within funding limits and considering any implications on current service delivery commitments, concentrating on the HIGH priority items and
d) a further report be brought to Cabinet covering alternatives to support the ongoing delivery and development of theatre provision in Rotherham town centre. 7. Proposals and Details
7.1In August 2010 an estimate was provided for repairs to the building fabric and mechanical and electrical services at Rotherham Civic Theatre to enable the continued operation of theatre services from the existing facility for a period of ten years. The estimate was based on results of visual surveys only.
7.2These estimates have now been updated with elements prioritised.
7.3A list of high priority items of works has been identified which includes the following: General roof repairs and associated works Structural remedial work and repair Replacement of smoke vents above stage Works to rectify boiler room problems Works to deal with wet/dry rot Mechanical Works Electrical Works
The estimated cost for these items is £266,000.
7.4A further list of items required to enable 10 years life of the theatre buildings is as follows: Works to doors and windows Works to changing room areas Refurbish kitchenette (room 25) Refurbish shower rooms (room 15 & 16) Refurbish back of house WC’s Re-plastering, redecorations and replacement floor coverings where required
The estimated cost for these items is £220,000.
7.5The Council’s Asbestos Register shows that asbestos is present in the building including the Fire Curtain separating the stage and auditorium. The Register is based on a non intrusive survey carried out 18 months previously. An intrusive survey and costs for management/removal of asbestos is estimated to cost £34,000.
7.6The theatre has suffered with drainage flooding on a number of occasions over the last 6 weeks with water entering the under-stage area and dressing rooms. Fortunately no performances were lost. A survey is currently under way but a sum of £10,000 should be allowed for remedial works.
7.7A section of the site boundary wall fronting Doncaster Gate is leaning and will probably need partially re-building. Although further investigation is required to assess the extent of work an allowance of £10,000 should be made for this work.
7.8The total budget estimate for works to bring the Civic Theatre in to a condition to last up to 10 years is £540,000 inclusive of project fees and contingencies.
7.9The above works could be carried out in a 24 week period, concentrating on the High priority works. Although any effect of the works would be minimised as far as possible it is unlikely that works can be carried out without closing the theatre for most of that time. There will therefore be a pressure on the theatre operating budget due to loss of programme and ticket sales.
7.10Cabinet will be aware of the potential for a Cultural Centre on the Forge Island site. It is recommended that a further report is submitted reviewing options for delivery of theatre provision in the town centre.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.