Resolved
Resolved :- (1) That the Director of Audit and Asset Management negotiate the terms of the proposed new lease as set out in the report. (2) That the Director of Legal and Democratic Services complete the necessary documentation.
Cabinet (Pre-Intervention decided this item on Wednesday 2 June 2004. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved :- (1) That the Director of Audit and Asset Management negotiate the terms of the proposed new lease as set out in the report. (2) That the Director of Legal and Democratic Services complete the necessary documentation.
To seek approval for the surrender of the existing lease and the granting of a new lease on the Chislett Centre on the terms reported.
That Cabinet approves:-
1. the Director of Audit and Asset Management negotiates the terms of the proposed new lease as described in the report. 2. the Director of Legal & Democratic Services completes the necessary documentation. 7. Proposals and Details
An earlier review of the buildings and services of the Youth Service within Children’s and Young Peoples Services revealed that a number of buildings were not sustainable within the existing Youth Service budgets.
Chislett Youth and Community Centre, cross hatched red on the attached plans, was indentified as one of those buildings identified for closure or if appropriate be taken over by a suitable Voluntary Organisation. The Kimberworth Park Community Partnership expressed their interest in taking on the management and lease of the building.
In June 2011 consent was obtained under the Council’s adopted Asset Transfer Policy to grant a seven year lease to Kimberworth Park Community Partnership at a nominal £1 per annum, subject to break options in favour of the Council. These break options, in line the adopted policy, protect the Council’s interests should the building be required for service delivery or that the asset be released for a potential capital receipt.
Since June 2011, the Partnership has successfully run the centre for the benefit of the local community, and earlier in the year initiated a local consultation exercise on the future of the Centre. This exercise found there was overwhelming support for the Chislett Centre being developed in ways that meet local needs. Continued support for work with children, young people and their families was seen as a priority, as was developing volunteering opportunities, seen as a way of enabling local people back into employment.
Kimberworth Park Community Partnership has been invited to submit a Stage 2 Big Lottery Reaching Communities – Capital Grant bid after successfully submitting an outline application. The basis of this application will be to upgrade and refurbish the Chislett Centre, in order establish the Centre as a ‘community hub’ for the delivery of local services and activities, developed and managed by local people and aspiring to the aims identified during the consultation exercise. The partnership is seeking initial funds of £365,000, which could rise to £492,000 by the end of the application process, which will increase the overall lifespan of the building.
In order to qualify for the bid, the Big Lottery requires that a lease of 21 years be in place without any break options before the bid is accepted. This is a requirement to protect the grant provided and ensure that the benefits of the monies are fully realised.
The granting of such a lease without the break options is a diversion from the adopted Asset Transfer Policy, and therefore requires Cabinet Approval to grant the required lease. It is therefore recommended that on this occasion due to the level of investment that is sought, and the community gain that the refurbishment will deliver, then the lease be granted without breaks for 21 years. 8. Finance
As per the adopted Asset Transfer Policy, all legal professional fees incurred by the Council in connection with the surrender and granting of the lease are to be met by Kimberworth Park Community Partnership, which has been estimated to be in the region of £500.
Estimated cost of surrender and grant of new lease
Revenue Costs: Professional Fees £150 Marketing – N/A Legal Services - £350 Maintenance costs until disposal – N/A
9. Risks and Uncertainties
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Rationalisation of the Property Portfolio: Chislett Youth and Community CentreReport | 6 pages | DownloadRead as text |
Follow Cabinet (Pre-Intervention at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Jun 2004 | IntroductionResolved :- (1) That a variation to the Standing Orders to allow for filming in the Council Chamber be approved. (2) ... | Approved | Open |
| 2 Jun 2004 | Questions from Members of the Public.It was agreed to provide a detailed answer in writing. | Agreed | Open |
| 2 Jun 2004 | Awards- That Members and staff involved be congratulated on these achievements. | Decided | Open |
| 2 Jun 2004 | John GomersallResolved :- That the best wishes of the Council be forwarded to John for a speedy recovery . | Decided | Open |
| 2 Jun 2004 | Wath Comprehensive SchoolResolved :- (1) That everyone involved in developing the new premises be congratulated on this outstanding success an... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.