Capital Programme Outturn 2013/14 and Updated Estimates 2014/15 to 2016/17

Noted Executive 2 papers

Cabinet (Pre-Intervention noted this item on Wednesday 2 June 2004. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

Resolved :- that the 2013/14 capital outturn position be noted. (2) Recommend :- That the updated 2014/15 to 2016/17 capital programme be approved.
Word for word from the decision Rotherham published for this meeting. Source: moderngov.rotherham.gov.uk

Follow this further

Built from Rotherham's papers

What the report saysPro

Report to Cabinet (Pre-Intervention, 14 pages

Summary

The purpose of this report is to report the capital outturn position for the 2013/14 financial year and recommend for approval changes to the programme for the financial years 2014/15 to 2016/17. These changes have resulted from the 2013/14 outturn and scheme changes since the overall programme was agreed in March 2014, as part of the budget setting process.

Recommendations

CABINET IS ASKED TO:

NOTE THE 2013/14 CAPITAL OUTTURN POSITION; AND

RECOMMEND THE APPROVAL OF THE UPDATED 2014/15 TO 2016/17 CAPITAL PROGRAMME BY FULL COUNCIL. 7 Proposals and Details

7.1Background - The Capital Programme

The finalisation of the 2013/14 capital expenditure and financing outlined in this report, provides an opportunity to reflect and update the future years’ programme that was previously approved by Council in March, for the financial years 2014/15 to 2016/17.

The current economic climate and the on-going impact of the Government’s austerity measures require that the capital programme is subject to continual oversight, and if necessary, revision, to ensure that the Council’s capital investment plans are aligned with strategic priorities and maximise the value from the limited capital resources available.

The financial implications of the Programme are reflected in the Council’s Medium Term Financial Strategy (MTFS) and Treasury Management and Investment Strategy.

For 2013/14 the Council’s capital investment into the regeneration and enhanced infrastructure of the Borough was £71.769m. The profile of this investment and the updated future expenditure plans are reflected in the Directorate summary table presented below. A detailed copy of the programme for each Directorate is attached at Appendices 1 to 4.

2013/14 2013/14 2014/15 2014/15 2015/16 2015/16 2016/17 2016/17 Outturn Variance Estimate Variance Estimate Variance Estimate Variance from from from from Last Last Last Last Report Report Report Report

Directorate £m £m £m £m £m £m £m £m Children & Young 20.961 -1.340 13.899 +2.756 5.334 -0.800 2.694 -0.390 People’s Service Environment & 18.446 -1.161 28.746 +6.727 8.159 0 1.200 0 Development Services Neighbourhoods 30.305 -2.712 37.330 +1.445 28.014 0 28.062 0 & Adult Services Resources 2.057 -0.802 2.142 +0.762 0.470 0 0.470 0

TOTAL 71.769 -6.015 82.117 +11.690 41.977 -0.800 32.426 -0.390

The updated programme has been prepared in light of the capital resources known to be available to the Council over these financial years, and estimated on a prudent basis.

The Council is continuing to undertake a comprehensive review of its assets and buildings portfolio, with the aim to rationalise both its operational and non- operational asset holdings, which may contribute both a future capital receipt and a revenue saving. 7.2 Children and Young People’s Services Capital Programme 2013/14 to 2016/17

The 2013/14 outturn was £20.961m, with total proposed expenditure over the period of the future programme of £21.927m, including new schemes at several schools across the Borough required to address the increase in pupil numbers, including the central Rotherham catchment areas where the problem is particularly acute.

For 2013/14 the major capital investments into the Council’s educational and learning facilities across the borough were:

Primary Schools

• The extension and refurbishment at Maltby Lilly Hall Primary school is now complete (£1.992m in 2013/14). The work has created six new classrooms together with associated facilities and external play areas. Budget, previously expected to not be required, has had to be reinstated to enable the subsequent discovery of asbestos to be properly managed as well as delays to roofing works caused by the wet winter weather conditions. £54k of outstanding invoices will be settled in 2014/15.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme Outturn 2013/14 and Updated Estimates 2014/15 to 2016/17Report 14 pages DownloadRead as text
PDF
Capital monitoring appendices: June: Base Data (v1)Report 11 pages Download

At this meeting

Whole meeting

On this subject at Rotherham

Search all
  1. Capital Programme Outturn 2013/14 and Updated Estimates 2014/15 to 2016/17This decision
  2. Asset Management Estimates and Capital Programme Audit UpdateNoted
  3. Recommendation from cabinet - financial outturn 2020/21 and capital programmeNoted
  4. Transportation Capital ProgrammeAgreed
  5. Highways Capital ProgrammeAgreed
  6. Highways Capital ProgrammeAgreed

More from Rotherham Cabinet (Pre-Intervention

All decisions
MeetingDecisionOutcome
2 Jun 2004 IntroductionResolved :- (1) That a variation to the Standing Orders to allow for filming in the Council Chamber be approved. (2) ... Approved Open
2 Jun 2004 Questions from Members of the Public.It was agreed to provide a detailed answer in writing. Agreed Open
2 Jun 2004 Awards- That Members and staff involved be congratulated on these achievements. Decided Open
2 Jun 2004 John GomersallResolved :- That the best wishes of the Council be forwarded to John for a speedy recovery . Decided Open
2 Jun 2004 Wath Comprehensive SchoolResolved :- (1) That everyone involved in developing the new premises be congratulated on this outstanding success an... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies