Resolved
Resolved :- That the report be received and the contents noted. (2) Recommended :- That the 2013/14 to 2015/16 Capital Programme be approved.
Cabinet (Pre-Intervention noted this item on Wednesday 2 June 2004. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved :- That the report be received and the contents noted. (2) Recommended :- That the 2013/14 to 2015/16 Capital Programme be approved.
The purpose of this report is to provide details of the current forecast outturn for the 2012/13 programme and enable the Council to review the capital programme for the financial years 2013/14 to 2015/16.
CABINET IS ASKED TO:
NOTE THE CONTENTS OF THIS REPORT; AND
RECOMMEND THE APPROVAL OF THE UPDATED 2012/13 TO 2015/16 CAPITAL PROGRAMME BY FULL COUNCIL. 7 Proposals and Details
7.1Background - The Capital Programme 2012/13 to 2015/16
The budget process that led to the original Capital Programme for 2012/13 to 2015/16 ensured that the Council’s capital investment plans were aligned with its strategic priorities and vision for Rotherham.
In order to maintain that strategic link, and make best use of the capital resources available to the Council, it is important that the programme is kept under regular review and where necessary revisions are made. This programme was initially reviewed in July 2012, following the finalisation of the 2011/12 outturn capital expenditure and financing, and again in October 2012. In addition the 2013/14 to 2015/16 programme was reviewed by Members in February 2013.
This review reflects the changes to the Council’s capital investment programme since the last report, which are incorporated into the Directorate summary table presented below. A detailed analysis of the programme for each Directorate is attached at appendices 1 to 4.
2012/13 2012/13 2013/14 2013/14 2014/15 2014/15 2015/16 2015/16 Revised Variance Estimate Variance Estimate Variance Estimate Variance Estimate from from from from Last Last Last Last Report Report Report Report
Directorate £m £m £m £m £m £m £m £m Children & Young 14.986 -6.200 15.178 +5.272 3.357 -0.096 3.007 +1.157 People’s Service Environment & 19.234 +0.610 18.647 +1.693 6.962 0.000 0.650 0.000 Development Services Neighbourhoods 23.019 -2.407 35.553 +1.906 29.288 0.000 29.481 0.000 & Adult Services Resources 10.744 -0.035 1.260 0.000 1.273 0.000 0.000 0.000
TOTAL 67.983 -8.032 70.638 +8.871 40.880 -0.096 33.138 +1.157
7.2Children and Young People’s Services Capital Programme 2012/13 to 2015/16
The revised proposed spend for 2012/13 is £14.986m, with a further £21.542m of investment in the following years of the current programme.
A copy of the current full programme is attached to this report at Appendix 1. Commentary on the main aspects of the programme and the nature of the spend is given below. Primary Schools
Spend on Primary Schools is expected to be £4.451m in 2012/13, with a further £3.282m of planned spend in 2013/14 to 2015/16. The major investments to note in this area are:
• Work is underway on the Maltby Lilly Hall new school project (£1.954m in 2012/13) which will create six new classrooms together with associated facilities and external play areas. In addition re- roofing work is being carried out which also requires the removal of asbestos, which was discovered when the project commenced. As a result, commencement of the work was delayed and has since been further interrupted due to adverse weather resulting in a re-profiling of the scheme. Completion is still expected to be in September 2013.
• Work was completed in April 2012, providing Wentworth C of E School (£0.202m in 2012/13) with a two storey extension, including disabled toilets, an additional class room, store rooms and other resource facilities.
• Work was also completed, in October 2012, on the Thornhill Primary School (£0.785m in 2012/13) extension which created Special Educational Needs facilities and a dining room extension to accommodate increased pupil numbers.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Programme Monitoring Report 2012/13: 2015/16Report | 13 pages | DownloadRead as text |
PDF |
Capital monitoring appendices: April CabinetReport | 9 pages | Download |
Follow Cabinet (Pre-Intervention at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Jun 2004 | IntroductionResolved :- (1) That a variation to the Standing Orders to allow for filming in the Council Chamber be approved. (2) ... | Approved | Open |
| 2 Jun 2004 | Questions from Members of the Public.It was agreed to provide a detailed answer in writing. | Agreed | Open |
| 2 Jun 2004 | Awards- That Members and staff involved be congratulated on these achievements. | Decided | Open |
| 2 Jun 2004 | John GomersallResolved :- That the best wishes of the Council be forwarded to John for a speedy recovery . | Decided | Open |
| 2 Jun 2004 | Wath Comprehensive SchoolResolved :- (1) That everyone involved in developing the new premises be congratulated on this outstanding success an... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.