Resolved
Resolved :- that the 2013/14 capital outturn position be noted. (2) Recommend :- That the updated 2014/15 to 2016/17 capital programme be approved.
Cabinet (Pre-Intervention noted this item on Wednesday 2 June 2004. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved :- that the 2013/14 capital outturn position be noted. (2) Recommend :- That the updated 2014/15 to 2016/17 capital programme be approved.
The purpose of this report is to report the capital outturn position for the 2013/14 financial year and recommend for approval changes to the programme for the financial years 2014/15 to 2016/17. These changes have resulted from the 2013/14 outturn and scheme changes since the overall programme was agreed in March 2014, as part of the budget setting process.
CABINET IS ASKED TO:
NOTE THE 2013/14 CAPITAL OUTTURN POSITION; AND
RECOMMEND THE APPROVAL OF THE UPDATED 2014/15 TO 2016/17 CAPITAL PROGRAMME BY FULL COUNCIL. 7 Proposals and Details
7.1Background - The Capital Programme
The finalisation of the 2013/14 capital expenditure and financing outlined in this report, provides an opportunity to reflect and update the future years’ programme that was previously approved by Council in March, for the financial years 2014/15 to 2016/17.
The current economic climate and the on-going impact of the Government’s austerity measures require that the capital programme is subject to continual oversight, and if necessary, revision, to ensure that the Council’s capital investment plans are aligned with strategic priorities and maximise the value from the limited capital resources available.
The financial implications of the Programme are reflected in the Council’s Medium Term Financial Strategy (MTFS) and Treasury Management and Investment Strategy.
For 2013/14 the Council’s capital investment into the regeneration and enhanced infrastructure of the Borough was £71.769m. The profile of this investment and the updated future expenditure plans are reflected in the Directorate summary table presented below. A detailed copy of the programme for each Directorate is attached at Appendices 1 to 4.
2013/14 2013/14 2014/15 2014/15 2015/16 2015/16 2016/17 2016/17 Outturn Variance Estimate Variance Estimate Variance Estimate Variance from from from from Last Last Last Last Report Report Report Report
Directorate £m £m £m £m £m £m £m £m Children & Young 20.961 -1.340 13.899 +2.756 5.334 -0.800 2.694 -0.390 People’s Service Environment & 18.446 -1.161 28.746 +6.727 8.159 0 1.200 0 Development Services Neighbourhoods 30.305 -2.712 37.330 +1.445 28.014 0 28.062 0 & Adult Services Resources 2.057 -0.802 2.142 +0.762 0.470 0 0.470 0
TOTAL 71.769 -6.015 82.117 +11.690 41.977 -0.800 32.426 -0.390
The updated programme has been prepared in light of the capital resources known to be available to the Council over these financial years, and estimated on a prudent basis.
The Council is continuing to undertake a comprehensive review of its assets and buildings portfolio, with the aim to rationalise both its operational and non- operational asset holdings, which may contribute both a future capital receipt and a revenue saving. 7.2 Children and Young People’s Services Capital Programme 2013/14 to 2016/17
The 2013/14 outturn was £20.961m, with total proposed expenditure over the period of the future programme of £21.927m, including new schemes at several schools across the Borough required to address the increase in pupil numbers, including the central Rotherham catchment areas where the problem is particularly acute.
For 2013/14 the major capital investments into the Council’s educational and learning facilities across the borough were:
Primary Schools
• The extension and refurbishment at Maltby Lilly Hall Primary school is now complete (£1.992m in 2013/14). The work has created six new classrooms together with associated facilities and external play areas. Budget, previously expected to not be required, has had to be reinstated to enable the subsequent discovery of asbestos to be properly managed as well as delays to roofing works caused by the wet winter weather conditions. £54k of outstanding invoices will be settled in 2014/15.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Programme Outturn 2013/14 and Updated Estimates 2014/15 to 2016/17Report | 14 pages | DownloadRead as text |
PDF |
Capital monitoring appendices: June: Base Data (v1)Report | 11 pages | Download |
Follow Cabinet (Pre-Intervention at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Jun 2004 | IntroductionResolved :- (1) That a variation to the Standing Orders to allow for filming in the Council Chamber be approved. (2) ... | Approved | Open |
| 2 Jun 2004 | Questions from Members of the Public.It was agreed to provide a detailed answer in writing. | Agreed | Open |
| 2 Jun 2004 | Awards- That Members and staff involved be congratulated on these achievements. | Decided | Open |
| 2 Jun 2004 | John GomersallResolved :- That the best wishes of the Council be forwarded to John for a speedy recovery . | Decided | Open |
| 2 Jun 2004 | Wath Comprehensive SchoolResolved :- (1) That everyone involved in developing the new premises be congratulated on this outstanding success an... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.