Resolved :- (1) That the financial support towards the regeneration of Rotherham High Street buildings as detailed in Option 2 of this report being the provision of a capital loan facility of up to £300,000 and the payment of a capital grant of £190,000 be approved. (2) That responsibility for drawing up the financial agreement on appropriate terms and conditions be delegated to the Director of Financial Services and Responsible Legal Officer. (3) That ... view the full minutes text for item 32.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
To consider a formal request from a local businessman, [name removed], for
1) an additional long term capital finance loan from the Council of £300,000 to bring the re-development of No’s 25 – 29 High Street ‘The Three Cranes’; and No.29a High Street, a former Georgian Town House, to a successful conclusion.
2) a grant of £190,000 from the Council to help bridge the funding shortfall which has arisen through the unforeseen delays and additional costs incurred by [name removed] in delivering this complex heritage project.
Recommendations
Cabinet is asked to :- (A) Approve the financial support towards the regeneration of Rotherham High Street buildings as detailed in option 2 of this report being the provision of a capital loan facility of up to £300,000 and the payment of a capital grant of £190,000.
(B) Delegate responsibility for drawing up the financial agreement on appropriate terms and conditions to the Director of Financial Services and Responsible Legal Officer. 7. Background
On 7th September 2011 and 27th November 2013, Cabinet approved long term loan facilities totalling £0.89m over 25 years to a local business man, [name removed], to restore buildings on the High Street in support of the Council’s corporate priority of creating a vibrant Town Centre.
The loan facilities were to facilitate the purchase and subsequent re- development of No’s 17,19 and 21 High Street along with the following listed buildings: No’s 25 – 29 High Street ‘The Three Cranes’; No.29a High Street a former Georgian Town House; and The George Wright Building.
Development by a private sector owner was necessary to lever in Heritage Lottery Funding (HLF) to meet the cost of additional works to the listed buildings.
[name removed] has since drawn down on the loan facility in full and has successfully completed the redevelopment of No’s 17, 19 and 21. Work has also commenced on the three Grade 2 Listed buildings, nos 25-29 (Alfonsos and Three Cranes) and the George Wright building and the work on these properties is scheduled to be completed by the end of December 2014.
Case for Further Support
There have however, been significant delays on the redevelopment of the three listed buildings. This has arisen due to delays in securing the HLF funding, the severe winters causing additional damage to the fabric of the building, additional unforeseen structural issues and subsequent additional costs associated with specialist archaeological and architects fees. In addition extra “abnormals” such as unforeseen works to the basement of 29 High Street and the party walls to 25/27 and 29 High Street have led to further costs that were not anticipated at the start of the project. The result is that [name removed] is experiencing a funding shortfall in order to complete the full restoration of these important historical buildings.
Options
Option 1 – RMBC do not provide assistance
Without additional support [name removed] will be unable to achieve a “fit out” of these buildings which in turn will hamper his ability to let these units and this in turn will exacerbate his ability to repay his existing loan commitments to the Council. It is therefore deemed prudent for the Council to continue its commitment to this important High Street regeneration project and ensure its ongoing success.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.